Concept explainers
Activity-based department rate product costing and product cost distortions
Big Sound Inc. manufactures two products: receivers and loud-speakers. The factory
Indirect labor | $400,400 |
Cutting Department | 198,800 |
Finishing Department | 114,800 |
Total | $714,000 |
The activity base associated with the two production departments is direct labor hours. The indirect labor can be assigned to two different activities as follows:
Activity | Budgeted Activity Cost | Activity Base |
Setup | $138,600 | Number of setup |
Quality Control | 261,800 | Number of inspections |
Total | $400,400 |
The activity-base usage quantities and units produced for the two products follow:
Number o Setup |
Number of Inspections |
Direct Labor Hours—Subassembly |
Direct Labor Hours—Final Assembly |
Units Produced |
|
Snowboards | 430 | 5,000 | 4,000 | 2,000 | 6,000 |
Skis | _70 | 2,500 | 2,000 | 4,000 | 6,000 |
Total | 500 | 7,500 | 6,000 | 6,000 | 12,000 |
Instructions
1. Determine the factory overhead rates under the multiple production department rate method. Assume that indirect labor is associated with the production departments, so that the total factory overhead is 5420,000 and $294,000 for the Subassembly and Final Assembly departments, respectively.
2. Determine the total and per-unit
3. Determine the activity rates, assuming that the indirect labor is associated with activities rather than with the production departments.
4. Determine the total and per-unit cost assigned to each product under activity-based costing.
5. Explain the difference in the per-unit overhead allocated to each product under the multiple production department factory overhead rate and activity-based costing methods.
1.
Multiple production department factory overhead rate: This allocation method identifies different departments in the process of production. The factory overheads are allocated to products based on the overhead rate for each of the production departments.
Formula to compute multiple production department overhead rate:
Activity-based costing (ABC) method: The costing method which allocates overheads to the products based on factory overhead rate for each activity or cost object, according to the cost pooled for the cost drivers (allocation base).
Formula to compute activity-based overhead rate:
To compute: The multiple production department overhead rate for both departments
Explanation of Solution
Compute multiple production department overhead rate for subassembly department.
Compute multiple production department overhead rate for final assembly department.
2.
To compute: The factory overhead allocated to total and per unit of each product
Explanation of Solution
Compute total factory overhead and per unit overhead allocated for receivers.
Production Department | Multiple Production Department Overhead Rate | × | Total Number of Budgeted DLH | = | Factory Overhead |
Subassembly | $300 per DLH | × | 875 DLH | = | $262,500 |
Final assembly | $210 per DLH | × | 525 DLH | = | 110,250 |
Total factory overhead costs allocated for receivers | $372,750 | ||||
Number of units of receivers | ÷ 7,000 units | ||||
Factory overhead cost per unit of receivers | $53.25 |
Table (1)
Note: Refer to part (A) for value and computation of multiple production department overhead rate.
Compute total factory overhead and per unit overhead allocated for loudspeakers.
Production Department | Multiple Production Department Overhead Rate | × | Total Number of Budgeted DLH | = | Factory Overhead |
Subassembly | $300 per DLH | × | 525 DLH | = | $157,500 |
Final assembly | $210 per DLH | × | 875 DLH | = | 183,750 |
Total factory overhead costs allocated for loudspeakers | $341,250 | ||||
Number of units of loudspeakers | ÷ 7,000 units | ||||
Factory overhead cost per unit of loudspeakers | $48.75 |
Table (2)
Note: Refer to part (A) for value and computation of multiple production department overhead rate.
3.
To compute: The activity-based overhead rate for each of the given activities
Explanation of Solution
Compute activity-based overhead rates.
Computation of Activity-Based Overhead Rates | |||||
Activity | Activity Cost | ÷ | Total Activity-Base Usage | = | Activity-Based Overhead Rates |
Setup | $138,600 | ÷ | 400 setups | = | $346.50 per setup |
Quality control | 261,800 | ÷ | 2,200 inspections | = | $119 per inspection |
Subassembly | 198,800 | ÷ | 1,400 DLH | = | $142 per DLH |
Final assembly | 114,800 | ÷ | 1,400 DLH | = | $82 per DLH |
Table (3)
4.
To compute: The activity-cost per unit of the products
Explanation of Solution
Compute activity cost allocated per unit of receivers.
Activity | Activity-Based Overhead Rates | × | Actual Use of Activity-Base (Cost Driver) | = | Activity Cost Allocated |
Setup | $346.50 per setup | × | 80 setups | = | $27,720 |
Quality control | $119 per inspection | × | 450 inspections | = | 53,550 |
Subassembly | $142 per DLH | × | 875 DLH | = | 124,250 |
Final assembly | $82 per DLH | × | 525 DLH | = | 43,050 |
Total activity costs allocated to receivers | $248,570 | ||||
Number of units of receivers | ÷ 7,000 units | ||||
Activity-based overhead cost per unit of receivers | $35.51 |
Table (4)
Note: Refer to Table (3) for the value and computation of activity allocation rates.
Compute activity cost allocated per unit of loudspeakers.
Activity | Activity-Based Overhead Rates | × | Actual Use of Activity-Base (Cost Driver) | = | Activity Cost Allocated |
Setup | $346.50 per setup | × | 320 setups | = | $110,880 |
Quality control | $119 per inspection | × | 1,750 inspections | = | 208,250 |
Subassembly | $142 per DLH | × | 525 DLH | = | 74,550 |
Final assembly | $82 per DLH | × | 875 DLH | = | 71,750 |
Total activity costs allocated to loudspeakers | $465,430 | ||||
Number of units of loudspeakers | ÷ 7,000 units | ||||
Activity-based overhead cost per unit of loudspeakers | $66.49 |
Table (5)
Note: Refer to Table (3) for the value and computation of activity allocation rates.
5.
To discuss: The product cost distortion due to multiple production department overhead rate
Explanation of Solution
The product cost under multiple production department overhead rate approach and ABC approach are different. The product cost is distorted in multiple production department overhead rate approach. Although the time spent for subassembly and final assembly departments for loudspeakers and receivers is in the same ratio, but the setup department and quality control department are not accounted for in multiple department overhead rate method.
Want to see more full solutions like this?
Chapter 26 Solutions
Working Papers, Volume 1, Chapters 1-15 for Warren/Reeve/Duchac's Corporate Financial Accounting, 13th + Financial & Managerial Accounting, 13th
- Activity-based department rate product costing and product cost distortions Big Sound Inc. manufactures two products: receivers and loudspeakers. The factory overhead incurred is as follows: The activity base associated with the two production departments is direct labor hours. The indirect labor can be assigned to two different activities as follows: The activity-base usage quantities and units produced for the two products follow: Instructions Determine the factory overhead rates under the multiple production department rate method. Assume that indirect labor is associated with the production departments, so that the total factory overhead is 420,000 and 294,000 for the Subassembly and Final Assembly departments, respectively. Determine the total and per-unit factory overhead costs allocated to each product, using the multiple production department overhead rates in (1). Determine the activity rates, assuming that the indirect labor is associated with activities rather than with the production departments. Determine the total and per-unit cost assigned to each product under activity-based costing. Explain the difference in the per-unit overhead allocated to each product under the multiple production department factory overhead rate and activity-based costing methods. production department factory overhead rate and activity-based costing methods.arrow_forwardMinor Co. has a job order cost system and applies overhead based on departmental rates. Service Department 1 has total budgeted costs of 168,000 for next year. Service Department 2 has total budgeted costs of 280,000 for next year. Minor allocates service department costs solely to the producing departments. Service Department 1 cost is allocated to producing departments on the basis of machine hours. Service Department 2 cost is allocated to producing departments on the basis of direct labor hours. Producing Department 1 has budgeted 8,000 machine hours and 12,000 direct labor hours. Producing Department 2 has budgeted 2,000 machine hours and 12,000 direct labor hours. What is the total cost allocation from the two service departments to Producing Department 1? a. 173,600 b. 140,000 c. 134,400 d. 274,400arrow_forwardOverhead Rates, Unit Costs Folsom Company manufactures specialty tools to customer order. There are three producing departments. Departmental information on budgeted overhead and various activity measures for the coming year is as follows: Currently, overhead is applied on the basis of machine hours using a plantwide rate. However, Janine, the controller, has been wondering whether it might be worthwhile to use departmental overhead rates. She has analyzed the overhead costs and drivers for the various departments and decided that Welding and Finishing should base their overhead rates on machine hours and that Assembly should base its overhead rate on direct labor hours. Janine has been asked to prepare bids for two jobs with the following information: The typical bid price includes a 35% markup over full manufacturing cost. Round all overhead rates to the nearest cent. Round all bid prices to the nearest dollar. Required: 1. Calculate a plantwide rate for Folsom Company based on machine hours. What is the bid price of each job using this rate? 2. Calculate departmental overhead rates for the producing departments. What is the bid price of each job using these rates?arrow_forward
- Pelder Products Company manufactures two types of engineering diagnostic equipment used in construction. The two products are based upon different technologies, X-ray and ultrasound, but are manufactured in the same factory. Pelder has computed the manufacturing cost of the X-ray and ultrasound products by adding together direct materials, direct labor, and overhead cost applied based on the number of direct labor hours. The factory has three overhead departments that support the single production line that makes both products. Budgeted overhead spending for the departments is as follows: Pelders budgeted manufacturing activities and costs for the period are as follows: The budgeted cost to manufacture one ultrasound machine using the activity-based costing method is: a. 225. b. 264. c. 293. d. 305.arrow_forwardThe management of Nova Industries Inc. manufactures gasoline and diesel engines through two production departments, Fabrication and Assembly. Management needs accurate product cost information in order to guide product strategy. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering the multiple production department factory overhead rate method. The following factory overhead was budgeted for Nova: Direct labor hours were estimated as follows: In addition, the direct labor hours (dlh) used to produce a unit of each product in each department were determined from engineering records, as follows: a. Determine the per-unit factory overhead allocated to the gasoline and diesel engines under the single plantwide factory overhead rate method, using direct labor hours as the activity base. b. Determine the per-unit factory overhead allocated to the gasoline and diesel engines under the multiple production department factory overhead rate method, using direct labor hours as the activity base for each department. c. Recommend to management a product costing approach, based on your analyses in (a) and (b). Support your recommendation.arrow_forwardActivity-based product costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: The activity bases identified for each activity are as follows: The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows: Each product requires 0.5 machine hour per unit. Instructions Determine the activity rate for each activity. Determine the total and per-unit activity cost for all three products. Round to nearest cent. Why arent the activity unit costs equal across all three products since they require the same machine time per unit?arrow_forward
- Medical Tape makes two products: Generic and Label. It estimates it will produce 423,694 units of Generic and 652,200 of Label, and the overhead for each of its cost pools is as follows: It has also estimated the activities for each cost driver as follows: How much is the overhead allocated to each unit of Generic and Label?arrow_forwardActivity-based costing: selling and administrative expenses Jungle Junior Company manufactures and sells outdoor play equipment. Jungle Junior uses activity-based costing to determine the cost of the sales order processing and the customer return activity. The sales order processing activity has an activity rate of 20 per sales order, and the customer return activity has an activity rate of 100 per return. Jungle Junior sold 2,500 swing sets, which consisted of 750 orders and 80 returns. Determine (A) the total and (B) the per-unit sales order processing and customer return activity cost for swing sets.arrow_forwardLansing. Inc., provided the following data for its two producing departments: Machine hours are used to assign the overhead of the Molding Department, and direct labor hours are used to assign the overhead of the Polishing Department. There are 30,000 units of Form A produced and sold and 50,000 of Form B. Required: 1. Calculate the overhead rates for each department. 2. Using departmental rates, assign overhead to live two products and calculate the overhead cost per unit. How does this compare with the plantwide rate unit cost, using direct labor hours? 3. What if the machine hours in Molding were 1,200 for Form A and 3,800 for Form B and the direct labor hours used in Polishing were 5,000 and 15,000, respectively? Calculate the overhead cost per unit for each product using departmental rates, and compare with the plantwide rate unit costs calculated in Requirement 2. What can you conclude from this outcome?arrow_forward
- Activity-based product costing Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: The activity bases identified for each activity are as follows: The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows: Each product requires 40 minutes per unit of machine time. Instructions Determine the activity rate for each activity. Determine the total and per-unit activity cost for all three products. Round to nearest cent. Why arent the activity unit costs equal across all three products since they require the same machine time per unit?arrow_forwardA manufacturing company has two service and two production departments. Building Maintenance and Factory Office are the service departments. The production departments are Assembly and Machining. The following data have been estimated for next years operations: The direct charges identified with each of the departments are as follows: The building maintenance department services all departments of the company, and its costs are allocated using floor space occupied, while factory office costs are allocable to Assembly and Machining on the basis of direct labor hours. 1. Distribute the service department costs, using the direct method. 2. Distribute the service department costs, using the sequential distribution method, with the department servicing the greatest number of other departments distributed first.arrow_forwardA manufacturing company has two service and two production departments. Human Resources and Machine Repair are the service departments. The production departments are Grinding and Polishing. The following data have been estimated for next years operations: The direct charges identified with each of the departments are as follows: The human resources department services all departments of the company, and its costs are allocated using the numbers of employees within each department, while machine repair costs are allocable to Grinding and Polishing on the basis of machine hours. 1. Distribute the service department costs, using the direct method. 2. Distribute the service department costs, using the sequential distribution method, with the department servicing the greatest number of other departments distributed first.arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning