(a)
Interpretation: The control limits for the mean and the range chart are to be determined.
Concept Introduction:
The control chart is used to determine the changes in the process over the time. The control chart consists three lines which are upper control limit line, lower control limit line and central line.
(b)
Interpretation: The capability of the process to meet the required specification is to be determined.
Concept Introduction:
The control chart is used to determine the changes in the process over the time. The control chart consists three lines which are upper control limit line, lower control limit line and central line.
(c)
Interpretation: The percent of the output which will fall outside the specification limit when the process is not capable is to be determined.
Concept Introduction:
The control chart is used to determine the changes in the process over the time. The control chart consists three lines which are upper control limit line, lower control limit line and central line.
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
- Cartons of Plaster are supposed to weigh exactly 32 ounces. Inspectors want to develop process control charts. They take five samples of six (5) boxes each and weigh them. Sample means (X-bar) are: 33.8, 34.6, 34.7, 34.1, and 34.2 respectively. Also, the corresponding ranges are: 1.1, 0.3, 0.4, 0.7, and 0.3, respectively. The lower and upper control limits of the R-chart are ,respectively O a. None is correct O b. O and O.15 O c. 0.01 and 1.13 O d. 0.03 and 1.18 O e. O and 1.18arrow_forwardIn a fabric manufacturing factory, the quality control process using control charts from SPC. In an hour there are a total of 5 samples are taken each having 5 observations regarding the thickness of fabric in measured in millimeters. In a particular hour, the sample means (X-bar) are noted to be: 156.46, 199.62, 189.31, 102.22, and112.09 respectively. In the same sample, the corresponding ranges are: 11.97, 12.17, 13.94, 11.86, and 11.83 respectively. What are the lower and upper control limits for the X-bar chart? O a. None is correct O b. 144.77,159.11 O c. 156.55, 170.47 d. 143.55, 165.47 e. 145.40, 190.72 f. 142.92, 160.66arrow_forwardIn a fabric manufacturing factory, the quality control process using control charts from SPC. In an hour there are a total of 5 samples are taken each having 5 observations regarding the thickness of fabric in measured in millimeters. In a particular hour, the sample means (X-bar) are noted to be: 156.46, 199.62, 189.31, 102.22, and112.09 respectively. In the same sample, the corresponding ranges are: 11.97, 12.17, 13.94, 11.86, and 11.83 respectively. What are the lower and upper control limits for the X-bar chart? ר O a. 142.92, 160.66 O b. 144.77,159.11 Oc. None is correct O d. 143.55, 165.47 O e. 156.55, 170.47 Of. 145.40, 190.72 OUS PAGE NEXT PAGE Type here to search - F5 F7 Pris F8 F9 F10 F12 %23 & 3 5 V 8 19 E T Y H. J K 1. 10 C V B NiM Alt く I LIarrow_forward
- Factors for Computing Control Chart Limits (3 sigma) Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor that must be controlled. From sample sizes of 10 pistons produced each day, the mean and the range of this diameter have been as follows: Day Mean x (mm) Range R (mm) 1 156.9 4.2 2 153.2 4.6 3 153.6 4.1 4 155.5 5.0 5 156.6 4.5 Part 4 c) What are the (UCLx) and (LCLx) using 3-sigma? (UCLx) = mm (round your response to two decimal places). (LCLx) = mmarrow_forwardIn a fabric manufacturing factory, the quality control process using control charts from SPC. In an hour there are a total of 5 samples are taken each having 6 observations regarding the thickness of fabric in measured in millimeters. In a particular hour, the sample means (X-bar) are noted to be: 156.46, 199.62, 189.31, 102.22, and112.09 respectively. In the same sample, the corresponding ranges are: 11.97, 12.17, 13.94, 11.86, and 11.83 respectively. What are the lower and upper control limits for the X-bar chart? O a. None is correct O b. 146.01, 157.87 Oc. 142.92, 160.66 Od. 143.55, 165.47 Oe. 156.55, 170.47 Of. 144.78, 159.11arrow_forwardIn a fabric manufacturing factory, the quality contral process using control charts from SPC. In an hour there are a total of 5 samples are taken each having 4 observations regarding the thickness of fabric in measured in millimeters. In a particular hour, the sample means (X-bar) are noted to be: 156.46, 199.62, 189.31, 102.22, and112.09 respectively. In the same sample, the corresponding ranges are: 11.97, 12.17, 13.94, 11.86, and 11.83 respectively. What are the lower and upper control limits for the X-bar chart?arrow_forward
- At Quick Car Wash, the wash process is advertised to take less than 8 minutes. Consequently, management has set a target average of 440 seconds for the wash process. Suppose the average range for a sample of 9 cars is 10 seconds. Use the accompanying table to establish control limits for sample means and ranges for the car wash process. Factors for calculating three-sigma limits for the x-chart and R-chart Size of Sample (n) Factor for UCL and LCL for x-chart (A2) Factor for LCL for R-Chart (D3) Factor for UCL for R-Chart (D4) 2 1.880 0 3.267 3 1.023 0 2.575 4 0.729 0 2.282 5 0.577 0 2.115 6 0.483 0 2.004 7 0.419 0.076 1.924 8 0.373 0.136 1.864 9 0.337 0.184 1.816 10 0.308 0.223 Part 2 The UCLR equals enter your response here seconds and the LCLR equals enter your response here seconds. (Enter your responses rounded to two decimal places.)arrow_forwardControl charts for X-bar and S are maintained for the fill volume of protein shake drink. The specifications are 330 + 10 mL. After 40 samples of size n=7 are analyzed, we find that: 40 40 = 13,200 Si = 296 i=1 i=D1 Find the best estimate of the process standard deviation. 7.498 7.400 7.570 2.737 7.713 8.032arrow_forwardA manufacturer of precision machine parts produces round shafts for use in the construction of drill presses. The average diameter of a shaft is .56 inch. Inspection samples contain 6 shafts each. The average range of these samples is .006 inch. Determine the upper and lower x control chart limits.arrow_forward
- Ross Hopkins is attempting to monitor a fill ing process that has an overall average of 705 mL. The average range is 6 mL. If you use a sample size of 10, what are the upper and lowercontrol limits for the mean and range?arrow_forwardsniparrow_forwardAuto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor that must be controlled. From sample sizes of 10 pistons produced each day, the mean and the range of this diameter have been as follows: a) What is the value of x? = x= 155.56 mm (round your response to two decimal places). b) What is the value of R? R 4.48 mm (round your response to two decimal places). c) What are the UCL; and LCL; using 3-sigma? Day 1 2 3 4 5 Upper Control Limit (UCL) = 156.94 mm (round your response to two decimal places). Lower Control Limit (LCL-) = 154.18 mm (round your response to two decimal places). d) What are the UCLR and LCLR using 3-sigma? Upper Control Limit (UCL) = 7.96 mm (round your response to two decimal places). Mean x (mm) 154.9 153.2 155.6 155.5 158.6 Range R (mm) 4.0 4.8 3.9 5.0 4.7 Lower Control Limit (LCL) = 1.00 mm (round your response to two decimal places). e) If the true diameter mean should be 155 mm and you want…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.