Table 2.3 breaks down the number of major jobs or activities involved in painting a two-story house.

  1. a. Develop a CPM network.
  2. b. Determine the critical path of the network.
  3. c. Determine the expected project’s duration time period.

Table 2.3: Problem 1

Chapter 2.8, Problem 1P, Table 2.3 breaks down the number of major jobs or activities involved in painting a two-story house.

(a)

Expert Solution
Check Mark
To determine

A CPM network.

Explanation of Solution

The CPM network for the data given in the Table 2.3 is shown below:

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  1

(b)

Expert Solution
Check Mark
To determine

The critical path of the network.

Answer to Problem 1P

The critical path activities are as follows.

Critical Paths
A-B-D-E-G-H-I-K
A-B-D-E-G-H-J-K
A-C-D-E-G-H-I-K
A-C-D-E-G-H-J-K

Explanation of Solution

Using Excel spread sheet the network path is framed and its critical path is identified and shown below:

ActivityEarly Start TimeEarly Finish Time
DurationLate Start TimeLate Finish Time
Float/Slack

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  2

Formula:

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  3

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  4

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  5

The identified network paths are shown below with duration:

PathsDuration
A-B-D-E-F-H-J-K23
A-B-D-E-G-H-I-K26
A-B-D-E-G-H-J-K26
A-C-D-E-F-H-I-K23
A-C-D-E-F-H-J-K23
A-C-D-E-G-H-I-K26
A-C-D-E-G-H-J-K26

The path with the longest duration is the critical path. Hence, the critical path activities are as follows.

Critical Paths
A-B-D-E-G-H-I-K
A-B-D-E-G-H-J-K
A-C-D-E-G-H-I-K
A-C-D-E-G-H-J-K

(c)

Expert Solution
Check Mark
To determine

The expected project duration time.

Explanation of Solution

Refer part (b)

The expected project duration time is shown below:

PathsDuration
A-B-D-E-G-H-I-K26
A-B-D-E-G-H-J-K26
A-C-D-E-G-H-I-K26
A-C-D-E-G-H-J-K26

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Determine the normal stresses σn and σt and the shear stress τnt at this point if they act on the rotated stress element shown
Using method of joints, determine the force in each member of the truss and state if the members are in tension or compression. A E 6 m D 600 N 4 m B 4 m 900 N
Question 5. The diagram below shows a mass suspended from a tie supported by two horizontal braces of equal length. The tie forms an angle "a" of 60° to the horizontal plane, the braces form an angle 0 of 50° to the vertical plane. If the mass suspended is 10 tonnes, and the braces are 10m long, find: a) the force in the tie; & b) the force in the braces Horizontal Braces, Tie Mass
Knowledge Booster
Background pattern image
Mechanical Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Automotive Technology: A Systems Approach (MindTa...
Mechanical Engineering
ISBN:9781133612315
Author:Jack Erjavec, Rob Thompson
Publisher:Cengage Learning
Text book image
Precision Machining Technology (MindTap Course Li...
Mechanical Engineering
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Cengage Learning
The Engineering Design Process - Simplified; Author: College & Career Ready Labs │ Paxton Patterson;https://www.youtube.com/watch?v=KpWrHVo972g;License: Standard Youtube License