The May 2018 revenue and cost information for McDonald Outfitters, Inc follows:
Sales Revenue (at standard) | $ 610,000 |
Cost of Goods Sold (at standard) | 348,000 |
Direct Materials Cost Variance | 1,500 F |
Direct Materials Efficiency Variance | 6,600 F |
Direct Labor Cost Variance | 4,200 U |
Direct Labor Efficiency Variance | 2,700 F |
Variable |
2,800 U |
Variable Overhead Efficiency Variance | 1,100 U |
Fixed Overhead Cost Variance | 2,300 U |
Fixed Overhead Volume Variance | 8,300 F |
Prepare a standard cost income statement for management through gross profit. Report all standard cost variances for management's use. Has management done a good or poor job of controlling costs? Explain.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
MANAGEMENT ACCOUNTING & CONTROL
STANDARD COSTS AND VARIANCE ANALYSIS
LEARNING ACTIVITY 1
Torres Company has established standard costs for the cabinet department, in which one size of MX cabinet is made. The standard costs of producing one of these MX cabinets are shown below:
Standard Cost Card – MX Cabinet
Direct Material: Lumber 50 board ft at P 4
200
Direct Labor: 8 hours at P 10
80
Overhead Costs: Variable – 8 hrs at P5
40
Fixed – 8 hrs at P3
24
Total Standard Unit Cost
344
During June 2018, 500 of these cabinets were produced. The cost of operations during the month are shown below. There is no work in process at the beginning and end of the month.
Direct material purchased: 30,000 bf at P4.10
123,000
Direct materials used: 24,000 board ft
Direct labor: 4,200 hrs at P9.50
39,900
Overhead Costs : Variable Costs
22,000
Fixed Costs
11,000…
Q.Prepare the manufacturing overhead cost budget for materials handling, setup, processing, and inspection costs.
Ti
Cost of good sold is US$ 30,000; Target ending inventory US$8,0003; beginning inventory is US$10,000. What is budgeted purchase?
O a. US$28,000
O b. US$48,000
O c. US$38,000
O d. US$32,000
age
EVIOUS ACTIVITY
pter 1: Introduction to Management Accounting
NEXT ACTIVITY
Chapter 2: Variance analysis
Jump to...
Chapter 23 Solutions
ACCOUNTING PRINCIPLES V1 6/17 >C<
Ch. 23 - Prob. 1QCCh. 23 - MajorNet Systems is a start-up company that makes...Ch. 23 - MajorNet Systems is a start-up company that makes...Ch. 23 - MajorNet Systems is a start-up company that makes...Ch. 23 - MajorNet Systems has budgeted three hours of...Ch. 23 - MajorNet Systems has budgeted three hours of...Ch. 23 - FrontGrade Systems allocates manufacturing...Ch. 23 - FrontGrade Systems allocates manufacturing...Ch. 23 - FrontGrade Systems allocates manufacturing...Ch. 23 - The person probably most responsible for the...
Ch. 23 - HajorNet System’s static budget predicted...Ch. 23 - What is a variance?Ch. 23 - Explain the difference between a favorable and an...Ch. 23 - What is a static budget performance report?Ch. 23 - How do flexible budgets differ from static...Ch. 23 - How is a flexible budget used?Ch. 23 - What are the two components of the static budget...Ch. 23 - What is a flexible budget performance report?Ch. 23 - What is a standard cost system?Ch. 23 - Explain the difference between a cost standard and...Ch. 23 - Give the general formulas for determining cost and...Ch. 23 - How does the static budget affect cost and...Ch. 23 - List the direct materials variances, and briefly...Ch. 23 - List the direct labor variances, and briefly...Ch. 23 - List the variable overhead variances, and briefly...Ch. 23 - List the fixed overhead variances, and briefly...Ch. 23 - How is the fixed overhead volume variance...Ch. 23 - What is management by exception?Ch. 23 - List the eight product variances and the manager...Ch. 23 - Briefly describe how journal entries differ in a...Ch. 23 - What is a standard cost income statement?Ch. 23 - Matching terms Learning Objective 1 Match each...Ch. 23 - Preparing flexible budgets Learning Objective 1...Ch. 23 - Calculating flexible budget variances Learning...Ch. 23 - Matching terms Learning Objective 2 Match each...Ch. 23 - Identifying the benefits of standard costs...Ch. 23 - Calculating materials variances Learning Objective...Ch. 23 - Calculating labor variances Learning Objective 3...Ch. 23 - Interpreting material and labor variances Learning...Ch. 23 - Computing standard overhead allocation rates...Ch. 23 - Computing overhead variances Learning Objective 4...Ch. 23 - Understanding variance relationships Learning...Ch. 23 - Journalizing materials entries Learning Objectives...Ch. 23 - Journalizing labor entries Learning Objectives 6...Ch. 23 - Preparing a standard cost income statement...Ch. 23 - Preparing a flexible budget Learning Objective 1...Ch. 23 - Preparing a flexible budget performance report...Ch. 23 - Preparing a flexible budget performance report...Ch. 23 - Defining the benefits of setting cost standards...Ch. 23 - Calculating materials and labor variances Learning...Ch. 23 - Computing overhead variances Learning Objective 4...Ch. 23 - Calculating overhead variances Learning Objective...Ch. 23 - Preparing a standard cost income statement...Ch. 23 - Preparing journal entries Learning Objective 6 MOH...Ch. 23 - Preparing a standard cost income statement...Ch. 23 - Preparing a flexible budget performance report...Ch. 23 - Preparing a flexible budget computing standard...Ch. 23 - Computing standard cost variances and reporting to...Ch. 23 - Computing and journalizing standard cost variances...Ch. 23 - Prob. P23.29APGACh. 23 - Preparing a flexible budget performance report...Ch. 23 - Preparing a flexible budget and computing standard...Ch. 23 - Prob. P23.32BPGBCh. 23 - Prob. P23.33BPGBCh. 23 - Preparing a standard cost income statement...Ch. 23 - Prob. P23.35CTCh. 23 - Preparing a flexible budget and performance report...Ch. 23 - Prob. 23.1TIATCCh. 23 - Decision Case 23-1 Suppose you manage the local...Ch. 23 - Fraud Case 23-1 Drew Castello, general manager of...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Quality Cost Report Loring Company had total sales of 2,400,000 for fiscal 20X1. The costs of quality-related activities are given below. Required: 1. Prepare a quality cost report, classifying costs by category and expressing each category as a percentage of sales. What message does the cost report provide? 2. Prepare a bar graph and pie chart that illustrate each categorys contribution to total quality costs. Comment on the significance of the distribution.arrow_forwardQuality Cost Report Evans Company had total sales of $1,800,000 for fiscal 20x5. The costs of quality-related activities are given below. Returns/allowances $90,000 Design changes 81,000 Prototype inspection 3,600 Downtime 81,000 Quality circles 5,400 Packaging inspection 5,400 Field testing 3,600 Complaint adjustment 117,000 Required: Question Content Area 1. Prepare a quality cost report, classifying costs by category and expressing each category as a percentage of sales. Round percentages to one decimal place, when rounding is required. For example, 5.78% would be entered as "5.8". Evans CompanyQuality Cost ReportFor the Year Ended 20x5 Quality Costs Total Percentage of Sales Prevention costs: $- Select - - Select - $- Select - - Select -% Appraisal costs: $- Select - - Select - - Select - - Select - Internal failure costs: $- Select - - Select - - Select - - Select - External…arrow_forwardiiarrow_forward
- Please do not give solution in image format thankuarrow_forwardDo not give image formatarrow_forwardA manufacturer uses activity-based costing to assign overhead costs to products. Budgeted cost information for selected activities for next year follows. Activity Purchasing Cleaning factory Providing utilities Activity cost pool Purchasing Factory Expected Cost $127,600 31,500 63,070 Expected Costs Compute activity rates for each of the cost pools. (Round your answers to 2 decimal places.) Expected Amount of Cost Driver Cost Driver Purchase orders Square feet Square feet 4,400 4,900 Activity Overhead Rate Expected Usage of Cost Driver 4,488 purchase orders 4,900 square feet 4,900 square feet per purchase order per square footarrow_forward
- need answer asaaaparrow_forwardKobe, Inc. had the following information relating to 2020. Budgeted factory overhead ₱ 74,800 Actual factory overhead ₱ 78,300 Applied factory overhead ₱ 76,500 Estimated labor hours 44,000 If Kobe decides to use the actual results from 2020 to determine the 2021 overhead rate, what will the 2021 overhead rate be? Show solution Group of answer choices ₱1.779 ₱1.740 ₱1.650 ₱1.738arrow_forwardQuestion 2) Textbook Exercise 14-22: Cost allocation and decision making.arrow_forward
- A4arrow_forwardeBook Question Content Area Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Santiago Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 78,000 units of product were as follows: Line Item Description Standard Costs Actual Costs Direct materials 202,800 lbs. at $4.60 per lb. 200,800 lbs. at $4.40 per lb. Direct labor 19,500 hrs. at $18.60 per hr. 19,950 hrs. at $18.80 per hr. Factory overhead Rates per direct labor hr., based on 100% of normal capacity of 20,350 direct labor hrs.: Factory overhead Variable cost, $3.60 $69,500 variable cost Factory overhead Fixed cost, $5.70 $115,995 fixed cost Each unit requires 0.25 hour of direct labor. Required: a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative…arrow_forwardDon't give answer in image formatarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningSurvey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY