STEVENSON OPERATIONS MANAGEMENT W/CONNEC
14th Edition
ISBN: 9781264578306
Author: Stevenson
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 5, Problem 11P
a)
Summary Introduction
To determine: The number of machines of each type required to handle the demand and its capacity and the machine that would have lower total cost.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
b)
Summary Introduction
To determine: The machine that would have lower total cost considering operating cost.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A manager must whether to buy machine A or B. Machine costs are as follows: A $52,000 each; B $100,000 each
Product forecast and processing times on the machines are as follows
Processing Time per unit (minutes)
Product
Annual Demand
A
B
1
8,000
2
18,000
3
10,000
Assume that only purchasing costs are being considered. Which machine would have the lowest purchase cost and how many
of that machine would be need? Machines operate 8 hours a day 250 days per year.
The machines differ in hourly operation costs. The A machines have an hourly operating cost of $12 each and B machines have
an hourly operating cost of $30 each. What is the operating cost per year and which alternative should be selected to minimize
total cost (for the first year) while satisfying the processing requirements?
Edit Format Table
12pt v
Paragraph v
BIUA ev T?v||:
MacBook Air
esc
80
888
DII
F1
F2
F3
F4
F5
F6
F7
FR
@
#
$
%
1
2
3
4
5
7
8.
Q
W
E
R
T
Y
A
S
D
F
G
< CO
A manager must decide which type of machine to buy, A, B, or C. Machines costs are as follows:
Machine
Cost
A
$40,000
B
$30,000
C
$80,000
Product forecast, processing times on the machines, and setup times are as follows:
Processing Time Per Unit (minutes)
Product
Annual Demand
A
B
C
Setup Times (minutes)
Production Lots (units)
1
16,000
3
4
2
20
200
2
12,000
4
5
3
35
100
3
6,000
5
6
3
60
50
4
30,000
2
4
1
15
500
Machines operate 10 hours a day, 250 days a year. The manager wants to have a capacity cushion of 10%.
a. Assume that only purchasing costs are being considered. Which machines would have the lowest total cost, and how many of that machines would be needed?
b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $11 each, B machines have an hourly operating cost of $10 each, and C machines have an hourly operating cost of $12 each. Which alternative would…
Problem 5-11 (Algo)
A manager must decide which type of
machine to buy, A, B, or C. Machine costs (per
individual machine) are as follows:
Machine
A
B
C
Cost
$80,000
$70,000
$40,000
Product forecasts and processing times on
the machines are as follows:
Annual
Product Demand
1
25,000
2 22,000
3
20,000
4
9,000
PROCCESSING TIME PER
UNIT (minutes)
AS335
4
1
6
Click here for the Excel Data File
U2462
C
Chapter 5 Solutions
STEVENSON OPERATIONS MANAGEMENT W/CONNEC
Ch. 5.8 - Explain the meaning of the phrase Hours versus...Ch. 5.8 - Prob. 1.2RQCh. 5.8 - Prob. 1.3RQCh. 5.8 - Prob. 1.4RQCh. 5.8 - Prob. 1.5RQCh. 5.S - Prob. 1DRQCh. 5.S - Prob. 2DRQCh. 5.S - Explain the term bounded rationality.Ch. 5.S - Prob. 4DRQCh. 5.S - Prob. 5DRQ
Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost $50,000 A B $40,000 C $70,000 Product forecasts and processing times on the machines are as follows: PROCCESSING TIME PER UNIT (minutes) Annual Product Demand 1 2 3 4 18,000 25,000 15,000 9,000 A 1 5 4 5 A B C B Click here for the Excel Data File 6531 Total processing time in minutes per machine: a. Assume that only purchasing costs are being considered. Compute the total processing time required for each machine type to meet demand, how many of each machine type would be needed, and the resulting total purchasing cost for each machine type. The machines will operate 8 hours a day, 220 days a year. (Enter total processing times as whole numbers. Round up machine quantities to the next higher whole number. Compute total purchasing costs using these rounded machine quantities. Enter the resulting total purchasing cost as a whole number.) C 2 1 2 6arrow_forwardA manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost A B C Product forecasts and processing times on the machines are as follows: $80,000 $70,000 $40,000 Annual Product Demand 1 25,000 2 22,000 3 20,000 4 9,000 A B PROCCESSING TIME PER UNIT (minutes) A B C A 5 3 3 5 B 4 1 1 Click here for the Excel Data File Total processing time in minutes per machine: 296,000 196,000 6 a. Assume that only purchasing costs are being considered. Compute the total processing time required for each machine type to meet demand, how many of each machine type would be needed, and the resulting total purchasing cost for each machine type. The machines will operate 10 hours a day, 250 days a year. (Enter total processing times as whole numbers. Round up machine quantities to the next higher whole number. Compute total purchasing costs using these rounded machine quantities. Enter the resulting total purchasing cost as a whole…arrow_forwardThe next TWO questions refer to the following data. (This data may not be the same as in the ClearEyes Cataracts Clinic case.) Receptionist PSR Technician Staff Surgeon Cleaner Total annual minutes required per job title 29,450 353,268 212,882 119,944 51,820 Number workers by job title 1 4 3 1 1 Non-surgeons are available 115,200 minutes per year and surgeons are available 100,800 minutes per year. The average capacity utilization of the staff surgeon is: Group of answer choices 84.0 percent 91.5 percent 100.0 percent 104.1 percent 118.99 percentarrow_forward
- A manager must decide which type of machine to buy, A or B. Machine costs are as follows: Machine Cost A $110,000 40,000 Product forecasts and processing times on the machines are as follows:arrow_forwardA manager must decide how many machines of a certain type to purchase. Each machine can process 100 customers per day. One machine will result in a fixed cost of $2,100 per day, while two machines will result in a fixed cost of $3,900 per day. Variable costs will be $17 per customer, and revenue will be $45 per customer. a. Determine the break-even point for each range. (Round your answers to the next whole number.) One machine Two machines 4,500 b. If estimated demand is 90 to 120 customers per day, how many machines should be purchased?arrow_forwardWhat is CAPACITY REQUIREMENTS FORECASTING?arrow_forward
- Determine the utilization and the efficiency for each of these situations:a. A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day.b. A furnace repair team that services an average of four furnaces a day if the design capacity is six furnaces a day and the effective capacity is five furnaces a day.c. Would you say that systems that have higher efficiency ratios than other systems will always have higher utilization ratios than those other systems? Explain.arrow_forward11. A manager must decide which type of machine to buy, A, B, or C. Machine costs are as follows: Machine A B C Product forecasts and processing times on the machines are as follows: PROCCESSING TIME PER UNIT (minutes) Product 1 2 3 4 Cost $40,000 $30,000 $80,000 Annual Demand 16,000 12,000 6,000 30,000 A 3452 2 B 4 4 6 2 C 2 3 4 1 a. Assume that only purchasing costs are being considered. Which machine would have the low- est total cost, and how many of that machine would be needed? Machines operate 10 hours a day, 250 days a year. b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $10 each, B machines have an hourly oper- ating cost of $11 each, and C machines have an hourly operating cost of $12 each. Which alternative would be selected, and how many machines, in order to minimize total cost while satisfying capacity processing requirements?arrow_forwardJ 1 ue K Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $5,000. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 75% Total Time 5.589 Unit Time .477 80% Total Time 6.315 Unit Time .583 85% Total Time 7.116 Xarrow_forward
- 1. A 32,000-seat baseball stadium is used 17 times for games, concerts, and graduation ceremonies. Each event averages five hours and assumes the stadium is full for each event. The stadium is available 365 days a year from 7 am to midnight. (Notice: the focus is stadium “seat” utilization). a. What is stadium (seat) utilization using Equation 7.1 (pg 146)? (Show your calculations) b. If in the above scenario, the utilization was 75% during the 17 events, but there were 2 additional events that garnered 100% utilization, would this be an increase or decrease in overall utilization from the result in “a”? (Show calculations) c. As an Operations Manager how would you improve utilization at the stadium? Provide at least three optional improvement plans with details. EQUATION 7.1 is : UTILIZATION (U) = Resources used / resources avaliable EQUATION 7.2 is: UTILIZATION (U) = Demand Rate / [Service Rate * Number of Servers]arrow_forwardA computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors should the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain .arrow_forwardWhat is the fundamental distinction between design capacity and effective capacity? Provide a brief examplearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,