1.
Introduction:
To compute: The predetermined overhead rate, total
1.

Answer to Problem 3.15E
Plantwide predetermined overhead rate is $20 per machine hour, The Manufacturing cost assigned to job D-70 is $1,460,000 ,Bid price for job D-70 is $2,325,000, Bid price for job C-200 is $3,010,000.
Explanation of Solution
- Estimate total fixed manufacturing overhead co
- Manufacturing cost assigned to job D-70
- Bid price of job D-70
- Cost of goods sold:
Total overhead cost (Y):
Estimated total fixed overhead (a) is $910,000
Estimated variable overhead cost per machine hour molding (
Machine hour for molding required to support estimated production (
Estimated variable overhead cost per machine hour for fabrication (
Machine hour fabrication to support estimated production (
Total overhead cost (Y):
Plantwide predetermined overhead rate is $20 per machine hour
Particular | Molding | Fabrication | Total |
Direct materials | 375000 | 325000 | 700000 |
Direct labor | 200000 | 160000 | 360000 |
Overhead | 280000 | 120000 | 400000 |
Total manufacturing cost | 855000 | 605000 | 1460000 |
The Manufacturing cost assigned to job D-70 is $1,460,000
Manufacturing cost assigned to job C-220
Particular | Molding | Fabrication | Total |
Direct materials | 300000 | 250000 | 550000 |
Direct labor | 175000 | 225000 | 400000 |
Overhead | 120000 | 480000 | 600000 |
Total manufacturing cost | 855000 | 955000 | 1550000 |
The Manufacturing cost assigned to job D-70 is $1,550,000
Bid price are 150% of the total manufacturing cost:
Total manufacturing cost is $1460000
Bid price of job C-200
Bid price are 150% of the total manufacturing cost:
Total manufacturing cost is $1460000
Bid price for job D-70 is $2,325,000
Bid price for job C-200 is $3,010,000
2.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead. Absorption costing is used to calculate the cost of product while taking indirect and direct expense into account. Activity based costing assign the cost of all the activity of the organization according to their actual consumption
To compute: The predetermined overhead rate, total manufacturing cost established bit price and cost of goods sold.
2.

Answer to Problem 3.15E
The unit product cost of D is $90 and R is $50
Explanation of Solution
- Total overhead cost (Y):
- Total manufacturing cost assigned to job D-70
- Bid price of job D-70
- Cost of goods sold:
Estimated total fixed overhead (a) is $700,000
Estimated variable manufacturing overhead cost per machine hour molding (
Machine hour for molding required to support estimated production (
Total overhead cost (Y):
Particular | Amount |
Direct material | 700000 |
Direct labor | 360000 |
Overheads | |
Molding department ( | 532000 |
Fabrication department ( | 48000 |
Total manufacturing cost | 1640000 |
The total manufacturing cost of Job D-70 is $1,640,000.
Total manufacturing cost assigned to job C-220
Particular | Amount |
Direct material | 550000 |
Direct labor | 400000 |
Overheads | |
Molding department ( | 228000 |
Fabrication department ( | 192000 |
Total manufacturing cost | 1370000 |
The total manufacturing cost of Job C-220 is $1,370,000.
Bid price are 150% of the total manufacturing cost:
Total manufacturing cost is $1460000
Bid price of job C-200
Bid price are 150% of the total manufacturing cost:
Total manufacturing cost is $1460000
3.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead. Absorption costing is used to calculate the cost of product while taking indirect and direct expense into account. Activity based costing assign the cost of all the activity of the organization according to their actual consumption
The managerial insight revealed in the problem.
3.

Answer to Problem 3.15E
The overhead rate in molding ($38 per Mh) is much higher than the fabrication. Bid price using job C-200 are lower by $270000 in departmental approach than the plantwide approach as in department approach as in department approach bid price is $1,370,000 whereas in plant wide approach it is $1,550,000.
Explanation of Solution
The result of such a pool in cost is because of the fact that job D-70 is an intensive user of molding machine hours. The overhead rate in molding ($38 per Mh) is much higher than the fabrication. Bid price using job C-200 are lower by $270000 in departmental approach than the plantwide approach as in department approach as in department approach bid price is $1,370,000 whereas in plant wide approach it is $1,550,000. This shows the fact that Job C-200 is an intensive user of fabrication machine hour.
Job order costing system that have a single plant wide overhead cost are mainly used to value closing inventories and cost of goods sold for external reporting purpose. But a single plantwide overhead rate can create inaccurate in internal system and decision.
Want to see more full solutions like this?
Chapter 3 Solutions
MANAGERIAL ACCOUNTING FOR MANAGERS AC
- Give me the answer in a clear organized table please. Thank you!arrow_forwardGive me the answer in a clear organized table please. Thank you!arrow_forwardAssess the role of the Conceptual Framework in financial reporting and its influence on accounting theory and practice. Discuss how the qualitative characteristics outlined in the Conceptual Framework enhance financial reporting and contribute to decision-usefulness. Provide examplesarrow_forward
- Current Attempt in Progress Cullumber Corporation has income from continuing operations of $464,000 for the year ended December 31, 2025. It also has the following items (before considering income taxes). 1. An unrealized loss of $128,000 on available-for-sale securities. 2. A gain of $48,000 on the discontinuance of a division (comprised of a $16,000 loss from operations and a $64,000 gain on disposal). Assume all items are subject to income taxes at a 20% tax rate. Prepare a partial income statement, beginning with income from continuing operations. Income from Continuing Operations Discontinued Operations Loss from Operations Gain from Disposal Net Income/(Loss) CULLUMBER CORPORATION Income Statement (Partial) For the Year Ended December 31, 2025 Prepare a statement of comprehensive income. Net Income/(Loss) $ CULLUMBER CORPORATION Statement of Comprehensive Income For the Year Ended December 31, 2025 = Other Comprehensive Income Unrealized Loss of Available-for-Sale Securities ✰…arrow_forwardPlease make a trial balance, adjusted trial balance, Income statement. end balance ,owners equity statement, Balance sheet , Cash flow statement ,Cash end balancearrow_forwardActivity Based Costing - practice problem Fontillas Instrument, Inc. manufactures two products: missile range instruments and space pressure gauges. During April, 50 range instruments and 300 pressure gauges were produced, and overhead costs of $89,500 were estimated. An analysis of estimated overhead costs reveals the following activities. Activities 1. Materials handling 2. Machine setups Cost Drivers Number of requisitions Number of setups Total cost $35,000 27,500 3. Quality inspections Number of inspections 27,000 $89.500 The cost driver volume for each product was as follows: Cost Drivers Instruments Gauge Total Number of requisitions 400 600 1,000 Number of setups 200 300 500 Number of inspections 200 400 600 Insructions (a) Determine the overhead rate for each activity. (b) Assign the manufacturing overhead costs for April to the two products using activity-based costing.arrow_forward
- Bodhi Company has three cost pools and two doggie products (leashes and collars). The activity cost pool of ordering has the cost drive of purchase orders. The activity cost pool of assembly has a cost driver of parts. The activity cost pool of supervising has the cost driver of labor hours. The accumulated data relative to those cost drivers is as follows: Expected Use of Estimated Cost Drivers by Product Cost Drivers Overhead Leashes Collars Purchase orders $260,000 70,000 60,000 Parts 400,000 300,000 500,000 Labor hours 300,000 15,000 10,000 $960,000 Instructions: (a) Compute the activity-based overhead rates. (b) Compute the costs assigned to leashes and collars for each activity cost pool. (c) Compute the total costs assigned to each product.arrow_forwardTorre Corporation incurred the following transactions. 1. Purchased raw materials on account $46,300. 2. Raw Materials of $36,000 were requisitioned to the factory. An analysis of the materials requisition slips indicated that $6,800 was classified as indirect materials. 3. Factory labor costs incurred were $55,900, of which $51,000 pertained to factory wages payable and $4,900 pertained to employer payroll taxes payable. 4. Time tickets indicated that $50,000 was direct labor and $5,900 was indirect labor. 5. Overhead costs incurred on account were $80,500. 6. Manufacturing overhead was applied at the rate of 150% of direct labor cost. 7. Goods costing $88,000 were completed and transferred to finished goods. 8. Finished goods costing $75,000 to manufacture were sold on account for $103,000. Instructions Journalize the transactions.arrow_forwardChapter 15 Assignment of direct materials, direct labor and manufacturing overhead Stine Company uses a job order cost system. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 430 $2,500 3,500 $1,900 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at an overhead rate of 60% of direct labor cost. Instructions Prepare summary journal entries to record (i) the requisition slips, (ii) the time tickets, (iii) the assignment of manufacturing overhead to jobs,arrow_forward
- Solve accarrow_forwardSolve fastarrow_forwardAssume that none of the fixed overhead can be avoided. However, if the robots are purchased from Tienh Inc., Crane can use the released productive resources to generate additional income of $375,000. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Direct materials Direct labor Variable overhead 1A Fixed overhead Opportunity cost Purchase price Totals Make A Buy $ SA Net Income Increase (Decrease) $ Based on the above assumptions, indicate whether the offer should be accepted or rejected? The offerarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education