Concept explainers
a.
Construct a payoffs table.
a.

Explanation of Solution
On observing the given information, it is clear that the lease about for a complete part set for summer season is $560. The rental amount per day is $5. Profit for each set for the first season is $10.
If the firm leased 41 complete sets, the profit for only 41 sets rented is shown below:
If the firm leased 42 complete sets, the profit for only 41 sets rented is shown below:
In a similar way, the calculations are obtained.
The payoffs are computed as follows:
Act | 41 | 42 | 43 | 44 | 45 | 46 |
41 | $410 | $410 | $410 | $410 | $410 | $410 |
42 | $405 | $420 | $420 | $420 | $420 | $420 |
43 | $400 | $415 | $430 | $430 | $430 | $430 |
44 | $395 | $410 | $425 | $440 | $440 | $440 |
45 | $390 | $405 | $420 | $435 | $450 | $450 |
46 | $385 | $400 | $415 | $430 | $445 | $460 |
b.
Find the expected payoffs for leasing 41, 42, and 44 complete sets from the Boston firms .
Give the recommended decision.
b.

Answer to Problem 17CE
The expected payoffs are given below:
Event | Expected payoffs |
41 | $410 |
42 | $419.1 |
43 | $426.70 |
44 | $432.20 |
45 | $431.70 |
46 | $427.45 |
Explanation of Solution
The expected profit for 41 sets is shown below:
Event | Payoff value | Probability | Expected payoffs |
41 | $410 | ||
42 | $410 | ||
43 | $410 | ||
44 | $410 | ||
45 | $410 | ||
46 | $410 | ||
Expected profit( | $410 |
The expected profit for 42 sets is shown below:
Event | Payoff value | Expected payoffs |
41 | $405 | |
42 | $420 | |
43 | $420 | |
44 | $420 | |
45 | $420 | |
46 | $420 | |
Expected profit( | $419.10 |
The expected profit for 43 sets is shown below:
Event | Payoff value | Expected payoffs |
41 | $400 | |
42 | $415 | |
43 | $430 | |
44 | $430 | |
45 | $430 | |
46 | $430 | |
Expected profit( | $426.70 |
Therefore, the expected profit for all the sets will be obtained in the same way.
The expected profit all the events is shown below:
Event | Expected payoffs |
41 | $410 |
42 | $419.1 |
43 | $426.70 |
44 | $432.20 |
45 | $431.70 |
46 | $427.45 |
c.
Identify the most profitable alternative based on the expected daily profit.
c.

Explanation of Solution
The expected profit for the event
Thus, the event
Hence, order 44 sets because the expected profit of $432.20 is the highest.
d.
Obtain the expected opportunity loss for 41, 42, and 43.
d.

Answer to Problem 17CE
The expected opportunity loss table is obtained as follows:
Act | ||||||
41 | 42 | 43 | 44 | 9 | 45 | |
Expected opp. loss | $28.3 | $19.2 | $11.6 | $6.10 | $6.60 | $10.85 |
Explanation of Solution
Opportunity loss:
From the table in Part (a) if the Supply
Then, the opportunity loss is obtained by taking the difference between $410 and $410 That is,
Thus, the opportunity loss for
In the same way, the remaining values in the table are obtained. If the Supply
Then, the opportunity loss is obtained by taking the difference between $410 and $405, that is,
Thus, the opportunity loss for
The opportunity loss table is obtained as follows:
Supply | Opportunity loss | |||||
41 | 42 | 43 | 44 | 45 | 46 | |
41 | $0 | $10 | $20 | $30 | $40 | $50 |
42 | $5 | $0 | $10 | $20 | $30 | $40 |
43 | $10 | $5 | $0 | $10 | $20 | $30 |
44 | $15 | $10 | $5 | $0 | $10 | $20 |
45 | $20 | $15 | $10 | $5 | $0 | $10 |
46 | $25 | $20 | $15 | $10 | $5 | $0 |
Then, the expected opportunity loss for 41 sets is calculated as follows:
Thus, the expected opportunity loss for 41 sets is $28.3.
The expected opportunity loss for 42 sets is calculated as follows:
Thus, the expected opportunity loss for 42 sets is $19.2.
The expected opportunity loss for 43 sets is calculated as follows:
Thus, the expected opportunity loss for 42 sets is $11.6.
In the same way, the remaining values are obtained. The expected opportunity losses are shown below:
Act | ||||||
41 | 42 | 43 | 44 | 9 | 45 | |
Expected opp. loss | $28.3 | $19.2 | $11.6 | $6.10 | $6.60 | $10.85 |
e.
Obtain the most profitable course of action to take based on the expected opportunity loss table.
State whether the decision made in Part (c) is agreed in this context.
e.

Explanation of Solution
On observing the table in Part (d), the opportunity loss when ordering 44 sets is minimum. Therefore, ordering 44 sets is most profitable.
Both the results stated in Part (c) and Part (e) conclude with the same results. Therefore, the result obtained in Part (c) is agreed with result in this context.
f.
Obtain the
f.

Answer to Problem 17CE
The expected value of perfect information is $6.10.
Explanation of Solution
It is given that
The above calculations show that the EMV for the ordering 44 sets is the maximum at $432.20.
In order to maximize the profit, it is appropriate to order 44.
The expected value of perfect information can be calculated using the following formula:
The expected monetary values calculated above provide the expected values under conditions of uncertainty.
Now, under conditions of certainty, the maximum rent
Using the probabilities, the expected value under conditions of certainty is calculated below:
Hence, the expected value of perfect information is calculated below:
Thus, the expected value of perfect information is $6.10.
On observing the evidence stated in the previous parts, the maximum amount to be paid for the perfect information is $6.10.
Want to see more full solutions like this?
Chapter 20 Solutions
STATISTICAL TECHNIQUES FOR BUSINESS AND
- According to flightstats.com, American Airlines flights from Dallas to Chicago are on time 80% of the time. Suppose 10 flights are randomly selected, and the number of on-time flights is recorded. (a) Explain why this is a binomial experiment. (b) Determine the values of n and p. (c) Find and interpret the probability that exactly 6 flights are on time. (d) Find and interpret the probability that fewer than 6 flights are on time. (e) Find and interpret the probability that at least 6 flights are on time. (f) Find and interpret the probability that between 4 and 6 flights, inclusive, are on time.arrow_forwardShow how you get critical values of 1.65, -1.65, and $1.96 for a right-tailed, left- tailed, and two-tailed hypothesis test (use a = 0.05 and assume a large sample size).arrow_forwardSuppose that a sports reporter claims the average football game lasts 3 hours, and you believe it's more than that. Your random sample of 35 games has an average time of 3.25 hours. Assume that the population standard deviation is 1 hour. Use a = 0.05. What do you conclude?arrow_forward
- Suppose that a pizza place claims its average pizza delivery time is 30 minutes, but you believe it takes longer than that. Your sample of 10 pizzas has an average delivery time of 40 minutes. Assume that the population standard deviation is 15 minutes and the times have a normal distribution. Use a = 0.05. a. What are your null and alternative hypotheses? b. What is the critical value? c. What is the test statistic? d. What is the conclusion?arrow_forwardTable 5: Measurement Data for Question 9 Part Number Op-1, M-1 Op-1, M-2 | Op-2, M-1 Op-2, M-2 | Op-3, M-1 Op-3, M-2 1 21 20 20 20 19 21 2 24 23 24 24 23 24 3 4 5 6 7 8 9 10 11 21 12 8222332 201 21 20 22 20 22 27 27 28 26 27 28 19 18 19 21 24 21 22 19 17 18 24 23 25 25 23 26 20 20 18 19 17 13 23 25 25 2 3 3 3 3 2 3 18 18 21 21 23 22 24 22 20 19 23 24 25 24 20 21 19 18 25 25 14 24 24 23 25 24 15 29 30 30 28 31 16 26 26 25 26 25 17 20 20 19 20 20 843882388 20 18 25 20 19 25 25 30 27 20 18 19 21 19 19 21 23 19 25 26 25 24 25 25 20 19 19 18 17 19 17 Question 9 A measurement systems experiment involving 20 parts, three operators (Op-1, Op-2, Op-3), and two measure- ments (M-1, M-2) per part is shown in Table 5. (a) Estimate the repeatability and reproducibility of the gauge. (b) What is the estimate of total gauge variability?" (c) If the product specifications are at LSL = 6 and USL 60, what can you say about gauge capability?arrow_forwardQuestion 5 A fraction nonconforming control chart with center line 0.10, UCL = 0.19, and LCL = 0.01 is used to control a process. (a) If three-sigma limits are used, find the sample size for the control charte 2 (b) Use the Poisson approximation to the binomial to find the probability of type I error. (c) Use the Poisson approximation to the binomial to find the probability of type II error if the process fraction defective is actually p = 0.20.arrow_forward
- Question 8 Ten parts are measured three times by the same operator in a gauge capability study. The data are shown in Table 4. (a) Describe the measurement error that results from the use of this gauge. I (b) Estimate total variability and product variability. (c) What percentage of total variability is due to the gauge? (d) If specifications on the part are at 100±15, find the P/T ratio for this gauge. Comment on the adequacy of the gauge. 3 Table 4: Measurement Data for Question 8 Part Number Measurement 1 Measurement 2 Measurement 3 1 2 100 95 101 100 93 97 3 101 103 100 4 96 95 97 5 98 98 96 6 99 98 98 7889 95 97 98 100 99 98 100 100 97 10 100 98 98 99arrow_forwardQuestion 6 The data shown in Table 3 are and R values for 24 samples of size n = 5 taken from a process producing bearings. The measurements are made on the inside diameter of the bearing, with only the last three decimals recorded (i.e., 34.5 should be 0.50345). Perform a process capability analysis using and R charts for the data from Table 3. Table 3: Data for Question 6 Sample Number R | Sample Number I Ꭱ 1 34.5 3 13 35.4 8 2 34.2 4 14 34.0 6 ∞∞ 31.6 15 37.1 5 4 31.5 4 16 34.9 7 56789 35.0 5 17 33.5 4 34.1 6 18 31.7 3 32.6 4 19 34.0 8 33.8 3 20 35.1 4 34.8 7 10 33.6 8 11 31.9 3 12 38.6 9 2232 21 33.7 2 32.8 1 33.5 24 34.2 2 32 3arrow_forwardQuestion 1 The commercial loan operation of a financial institution has a standard for processing new loan applications in 24 hours. Table 1 shows the number of applications processed each day for the last 20 days and the number of applications that required more than 24 hours to complete. Table 1: Loan Application Data for Question 1 Day Applications Late Day Applications Late 1 200 3 11 219 0 2 250 4 12 238 10 3 240 2 13 250 4 4 300 5 14 302 6 5 200 2 15 219 20 6 250 4 16 246 3 7 246 3 17 251 6 8 258 5 18 273 7 9 275 2 19 245 3 10 274 1 20 260 (a) Set up the fraction nonconforming control chart for this process. Use the variable-width control limit approach. Plot the preliminary data in Table 1 on the chart. Is the process in statistical control? (b) Assume that assignable causes can be found for any out-of-control points on this chart. What center line should be used for process monitoring in the next period, and how should the control limits be calculated?arrow_forward
- help me with ab please. please handwrite if possible. please don't use AI tools to answerarrow_forwardhelp me with ab please. please handwrite if possible. please don't use AI tools to answerarrow_forwardhelp me with abcd please. please handwrite if possible. please don't use AI tools to answerarrow_forward
- MATLAB: An Introduction with ApplicationsStatisticsISBN:9781119256830Author:Amos GilatPublisher:John Wiley & Sons IncProbability and Statistics for Engineering and th...StatisticsISBN:9781305251809Author:Jay L. DevorePublisher:Cengage LearningStatistics for The Behavioral Sciences (MindTap C...StatisticsISBN:9781305504912Author:Frederick J Gravetter, Larry B. WallnauPublisher:Cengage Learning
- Elementary Statistics: Picturing the World (7th E...StatisticsISBN:9780134683416Author:Ron Larson, Betsy FarberPublisher:PEARSONThe Basic Practice of StatisticsStatisticsISBN:9781319042578Author:David S. Moore, William I. Notz, Michael A. FlignerPublisher:W. H. FreemanIntroduction to the Practice of StatisticsStatisticsISBN:9781319013387Author:David S. Moore, George P. McCabe, Bruce A. CraigPublisher:W. H. Freeman





