Concept explainers
The time required to complete the filling and emptying cycle for a refuse collection vehicle.
Answer to Problem 3.1P
The time required to complete the filling and emptying cycle for a refuse collection vehicle is
Explanation of Solution
Given:
The two container of
The refuse is picked up twice per week.
The truck has a compaction ratio of
The pickup time is
The time spend by truck on disposal is
The time spend to reach the disposal site is
Calculation:
Assume the volume of the truck as
Calculate the volume of refuse produced by each resident in
Here, the volume of refuses produces by each resident is
Write the expression to calculate the compacted volume by the truck’s compacting ratio.
Here, the compacted volume is
Substitute
Write the expression to calculate the number of loads done by the truck.
Here, the number of loads done by the truck is
Substitute
Write the expression to calculate the total time of cycle.
Here, the total time of cycle is
Substitute
Conclusion:
Thus, the time required to complete the filling and emptying cycle for a refuse collection vehicle is
Want to see more full solutions like this?
Chapter 3 Solutions
Solid Waste Engineering: A Global Perspective, Si Edition
- The City of Forty-Five (population 465,565) has requested your assistance in evaluating its solid waste collection system. Determine the mean time per collection stop plus the mean time to reach the next stop, the number of pickup locations per load, and the minimum number of trucks the city must own. The City of Forty-Five collection data are as follows: Average truck capacity = 12.5 m3; Average observed compaction ratio = 2.87 Crew size = 2; Number of pickups = 1 /wk (no rear-of-house service) Average number of cans per stop = 2.63/wk at 0.1136 m3/can Average number of residents per stop = 5 Average uncompacted density = 105.76 kg/m3 Average transport time to disposal site including delays and dumping = 1.78 h/trip Average number of trips to disposal site = 2/d; Rest breaks = 2 at 28.0 min Average maintenance downtime = 37.0 min/d; Average workday = 8.00 h Average percent of trucks out of service for major repairs = 15.0% Number of workday per week = 5arrow_forwardThe first decision to be made is how the solid waste container will get from the residence to the collection vehicle. Compare the advantages and disadvantages of the two methods of collection truck routing. i. Daily route method ii. Single load methodarrow_forwardUsing simple calculation method.arrow_forward
- 7-5. Assuming that the quantities of solid wastes generated daily at a commercial facility are distributed normally, with a mean value of 10 yd3 and a standard deviation of 7 yd3, what size container would you recommend for this facility? What are the important tradeoffs in the selection of container size?arrow_forwardAssume two truckloads, 4.02 hours of actual collection per day, the truck be if it has a compaction ratio of 3.5:1, and pickup vehicle averages 5 mph between stops that are on the average separated by 150 feet. Each stop collects from two households that each put out two full 30-gallon (4.4 cubic feet) containers. It takes an average of 20 seconds to empty one container. What is the time required to serve each stop in seconds?arrow_forwardFrom the following date, estimate the unit waste disposal rate per week for a residential area consisting of 1200 homes. The average occupancy is 4 persons per home. The observation location is a local transfer station that receives all of the wastes collected for disposal. The observation period was one week. Data: Number of compactor truck loads = 10 Average size of compactor truck = 20 yd³ Number of flatbed loads = 6 Average flatbed volume = 3 yd³ Number of loads from individual residents' private cars and trucks = 20 Estimated average volume per domestic vehicle = 9 ft³arrow_forward
- The rate of percolation into a 12-m deep landfill is 248 mm/y. The refuse (i.e., waste) field capacity is 305 mm/m and the moisture content of the refuse is 180 mm/m. Calculate how many years it will take for the moisture front to move through the landfill and produce leachate. Round your answer to one term past the decimal point.arrow_forwardFrom the following date, estimate the unit waste disposal rate per week for a residentialarea consisting of 1200 homes. The average occupancy is 4 persons per home. Theobservation location is a local transfer station that receives all of the wastes collected fordisposal. The observation period was one week.Data:Number of compactor truck loads = 10Average size of compactor truck = 20 yd3Number of flatbed loads = 6Average flatbed volume = 3 yd3Number of loads from individual residents’ private cars and trucks = 20 Estimatedaverage volume per domestic vehicle = 9 ft3arrow_forwardA town with 2,350 residents wants to establish a municipality owned and operated solid waste( garbage) collection program. They can purchase one of three possible trucks that have the ff. characteristics: Truck A, 18 m3 capacity Truck B, 15 m3 capacity Truck C, 12 m3 capacity If the truck is to collect the refuse for one-fifth of the town each day during a 5-day work week, then every residence will be collected during the week, and the truck will have to make only one trip per day to the landfill. Which truck or trucks will have sufficient capacity. Assume a rate of 1.75 kg/capitald. Assume that the truck is able to compact the refuse to 350 kg/ m3 * 14.1 5,757.5 4,935 24,675 28.787 5 Truck Truck Truck 16.45 A B What is the total tonnage of solid waste to be collected/wk? What is the total weight of waste to be collected everyday? What is the required truck сарacity in cubic meters? Which truck ооо о о о о should be bought ?arrow_forward
- A municipal solid-waste site for a city must be located at Site A or Site B. After sorting, some of the solid refuse will be transported to an electric power plant where it will be used as fuel. Data for the hauling of refuse from each site to the power plant are shown in the following table: Site A Site B Average hauling distance 4.8 km 6.4 km Annual rental fee $40,000 for solid-waste $25,000 site Hauling cost $2/m²-km $2/m²-km If the power plant will pay $8.00 per cubic meter of sorted solid waste delivered to the plant, where should the solid-waste site be located? Use the city's viewpoint and assume 120,000 cubic meters of refuse will be hauled to the plant for one year only. One site must be selected.arrow_forwardAssume two truckloads, 5.59 hours of actual collection per day, the truck be if it has a compaction ratio of 3.5:1, and pickup vehicie averages 5 mph between stops that are on the average separated by 150 feet. Each stop collects from two households that each put out two full 30-gallon (4.9 cubic feet) containers. it takes an average of 29 seconds to empty one container. What is the time required to serve each stop in seconds?arrow_forwardChapter 10 Disposal of Solid Wastes and Residual Matter 10.7 A). Determine the impact of a resource recovery program on landfill area requirement, in which 40% of the paper, 60% of the glass, and 80% of tin cans are recovered. Knowing that the previous land fill was designed for a city of 40 000 in population, Amount of waste generation = 2.5 kg/capita/d refuse is filled into a depth of about 3 m. The landfill site is to be used for 13 years component Typical composition% Food waste 15 Paper 40 Cardboard 4 Plastics 3 Textile 2 Rubber 0.5 Leather 0.5 Garden trimming 12 Wood 2 Glass 8 6 1 Tin cans Non-ferrous metals Ferrous metals 2 Dirt, ashes, brick, 4 etc. Density kg/m3 18.0 5.1 3.1 4 8 10 6.5 15.0 12.1 5.5 10.0 20 30 B) If the site above were to be constructed in three lifts what is the new area يأتي Gehöarrow_forward
- Solid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,