Loose Leaf For Fundamental Accounting Principles Format: Loose-leaf
Loose Leaf For Fundamental Accounting Principles Format: Loose-leaf
24th Edition
ISBN: 9781260158557
Author: Wild
Publisher: Mcgraw Hill Publishers
Question
Book Icon
Chapter 26, Problem 6BPSB
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-1:

To Calculate:

Payback period for the project

Expert Solution
Check Mark

Answer to Problem 6BPSB

Payback period for the project is 1.9 years

Explanation of Solution

Payback period for the project is calculated as follows;

    Cash Flows Accumulated Cash Flows
    Period 1 $ 450,000 $ 450,000
    Period 2 $ 400,000 $ 850,000
    Period 3 $ 350,000 $1,200,000
    Period 4 $ 300,000 $1,500,000
    Payback Period = 1 Year + (800000-450000)/400000 = 1.9 Years
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-2:

To Calculate:

Breakeven time for the investment

Expert Solution
Check Mark

Answer to Problem 6BPSB

Breakeven time for the investment is 2.2 Years

Explanation of Solution

Breakeven time for the investment is calculated as follows:

    Cash Flows PV of $1 (10%)PV Accumulated PV
    A BC=A*B
    Period 1 $ 450,000 0.9091 $ 409,095.00 $ 409,095.00
    Period 2 $ 400,000 0.8264 $ 330,560.00 $ 739,655.00
    Period 3 $ 350,000 0.7513 $ 262,955.00 $ 1,002,610.00
    Period 4 $ 300,000 0.6830 $ 204,900.00 $ 1,207,510.00
    Breakeven Time = 2 Years +(800000-739655)/262955 =2.2 Years
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-3:

To Calculate:

The Net Present Value of the investment

Expert Solution
Check Mark

Answer to Problem 6BPSB

The Net Present Value of the investment is $407,510

Explanation of Solution

The Net Present Value of the investment is calculated as follows:

    Cash Flows PV of $1 (10%)PV
    A BC=A*B
    Period 1 $ 450,000 0.9091 $ 409,095
    Period 2 $ 400,000 0.8264 $ 330,560
    Period 3 $ 350,000 0.7513 $ 262,955
    Period 4 $ 300,000 0.6830 $ 204,900
    Total Present value $1,207,510
    Less: Initial investment $(800,000)
    Net Present value $ 407,510
To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-4:

If the management should invest in the project

Expert Solution
Check Mark

Answer to Problem 6BPSB

Yes, the management should invest in the project.

Explanation of Solution

The Net Present Value of the investment is calculated as follows:

    Cash Flows PV of $1 (10%)PV
    A BC=A*B
    Period 1 $ 450,000 0.9091 $ 409,095
    Period 2 $ 400,000 0.8264 $ 330,560
    Period 3 $ 350,000 0.7513 $ 262,955
    Period 4 $ 300,000 0.6830 $ 204,900
    Total Present value $1,207,510
    Less: Initial investment $(800,000)
    Net Present value $ 407,510

The Net Present Value of the investment is $407,510; hence the management should invest in the project.

To determine

Concept Introduction:

Payback Period:

Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:

  Payback Period= Initial InvestmentAnnual Cash inflow

NPV:

Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:

  NPV = Present value of cash inflows  Present value of cash out flows

Requirement-5:

If the reason of differences in answers as compared with the previous situation

Expert Solution
Check Mark

Answer to Problem 6BPSB

The reason of differences in answers as compared with the previous situation is the cash flow pattern.

Explanation of Solution

The reason of differences in answers as compared with the previous situation is the cash flow pattern. In the previous case, the higher cash flows are occurring in later years but in this situation the cash flows are higher in initial years of the project.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Question 4Waterfront Inc. wishes to borrow on a short-term basis withoutreducing its current ratio below 1.25. At present its current assetsand current liabilities are $1,600 and $1,000 respectively. How muchcan Waterfront Inc. borrow?
Question 6During 2019, Bitsincoins Corporation had EBIT of $100,000, a changein net fixed assets of $400,000, an increase in net current assets of$100,000, an increase in spontaneous current liabilities of $400,000,a depreciation expense of $50,000, and a tax rate of 30%. Based onthis information, what is Bitsincoin’s free cash flow?
Cariveh Co sells automotive supplies from 25 different locations in one country. Each branch has up to 30 staff working there, although most of the accounting systems are designed and implemented from the company's head office. All accounting systems, apart from petty cash, are computerised, with the internal audit department frequently advising and implementing controls within those systems.Cariveh has an internal audit department of six staff, all of whom have been employed at Cariveh for a minimum of five years and some for as long as 15 years. In the past, the chief internal auditor appoints staff within the internal audit department, although the chief executive officer (CEO) is responsible for appointing the chief internal auditor.The chief internal auditor reports directly to the finance director. The finance director also assists the chief internal auditor in deciding on the scope of work of the internal audit department.You are an audit manager in the internal audit department…

Chapter 26 Solutions

Loose Leaf For Fundamental Accounting Principles Format: Loose-leaf

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education