Table 2.3 breaks down the number of major jobs or activities involved in painting a two-story house.

  1. a. Develop a CPM network.
  2. b. Determine the critical path of the network.
  3. c. Determine the expected project’s duration time period.

Table 2.3: Problem 1

Chapter 2.8, Problem 1P, Table 2.3 breaks down the number of major jobs or activities involved in painting a two-story house.

(a)

Expert Solution
Check Mark
To determine

A CPM network.

Explanation of Solution

The CPM network for the data given in the Table 2.3 is shown below:

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  1

(b)

Expert Solution
Check Mark
To determine

The critical path of the network.

Answer to Problem 1P

The critical path activities are as follows.

Critical Paths
A-B-D-E-G-H-I-K
A-B-D-E-G-H-J-K
A-C-D-E-G-H-I-K
A-C-D-E-G-H-J-K

Explanation of Solution

Using Excel spread sheet the network path is framed and its critical path is identified and shown below:

ActivityEarly Start TimeEarly Finish Time
DurationLate Start TimeLate Finish Time
Float/Slack

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  2

Formula:

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  3

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  4

ENGINEERING DESIGN PROCESS, Chapter 2.8, Problem 1P , additional homework tip  5

The identified network paths are shown below with duration:

PathsDuration
A-B-D-E-F-H-J-K23
A-B-D-E-G-H-I-K26
A-B-D-E-G-H-J-K26
A-C-D-E-F-H-I-K23
A-C-D-E-F-H-J-K23
A-C-D-E-G-H-I-K26
A-C-D-E-G-H-J-K26

The path with the longest duration is the critical path. Hence, the critical path activities are as follows.

Critical Paths
A-B-D-E-G-H-I-K
A-B-D-E-G-H-J-K
A-C-D-E-G-H-I-K
A-C-D-E-G-H-J-K

(c)

Expert Solution
Check Mark
To determine

The expected project duration time.

Explanation of Solution

Refer part (b)

The expected project duration time is shown below:

PathsDuration
A-B-D-E-G-H-I-K26
A-B-D-E-G-H-J-K26
A-C-D-E-G-H-I-K26
A-C-D-E-G-H-J-K26

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Determine the stress in each section of the bar shown in Fig. when subjected to an axial tensile load shown in Fig. The central section is 30 mm hollow square cross- section; the other portions are of circular section, their diameters being indicated What will be the total deformation of the bar? For the bar material E = 210GPa. 20mi О 30mm 30mmm 2.6 15mm 30kN 1 2 10kN - 20kN 3 -329 91mm 100mm 371mm
Calculate the load that will make point A move to the left by 6mm, E=228GPa. The diameters of the rods are as shown in fig. below. 2P- PA 80mm B 200mm 2P 0.9m 1.3m.
If the rods are made from a square section with the dimension as shown. Calculate the load that will make point A move to the left by 6mm, E=228GPa. 2P- P A 80mm B 200mm 2P 0.9m 1.3m
Knowledge Booster
Background pattern image
Mechanical Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Automotive Technology: A Systems Approach (MindTa...
Mechanical Engineering
ISBN:9781133612315
Author:Jack Erjavec, Rob Thompson
Publisher:Cengage Learning
Text book image
Precision Machining Technology (MindTap Course Li...
Mechanical Engineering
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Cengage Learning
The Engineering Design Process - Simplified; Author: College & Career Ready Labs │ Paxton Patterson;https://www.youtube.com/watch?v=KpWrHVo972g;License: Standard Youtube License