Bodhi Company has three cost pools and two doggie products (leashes and collars). The activity cost pool of ordering has the cost drive of purchase orders. The activity cost pool of assembly has a cost driver of parts. The activity cost pool of supervising has the cost driver of labor hours. The accumulated data relative to those cost drivers is as follows: Expected Use of Estimated Cost Drivers by Product Cost Drivers Overhead Leashes Collars Purchase orders $260,000 70,000 60,000 Parts 400,000 300,000 500,000 Labor hours 300,000 15,000 10,000 $960,000 Instructions: (a) Compute the activity-based overhead rates. (b) Compute the costs assigned to leashes and collars for each activity cost pool. (c) Compute the total costs assigned to each product.

Principles of Cost Accounting
17th Edition
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Edward J. Vanderbeck, Maria R. Mitchell
Chapter4: Accounting For Factory Overhead
Section: Chapter Questions
Problem 4P: Using the data in P4-2 and Microsoft Excel: 1. Separate the variable and fixed elements. 2....
icon
Related questions
Question
Bodhi Company has three cost pools and two doggie products (leashes and collars). The activity cost pool
of ordering has the cost drive of purchase orders. The activity cost pool of assembly has a cost driver of
parts. The activity cost pool of supervising has the cost driver of labor hours. The accumulated data
relative to those cost drivers is as follows:
Expected Use of
Estimated
Cost Drivers by Product
Cost Drivers
Overhead
Leashes
Collars
Purchase orders
$260,000
70,000
60,000
Parts
400,000
300,000
500,000
Labor hours
300,000
15,000
10,000
$960,000
Instructions: (a) Compute the activity-based overhead rates. (b) Compute the costs assigned to leashes
and collars for each activity cost pool. (c) Compute the total costs assigned to each product.
Transcribed Image Text:Bodhi Company has three cost pools and two doggie products (leashes and collars). The activity cost pool of ordering has the cost drive of purchase orders. The activity cost pool of assembly has a cost driver of parts. The activity cost pool of supervising has the cost driver of labor hours. The accumulated data relative to those cost drivers is as follows: Expected Use of Estimated Cost Drivers by Product Cost Drivers Overhead Leashes Collars Purchase orders $260,000 70,000 60,000 Parts 400,000 300,000 500,000 Labor hours 300,000 15,000 10,000 $960,000 Instructions: (a) Compute the activity-based overhead rates. (b) Compute the costs assigned to leashes and collars for each activity cost pool. (c) Compute the total costs assigned to each product.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College