a)

Summary Introduction

To draw: A process flow diagram for this process.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  1

Process flow diagram:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  2

b)

Summary Introduction

To determine: The capacity at the resource “Apply a lid”.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  3

Calculation of capacity:

Capacity=Number of machines×Seconds per hourSeconds per bottle=1×3,6003=1,200 bottles

The capacity is 1,200 bottles.

c)

Summary Introduction

To determine: The bottleneck in the process.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  4

Determination of bottleneck:

The process step with the longest processing time “seconds per bottle” is the bottleneck in the process. Packaging has the highest time of 3 seconds per bottle.

Hence, the bottleneck is Packaging.

d)

Summary Introduction

To determine: The flow rate.

d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  5

Determination of flow rate:

Flow rate=Seconds per hourBottleneck capacity=3,6004=900 bottles

The flow rate is 900 bottles.

e)

Summary Introduction

To determine: The utilization of resource “Apply a lid”

e)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  6

Calculation of utilization:

Utilization=Flow rateCapacity×100=900Number of machines×Seconds per hourSeconds per bottle×100=9001×3,6003×100=9001,200×100=75%

The utilization is 75%.

f)

Summary Introduction

To determine: The utilization of bottling.

f)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  7

Calculation of utilization:

Utilization=Flow rateCapacity×100=Number of machinesSeconds per minuteDemand per minuteSeconds per bottle×100=160121×100=151×100=20%

The utilization is 20%.

g)

Summary Introduction

To determine: The cycle time of the process.

g)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  8

Calculation of cycle time:

The demand is constrained and has a flow rate of

Flow rate=Number of machinesSeconds per minuteDemand per minute=16012=0.20 bottle per second

Cycle time=1Flow rate=10.2=5 seconds

The cycle time is 5 seconds.

h)

Summary Introduction

To determine: The time taken to produce 500 bottles.

h)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATION MANAGEMENT, Chapter 3, Problem 4PA , additional homework tip  9

Calculation of time taken to produce 500 bottles:

Time taken=(4×5)+[(500-1)×5]=20+(499×5)=20+2,495=2,515 seconds

The time taken to produce 500 bottles is 2,515 seconds.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The Clothing Shack is an online retailer of men's, women's, and children's clothing. The company has been in business for four years and makes a modest profit from its online sales. However, in an effort to compete successfully against online retailing heavyweights, the Clothing Shack's marketing director, Makaya O'Neil, has determined that the Clothing Shack's marketing information systems need improvement. Ms. O'Neil feels that the Clothing Shack should begin sending out catalogs to its customers, keep better track of its customer's buying habits, perform target marketing, and provide a more personalized shopping experience for its customers. Several months ago, Ms. O'Neil submitted a systems service request (SSR) to the Clothing Shack's steering committee. The committee unanimously approved this project. You were assigned to the project at that time and have since helped your project team successfully complete the project initiation and planning phase. Your team is now ready to move…
b-1.   Activity ES EF LS LF Slack 1           2           3           4           5           6           7           8           9           b-2. Identify the critical activities, and determine the duration of the project. The critical activities are                 .
The forecast for each week of a four-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are follows: Week Customer Order 1 52 35 20 12 Use a production lot size of 75 units and no beginning Inventory. Determine the available-to-promise (ATP) quantities for each period. Note: Leave no cells blank - be certain to enter "0" wherever required. Period ATP 1 2 3
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,