ENGINEERING DESIGN PROCESS
3rd Edition
ISBN: 9781305253285
Author: HAIK
Publisher: CENGAGE L
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 2.8, Problem 1P
Table 2.3 breaks down the number of major jobs or activities involved in painting a two-story house.
- a. Develop a CPM network.
- b. Determine the critical path of the network.
- c. Determine the expected project’s duration time period.
Table 2.3: Problem 1
(a)
Expert Solution
To determine
A CPM network.
Explanation of Solution
The CPM network for the data given in the Table 2.3 is shown below:
(b)
Expert Solution
To determine
The critical path of the network.
Answer to Problem 1P
The critical path activities are as follows.
Critical Paths |
A-B-D-E-G-H-I-K |
A-B-D-E-G-H-J-K |
A-C-D-E-G-H-I-K |
A-C-D-E-G-H-J-K |
Explanation of Solution
Using Excel spread sheet the network path is framed and its critical path is identified and shown below:
Activity | Early Start Time | Early Finish Time |
Duration | Late Start Time | Late Finish Time |
Float/Slack |
Formula:
The identified network paths are shown below with duration:
Paths | Duration |
A-B-D-E-F-H-J-K | 23 |
A-B-D-E-G-H-I-K | 26 |
A-B-D-E-G-H-J-K | 26 |
A-C-D-E-F-H-I-K | 23 |
A-C-D-E-F-H-J-K | 23 |
A-C-D-E-G-H-I-K | 26 |
A-C-D-E-G-H-J-K | 26 |
The path with the longest duration is the critical path. Hence, the critical path activities are as follows.
Critical Paths |
A-B-D-E-G-H-I-K |
A-B-D-E-G-H-J-K |
A-C-D-E-G-H-I-K |
A-C-D-E-G-H-J-K |
(c)
Expert Solution
To determine
The expected project duration time.
Explanation of Solution
Refer part (b)
The expected project duration time is shown below:
Paths | Duration |
A-B-D-E-G-H-I-K | 26 |
A-B-D-E-G-H-J-K | 26 |
A-C-D-E-G-H-I-K | 26 |
A-C-D-E-G-H-J-K | 26 |
Want to see more full solutions like this?
Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Discuss each element of the example plan provided and indicate benefits each section activity provides in helping to manage risk with the mechanical and electrical subcontractors on a project.
After reviewing the sample plan discuss the benefits of of the activities defined in the subsections that help manage risks with mechanical and electrical subcontractors.
Please be as detailed as possible
and thank you in advance for your help.
List any 3 project ideas of process improvement or design for industrial engineering
Problem 3: A small gearing system in your brand-new 3D printer fails as you were printing,
leading to an overload in the motor and a fire in your home. The fire spreads, burning half of
Everglades National Park in the worst environmental disaster in US history.
The printer company blames you! Stating that you must have been misusing the printer some-
how. Use your engineering knowledge to "show those jerks you mean business!"
You investigate and find a serial number on the gears and type it into Google, finding the
company that manufactures the gears. Their website provides some info that this series of gear is
made from AISI 4340 steel and the yield strength is 125 kpsi.
Assuming each gear tooth acts as a small cantilever, prove to the 3D printer company that they
are liable for the fire.
oct
#
Gear Information
Gear radius (r): 1.00 in
Tooth length (1): 0.15 in
Tooth height (h): 0.15 in
Tooth thickness (b): 0.1 in
Angular velocity (w): 0.1 rad/s
Motor Information
Power (H): 0.009 hp
1…
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.Similar questions
- Subject: MICROCONTROLLER SYSTEM AND DESIGN kindly do this in 10 Minutes ASAP.arrow_forwardTask 1: - Wind Turbine Electrical Arrangements: There are four types of wind turbines in terms of their electrical design, namely: Type A, B, C and D. Considering the mechanical, electrical, electronic and control design features of these four types, compare them in terms of: Efficiency. Performance.arrow_forward5 Look at the flow chart showing the steps of the design process. Then read the list of steps for designing a thermos. These steps are not in order. Write the letter of each step in the appropriate box of the flow chart. The Design Process Find a problem Keep records Plan and build a prototype Keep records Test and improve Keep records Communicate the solutionarrow_forward
- Answer the two connected questions (Task A-1 and A-2). Provided in the last part are the guides and examples: The process for large-scale manufacture of paper has been largely unchanged for the last 125 years. The pulp and paper industry today is highly capital intensive, and there is an ongoing drive towards process integration, thereby increasing the efficiency of utilization of available process resources. This paper deals with the Kraft process (see Fig. 1) though the general principles described can be extended to other pulping processes. As shown in Figure 1, five water sinks and four water sources are considered for in-plant water reuse/ recycle. Prior to water reuse/ recycle, the network requires a freshwater flow rate of 36,400 tonne/day and generates 37,186 tonne/day of wastewater (sum of the individual sink and source flow rates in Table 1). The freshwater source that is available for service has an impurity concentration (chloride content) of 4.2 ppm, which is higher than…arrow_forwardit is multiply choisy so answer quicklyarrow_forwardAs a building designer, you have been asked to analyze and select the bestwindow frame type alternative—either aluminum or steel. The project is located in a remotearea, and the nearest industrial area hosting steel and aluminum windows framesmanufacturers is 250 km away. All project windows are identical, and the circumference ofthe window frame is 6.2 meter. A crew of two labors is required to manufacture one steelframe. It takes 2.5 hours to manufacture the first window every day, and the learning rate is0.9. The number of production units is per day is limited to 8. The weight of steel is 12 kg permeter, and the weight of aluminum is 4.5 kg per meter. The cost of steel is 0.4 OMR per kgand the cost of aluminum 1.1 OMR per kg. If 45 windows frames are required for the project,the crew cost is 3 OMR per hour for steel frames and 3.6 for aluminum frames, and thetransportation, price is 0.01 OMR per kg per 50 km, which alternative would you select?arrow_forward
- Briefly define Scrum project methodologyarrow_forwardSHOW YOUR SOLUTIONS PLS, THANKS show me how you did it so I can understand, thank you. Pls answer both, this is my last tutor question, pls. thank you. (Porosity). A dry rock weighs 240 grams and has a bulk density of 2.4 grams per cubic centimeter. When saturated with pure water at room temperature (T=25°C), it weighs 250 grams. At room temperature, the specific volume of water is 1.00295 x10-3m3/kg. Calculate the porosity of the sample. (Permeability). A cylindrical core sample of 1 cm length and 1 cm2cross-section has upstream and downstream pressures of 2 atm and 1 atm, respectively, during steady state flow of water at 0.997 g/s at room temperature. Calculate the permeability of the core. Note: Water @ 25°C, viscosity = 1 cp, density of water = 0.997 g/cm3.arrow_forwardMultiple-Choice Questions In 4D printing, what is the fourth dimension? A. Space B. Movement C. Time D. Material What inspired the team at the MIT self-assembly lab to conceive the Autonomous Mass Assembly concept? A. The natural growth of viruses B. Japanese architecture C. Islamic patterns in traditional ornaments D. The movie "Avatar" Which of the following are possible applications of 4D printing? Select all correct answers. A. Smart water pipes B. Self-assembled structures C. Ready-made electronic devices D. Superior sound systems What activating energies are used in the 4D products presented in the lesson? A. Heat B. Water C. Microwave D. Sound-wavesarrow_forward
- SUBJECT ; INDUSTRIAL CONTROL PLEASE PROVIDE CLEAR EXPLAINATION , THANK YOU IN ADVANCEarrow_forwardGroup Problem: You are planning to build a log cabin in Northern Minnesota on a remote hill with a beautiful view of the setting sun. You will drag the logs up a long sometimes rocky hill to the building site by means of a rope attached to a winch. You will need a rope for this job so you aim to know how much weight the rope would safely support. You are operating on a tight budget so matching the rope strength would be a cost saver. You know that the logs are heavy, and estimate the heaviest as 1,000 lbs. From maps you verify the hill is steeped at an angle of = 70° with respect to the vertical, and you estimate a coefficient of kinetic friction between a log and the earthen hill as 0.5. When pulling a log you will ensure that the uphill acceleration is never more than 3.0 ft/s². The maximum recommended load is th of the nominal strength for the ropes considered as stated on the product labels, you have three ropes in mind: 12 kN, 18 kN, & 24 kN. Which one of these three rope…arrow_forwardPlease and explain step by step, instructions given at toparrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Precision Machining Technology (MindTap Course Li...Mechanical EngineeringISBN:9781285444543Author:Peter J. Hoffman, Eric S. Hopewell, Brian JanesPublisher:Cengage LearningAutomotive Technology: A Systems Approach (MindTa...Mechanical EngineeringISBN:9781133612315Author:Jack Erjavec, Rob ThompsonPublisher:Cengage Learning
Precision Machining Technology (MindTap Course Li...
Mechanical Engineering
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Cengage Learning
Automotive Technology: A Systems Approach (MindTa...
Mechanical Engineering
ISBN:9781133612315
Author:Jack Erjavec, Rob Thompson
Publisher:Cengage Learning
The Engineering Design Process - Simplified; Author: College & Career Ready Labs │ Paxton Patterson;https://www.youtube.com/watch?v=KpWrHVo972g;License: Standard Youtube License