Explanation of Solution

When a project is planned, milestones need to be defined. Milestones are associated with a single task or with a group of related tasks. The independent tasks are carried out parallel. A task which is dependent on another task is performed after that particular task is complete.

Bar Chart:

The bar chart that shows the project schedule is given below.

Explanation:

  • The time duration taken by the task T1 is 10.
  • Task T2 starts after task T1 completes because task T2 depends on task T1 and it will take time duration of 15 and is indicated as a milestone M1.
  • Task T3 starts after task T2 completes because task T3 depends on task T1 and T2 and it will take time duration of 10 and is indicated as a milestone M2.
  • Task T4 does not have any dependencies. So it will start at the beginning of the project by taking time duration of 20.
  • Task T5 also does not have any dependencies. So it will start at the beginning of the project by taking time duration of 10.
  • Task T6 starts after task T3 completes because task T6 depends on task T3 and T4 and it will take time duration of 15 and is indicated as a milestone M3.
  • Task T7 starts after task T3 completes because task T7 depends on task T3 and it will take time duration of 20 and is indicated as a milestone M4...

Blurred answer
Students have asked these similar questions
Implementation of an Integrated Inventory Management System at Green Fields Manufacturing” Green Fields Manufacturing is a mid-sized company specialising in eco-friendly home and garden products. In recent years, growing demand has exposed the limitations of their fragmented processes and outdated systems. Different departments manage production schedules, raw material requirements, and finished goods inventory using a patchwork of spreadsheets and older software tools. These silos create inconsistent data, errors in stock levels, delivery delays, and customer dissatisfaction.  Green Fields plans to implement an Integrated Inventory Management System to centralise production, procurement, inventory, and sales data to address these challenges. This technology aims to provide real-time visibility into stock levels, automate reorder points, and generate analytical dashboards for managers at both operational and strategic levels. Ultimately, the new system will streamline workflows, reduce…
. Differentiate between continuous and discrete systems. How does their nature affect the selection of simulation techniques?
hi, I need help to resolve the case, thank you
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
C++ for Engineers and Scientists
Computer Science
ISBN:9781133187844
Author:Bronson, Gary J.
Publisher:Course Technology Ptr
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Programming Logic & Design Comprehensive
Computer Science
ISBN:9781337669405
Author:FARRELL
Publisher:Cengage