To determine

Find the equivalent annual worth of the cash flow diagram.

Expert Solution & Answer
Check Mark

Answer to Problem 17P

The equivalent annual worth of the cash flow diagram is $3868.37.

Explanation of Solution

Given data:

The normal interest rate (i) is 8%.

Formula used:

Formula to calculate the annual worth for the given cash flow diagram is,

AW=[$5000(PA,i,n)(AP,i,n)$2000(PA,i,n)(PF,i,n)(AP,i,n)+$8000(PF,i,n)(AP,i,n)+$5000(AF,i,n)] (1)

Here,

F is the future cost,

P is the present cost,

A is the uniform series payment,

i is the normal interest rate, and

n is the number of years.

Refer the Problem 20.17 Figure in the textbook, the equation (1) is rewritten with respect to the given number of years is,

AW=[$5000(PA,i,6)(AP,i,10)$2000(PA,i,3)(PF,i,4)(AP,i,10)+$8000(PF,i,8)(AP,i,10)+$5000(AF,i,10)] (2)

Formula to calculate the present cost for the given uniform series payment is,

(PA,i,n)=[(1+i)n1i(1+i)n] (3)

Formula to calculate the uniform series payment for the given present cost is,

(AP,i,n)=[i(1+i)n(1+i)n1] (4)

Formula to calculate the present cost for the given future cost is,

(PF,i,n)=[1(1+i)n] (5)

Formula to calculate the uniform series payment for the given future cost is,

(AF,i,n)=[i(1+i)n1] (6)

Calculation:

To calculate the equivalent annual worth of the cash flow diagram:

Substitute 8% for i, and 6 for n in equation (3) to find (PA,i,6).

(PA,i,6)=[(1+(8%))61(8%)(1+(8%))6]=[(1+0.08)610.08(1+0.08)6]=4.623

Substitute 8% for i, and 10 for n in equation (4) to find (AP,i,10).

(AP,i,10)=[(8%)(1+(8%))10(1+(8%))101]=[0.08(1+0.08)10(1+0.08)101]=0.149

Substitute 8% for i, and 3 for n in equation (3) to find (PA,i,3).

(PA,i,3)=[(1+(8%))31(8%)(1+(8%))3]

(PA,i,3)=[(1+0.08)310.08(1+0.08)3]=2.577

Substitute 8% for i, and 4 for n in equation (5) to find (PF,i,4).

(PF,i,4)=[1(1+(8%))4]=[1(1+0.08)4]=0.735

Substitute 8% for i, and 8 for n in equation (5) to find (PF,i,8).

(PF,i,8)=[1(1+(8%))8]=[1(1+0.08)8]=0.540

Substitute 8% for i, and 10 for n in equation (6) to find (AF,i,10).

(AF,i,10)=[(8%)(1+(8%))101]=[0.08(1+0.08)101]=0.069

Substitute 4.623 for (PA,i,6), 0.149 for (AP,i,10), 2.577 for (PA,i,3), 0.735 for (PF,i,4), 0.540 for (PF,i,8), and 0.069 for (AF,i,10) in equation (2) to find AW.

AW=[$5000(4.623)(0.149)$2000(2.577)(0.735)(0.149)+$8000(0.540)(0.149)+$5000(0.069)]=$3868.37

Therefore, the equivalent annual worth of the cash flow diagram is $3868.37.

Conclusion:

Thus, the equivalent annual worth of the cash flow diagram is $3868.37.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Q1/ The specific gravity of the soil is 1.41 percentage of water content by weight at field capacity and wilting point are 15% and 7% respectively calculate the equivalent moisture content as equivalent depth for 1.2m root zone : 1. at permanent wilting point 2. at field capacity 3. for ready available water
Kindy explain the pie chart percentage and give some related study and references about Value of travel time connected to the pie chart
Consider the specifications for an asphaltic concrete mixture and the results of a sieve analysis below. Coarse aggregates: Fine aggregates: Filler: 60% 35% 5% Percent of Weight of Aggregate or Filler Passing Sieve Designation Retained on Sieve Designation Coarse Aggregate Fine Aggregate Mineral Filler 3/4 in. (19 mm) 1/2 in. 6 1/2 in. (12.5 mm) 3/8 in. 15 3/8 in. (9.5 mm) No. 4 50 - No. 4 (4.75 mm) No. 10 20 1 No. 10 (2 mm) No. 40 (0.425 mm) No. 40 9 35 - No. 80 31 40 No. 80 (0.180 mm) No. 200 (0.075 mm) Total No. 200 - 33 - - 25 35 100 100 100 Determine the proportion of different aggregates to obtain the required gradation. Percent of Total Weight of Mixture Passing Sieve Designation Retained on Sieve Designation Coarse Aggregate Fine Aggregate 3/4 in. (19 mm) 1/2 in. (12.5 mm) 3/8 in. (9.5 mm) 1/2 in. 3/8 in. No. 4 No. 4 (4.75 mm) No. 10 No. 10 (2 mm) No. 40 No. 40 (0.425 mm) No. 80 No. 80 (0.180 mm) No. 200 No. 200 (0.075 mm) Total Need Help? Read It Mineral Filler Total 100
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning