1.
To compute: Annual expected net
1.
Explanation of Solution
Given below is the table for the computation of annual expected net cash flows:
Annual cash flow | ||
Particulars | Project Y ($) | Project Z ($) |
Profit after tax | 56,000 | 36,400 |
87,500 | 116,666.66 | |
Cash flows after tax | 143,500 | 153,066.66 |
Working notes:
Calculation of annual depreciation of Project Y,
Calculation of annual depreciation of Project Z,
Hence, cash flow after tax is from project Y is $143,500 and Project Z is $153,066.67
2.
To compute: Payback period.
2.
Explanation of Solution
Computation of payback period for project Y:
Given,
Cost of investment of Project Y is $350,000.
Annual net cash flow from Project Y is $143,500.
Formula to calculate payback period,
Substitute $350,000 for initial investment and $143,500 for net annual
Computation of payback period for project Z:
Given,
Cost of investment of Project Z is $280,000.
Annual net cash flow from Project Z is $153,066.66.
Formula to calculate payback period,
Substitute $280,000 for initial investment and $153,066.66 for net annual cash inflow.
Hence, payback period of project Y is 2.44 years and Project Z is 1.83 years.
3.
To compute: Accounting
3.
Explanation of Solution
Computation of accounting rate of return (ARR) for Project Y:
Given,
Average annual profit of Project Y is $56,000.
Average investment in Project Y is $175,000.
Formula to calculate accounting rate of return,
Substitute $56,000 for average annual profit and $175,000 for average investment.
Computation of accounting rate of return (ARR) for Project Z:
Given,
Average annual profit of Project Z is $36,400.
Average investment in Project Z is $140,000.
Formula to calculate of accounting rate of return,
Substitute $56,000 for average annual profit and $175,000 for average investment.
Working notes:
Calculation of average investment of Project Y,
Calculation of average investment of Project Z,
Hence, ARR for Project Y is 32% and Project Z is 26%.
4.
To compute:
4.
Explanation of Solution
Computation of net present value (NPV) for Project Y:
Given,
Annual net cash flows from Project Y is $143,500
Cost of investment is $350,000.
Market interest rate is 8%.
Number of periods is 4 years.
Present value factor for cumulative 4 years is 3.31.
Formula to calculate NPV,
Substitute $457,290.20 for the present value of cash flows and $350,000 for the cost of investment.
Computation of Net present value (NPV) for Project Z:
Given,
Annual net cash flow from Project Z is $153,066.66.
Cost of investment is $280,000.
Market interest rate is 8%.
Number of periods is 3 years.
Present value factor for cumulative 3 years is 2.58.
Formula to calculate NPV,
Substitute $394,467.63 for the present value of cash flows and $280,000 for the cost of investment.
Working notes:
Calculation of present value of cash flows of Project Y,
Calculation of present value of cash flows of Project Z,
Hence, NPV for project Y is $125,290.20 and Project Z is $114,467.63.
5.
To identify: Recommendation to management to pursue Project Y.
5.
Explanation of Solution
ul
Hence, it is recommended to management to pursue Project Y.
Want to see more full solutions like this?
Chapter 24 Solutions
FINANCIAL & MANAGERIAL ACCOUNTING
- Inventory records for Dunbar Incorporated revealed the following: Date Transaction No. of units Unit cost Apr. 1 Beginning inventory 440 $ 2.31 Apr. 20 Purchase 430 $ 2.70 Dunbar sold 600 units of inventory during the month Ending inventory assuming FIFO would be a. $1,016 b. $1,188 c. $729 d. $624arrow_forwardI need this question answer general accounting questionarrow_forwardFinancial Accounting Questionarrow_forward
- Platz Company makes chairs and planned to sell 4,100 chairs in its master budget for the coming year. The budgeted selling price is $36 per chair, variable costs are $17 per chair, and budgeted fixed costs are $45,000 per month. At the end of the year, it was determined that Platz actually sold 4,400 chairs for $145,700. Total variable costs were $50,375 and fixed costs were $38,000. The volume variance for sales revenue was: a. $14,500 unfavorable b. $11,200 favorable c. $10,800 favorable d. $12,700 favorable want solution of this questionarrow_forwardWhat is the total cost of job.... Please answer the general accounting questionarrow_forwardArmour, Inc., an advertising agency, applies overhead to jobs on the basis of direct professional labor hours. Overhead was estimated to be $226,000, direct professional labor hours were estimated to be 28,000, and direct professional labor cost was projected to be $425,000. During the year, Armour incurred actual overhead costs of $205,200, actual direct professional labor hours of 23,900, and actual direct labor costs of $333,000. By year-end, the firm's overhead wasarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education