1.
To compute: Annual expected net
1.

Explanation of Solution
Given below is the table for the computation of annual expected net cash flows:
Annual cash flow | ||
Particulars | Project Y ($) | Project Z ($) |
Profit after tax | 56,000 | 36,400 |
87,500 | 116,666.66 | |
Cash flows after tax | 143,500 | 153,066.66 |
Working notes:
Calculation of annual depreciation of Project Y,
Calculation of annual depreciation of Project Z,
Hence, cash flow after tax is from project Y is $143,500 and Project Z is $153,066.67
2.
To compute: Payback period.
2.

Explanation of Solution
Computation of payback period for project Y:
Given,
Cost of investment of Project Y is $350,000.
Annual net cash flow from Project Y is $143,500.
Formula to calculate payback period,
Substitute $350,000 for initial investment and $143,500 for net annual
Computation of payback period for project Z:
Given,
Cost of investment of Project Z is $280,000.
Annual net cash flow from Project Z is $153,066.66.
Formula to calculate payback period,
Substitute $280,000 for initial investment and $153,066.66 for net annual cash inflow.
Hence, payback period of project Y is 2.44 years and Project Z is 1.83 years.
3.
To compute: Accounting
3.

Explanation of Solution
Computation of accounting rate of return (ARR) for Project Y:
Given,
Average annual profit of Project Y is $56,000.
Average investment in Project Y is $175,000.
Formula to calculate accounting rate of return,
Substitute $56,000 for average annual profit and $175,000 for average investment.
Computation of accounting rate of return (ARR) for Project Z:
Given,
Average annual profit of Project Z is $36,400.
Average investment in Project Z is $140,000.
Formula to calculate of accounting rate of return,
Substitute $56,000 for average annual profit and $175,000 for average investment.
Working notes:
Calculation of average investment of Project Y,
Calculation of average investment of Project Z,
Hence, ARR for Project Y is 32% and Project Z is 26%.
4.
To compute:
4.

Explanation of Solution
Computation of net present value (NPV) for Project Y:
Given,
Annual net cash flows from Project Y is $143,500
Cost of investment is $350,000.
Market interest rate is 8%.
Number of periods is 4 years.
Present value factor for cumulative 4 years is 3.31.
Formula to calculate NPV,
Substitute $457,290.20 for the present value of cash flows and $350,000 for the cost of investment.
Computation of Net present value (NPV) for Project Z:
Given,
Annual net cash flow from Project Z is $153,066.66.
Cost of investment is $280,000.
Market interest rate is 8%.
Number of periods is 3 years.
Present value factor for cumulative 3 years is 2.58.
Formula to calculate NPV,
Substitute $394,467.63 for the present value of cash flows and $280,000 for the cost of investment.
Working notes:
Calculation of present value of cash flows of Project Y,
Calculation of present value of cash flows of Project Z,
Hence, NPV for project Y is $125,290.20 and Project Z is $114,467.63.
5.
To identify: Recommendation to management to pursue Project Y.
5.

Explanation of Solution
ul
Hence, it is recommended to management to pursue Project Y.
Want to see more full solutions like this?
Chapter 24 Solutions
Connect 2 Semester Access Card for Financial and Managerial Accounting
- Please don't use AI And give correct answer .arrow_forwardLouisa Pharmaceutical Company is a maker of drugs for high blood pressure and uses a process costing system. The following information pertains to the final department of Goodheart's blockbuster drug called Mintia. Beginning work-in-process (40% completed) 1,025 units Transferred-in 4,900 units Normal spoilage 445 units Abnormal spoilage 245 units Good units transferred out 4,500 units Ending work-in-process (1/3 completed) 735 units Conversion costs in beginning inventory $ 3,250 Current conversion costs $ 7,800 Louisa calculates separate costs of spoilage by computing both normal and abnormal spoiled units. Normal spoilage costs are reallocated to good units and abnormal spoilage costs are charged as a loss. The units of Mintia that are spoiled are the result of defects not discovered before inspection of finished units. Materials are added at the beginning of the process. Using the weighted-average method, answer the following question: What are the…arrow_forwardQuick answerarrow_forward
- Financial accounting questionarrow_forwardOn November 30, Sullivan Enterprises had Accounts Receivable of $145,600. During the month of December, the company received total payments of $175,000 from credit customers. The Accounts Receivable on December 31 was $98,200. What was the number of credit sales during December?arrow_forwardPaterson Manufacturing uses both standards and budgets. For the year, estimated production of Product Z is 620,000 units. The total estimated cost for materials and labor are $1,512,000 and $1,984,000, respectively. Compute the estimates for: (a) a standard cost per unit (b) a budgeted cost for total production (Round standard costs to 2 decimal places, e.g., $1.25.)arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education