Explanation of Solution

Finding optimal solution:

The demand for sail boats during each of the next four quarters is;

First quarter-40 sailboats

Second quarter-60 sailboats

Third quarter- 75 sailboats

Fourth quarter- 25 sailboats

An inventory of 10 sailboats is at the beginning of the first quarter. Also, it is assumed that sailboats manufactured during a quarter can be used to meet demand for that quarter.

Also, during each quarter, Sailco can produce up to 40 sailboats with total cost of $400 per sailboat.

Additional sailboats with overtime labor can be produced at a total cost of $450 per sailboat.

A carrying cost of $20 per sailboat is incurred at the end of each quarter. A production schedule to minimize the sum of production and inventory costs during the next four quarters using linear programming is to be formulated and using the solver add in excel, the number of sailboats during each quarter is to be determined.

Let,

xt= Number of sailboats produced by regular time labour (at $400 pre boat) during quarter t where t=1,2,3,4.

yt= Number of sailboats produced by overtime time labour (at $450 per boat) during quarter t where, t=1,2,3,4.

it= Number of sailboats on hand at the end of quarter t where, t=1,2,3,4.

Sailco’s total cost can be determined as follows.

 Cost=Cost of producing regular time boats + Cost of producing overtime boats + inventory costs=400(x1+x2+x3+x4)+450(y1+y2+y3+y4)+20(i1+i2+i3+i4)

Since the total cost to be minimized, the objective function of Sailco is given below,

Minimize, z=400(x1+x2+x3+x4)+450(y1+y2+y3+y4)+20(i1+i2+i3+i4)

The constraints are given below,

For each period’s regular time production will not exceed 40. So the below given constraints are obtained.

x140x240x340x440

Also suppose that,

Inventory at the end of quarter t= Inventory at the end of quarter(t-1)                                                     +quarter t production – quarter t demand

This means,

it=it-1+(xt+yt)-di where, (t=1,2,3,4)

When submitting the values, the following constraints are obtained.

i1=10+x1+y1-40i2=i1+x2+y2-60i3=i2+x2+y3-75i4=i3+x4+y4-25

Also, it(t=1,2,3,4) implies that each quarter’s demand is met on time and xt0 implies that the production levels are positive at all time

Blurred answer
Students have asked these similar questions
Please solve and answer the question correctly please. Thank you!!
Please solve and answer the question correctly please. Thank you!!
W AutoSave Off File Home Insert Draw Design Assignment_1[1] - Protected... ■ Saved V > Search Layout References Mailings Review View Help QuillBot RefWorks - RCM PROTECTED VIEW Be careful-files from the Internet can contain viruses. Unless you need to edit, it's safer to stay in Protected View. Enable Editing PR Comments Viewing Share × 2. The following state transition table is a simplified model of process management, with the labels representing transitions between states of READY, RUN, BLOCKED, and NONRESIDENT. READY RUN BLOCKED NONRESIDENT READY RUN - 1 - 5 BLOCKED 2 4 3 - 6 Give an example of an event that can cause each of the above transitions. Draw a diagram if that helps. (5) Page 2 of 4 20 of 278 words Text Predictions: On 64 f W Focus + 170% ENG US 17:13 2025/03/24

Chapter 4 Solutions

OPERATIONS RESEARCH >INTERNATIONAL EDITI

Ch. 4.5 - Prob. 1PCh. 4.5 - Prob. 2PCh. 4.5 - Prob. 3PCh. 4.5 - Prob. 4PCh. 4.5 - Prob. 5PCh. 4.5 - Prob. 6PCh. 4.5 - Prob. 7PCh. 4.6 - Prob. 1PCh. 4.6 - Prob. 2PCh. 4.6 - Prob. 3PCh. 4.6 - Prob. 4PCh. 4.7 - Prob. 1PCh. 4.7 - Prob. 2PCh. 4.7 - Prob. 3PCh. 4.7 - Prob. 4PCh. 4.7 - Prob. 5PCh. 4.7 - Prob. 6PCh. 4.7 - Prob. 7PCh. 4.7 - Prob. 8PCh. 4.7 - Prob. 9PCh. 4.8 - Prob. 1PCh. 4.8 - Prob. 2PCh. 4.8 - Prob. 3PCh. 4.8 - Prob. 4PCh. 4.8 - Prob. 5PCh. 4.8 - Prob. 6PCh. 4.10 - Prob. 1PCh. 4.10 - Prob. 2PCh. 4.10 - Prob. 3PCh. 4.10 - Prob. 4PCh. 4.10 - Prob. 5PCh. 4.11 - Prob. 1PCh. 4.11 - Prob. 2PCh. 4.11 - Prob. 3PCh. 4.11 - Prob. 4PCh. 4.11 - Prob. 5PCh. 4.11 - Prob. 6PCh. 4.12 - Prob. 1PCh. 4.12 - Prob. 2PCh. 4.12 - Prob. 3PCh. 4.12 - Prob. 4PCh. 4.12 - Prob. 5PCh. 4.12 - Prob. 6PCh. 4.13 - Prob. 2PCh. 4.14 - Prob. 1PCh. 4.14 - Prob. 2PCh. 4.14 - Prob. 3PCh. 4.14 - Prob. 4PCh. 4.14 - Prob. 5PCh. 4.14 - Prob. 6PCh. 4.14 - Prob. 7PCh. 4.16 - Prob. 1PCh. 4.16 - Prob. 2PCh. 4.16 - Prob. 3PCh. 4.16 - Prob. 5PCh. 4.16 - Prob. 7PCh. 4.16 - Prob. 8PCh. 4.16 - Prob. 9PCh. 4.16 - Prob. 10PCh. 4.16 - Prob. 11PCh. 4.16 - Prob. 12PCh. 4.16 - Prob. 13PCh. 4.16 - Prob. 14PCh. 4.17 - Prob. 1PCh. 4.17 - Prob. 2PCh. 4.17 - Prob. 3PCh. 4.17 - Prob. 4PCh. 4.17 - Prob. 5PCh. 4.17 - Prob. 7PCh. 4.17 - Prob. 8PCh. 4 - Prob. 1RPCh. 4 - Prob. 2RPCh. 4 - Prob. 3RPCh. 4 - Prob. 4RPCh. 4 - Prob. 5RPCh. 4 - Prob. 6RPCh. 4 - Prob. 7RPCh. 4 - Prob. 8RPCh. 4 - Prob. 9RPCh. 4 - Prob. 10RPCh. 4 - Prob. 12RPCh. 4 - Prob. 13RPCh. 4 - Prob. 14RPCh. 4 - Prob. 16RPCh. 4 - Prob. 17RPCh. 4 - Prob. 18RPCh. 4 - Prob. 19RPCh. 4 - Prob. 20RPCh. 4 - Prob. 21RPCh. 4 - Prob. 22RPCh. 4 - Prob. 23RPCh. 4 - Prob. 24RPCh. 4 - Prob. 26RPCh. 4 - Prob. 27RPCh. 4 - Prob. 28RP
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole