To determine

(a)

The volume of traffic across the bridge.

Expert Solution
Check Mark

Answer to Problem 3P

The volume of traffic across the bridge is 333.33veh/hr.

Explanation of Solution

Given:

The total cost to travel across bridge except tolls is expressed as,

  C=50+0.5V.

Here, V is the number of vehicles per hour and C is the cost/veh in cents.

The demand to travel across the bridge is,

  V=250010C.

Calculations:

Calculate volume of traffic across the bridge.

The total cost to travel across bridge except tolls is,

  C=50+0.5V ....... (I)

The volume across the bridge is,

  V=250010C ....... (II)

Solve Equations (I) and (II).

  C=216.67

  V=333.33

Conclusion:

Therefore, the volume of traffic across the bridge is 333.33veh/hr.

To determine

(b)

The volume of traffic across the bridge if a toll of 25cents is added and for 50cents increase.

Expert Solution
Check Mark

Answer to Problem 3P

The volume of traffic across the bridge if a toll of 25cents is added is 291.67veh/hr and for 50cents increase is 327.49veh/hr.

Explanation of Solution

Concept used:

Write the expression to calculate the volume expected for a 50cents increase.

  V=V(V new50)

Here, Vnew is the volume of traffic across the bridge if toll is increased to 25cents and V is the volume of traffic across the bridge.

Calculations:

Calculate volume of traffic across the bridge if toll is increased to 25cents.

The new cost of the cost of travel across bridge is,

  C=50+0.5V+25

Substitute (50+0.5V+25) for C in Equation (II).

  V=2,50010(50+0.5V+25)V=2,5005005V2506V=1,750V=291.67

Calculate volume of traffic expected for a 50cents increase.

Substitute 333.33veh/hr for Vnew and 291.67veh/hr for V in Equation (II).

  V=333.33veh/hr( 291.67 veh/ hr 50)=333.33veh/hr5.8334veh/hr=327.49veh/hr

Conclusion:

Therefore, the volume of traffic across the bridge if a toll of 25cents is added is 291.67veh/hr and for 50cents increase is 327.49veh/hr.

To determine

(c)

The volume of traffic across the bridge.

Expert Solution
Check Mark

Answer to Problem 3P

The volume of traffic across the bridge is 666.67veh/hr.

Explanation of Solution

Given:

The total cost to travel across bridge including toll is expressed as,

  C=50+0.2V

Calculations:

Calculate volume of traffic across the bridge.

Substitute (50+0.2V) for C in equation (II).

  V=2,50010(50+0.2V)V=2,5005002V3V=2,000V=666.67

Conclusion:

Therefore, the volume of traffic across the bridge is 666.67veh/hr.

To determine

(d)

The toll to yield the highest revenue for demand and supply function and the associated demand and revenue.

Expert Solution
Check Mark

Answer to Problem 3P

The toll which yield the highest revenue for demand and supply function is $1.00, associated demand is 166.67veh/hr and revenue. $16,666,67 per hour.

Explanation of Solution

Concept used:

Write the expression to calculate the revenue generated.

  R=V×T ....... (III)

Here, R is the revenue and T is the toll.

Calculations:

Assume the toll rate as T to yield highest revenue.

The new cost of the cost of travel across bridge is,

  C=50+0.5V+T

Substitute (50+0.5V+T) for C in Equation (II).

  V=2,50010(50+0.5V+T)V=2,5005005V10T6V=2,00010TV=2,00010T6 ....... (IV)

Substitute (2,00010T6) for V in Equation (III).

  R=( 2,00010T6)×T=2,000T10T26 ....... (V)

From the above equation, the toll which would yield the maximum revenue is 100 cents or $1.00.

Substitute 100 for T in Equation (V).

  R=2,000( 100)10 ( 100 )26=2,00,0001,00,0006=1,00,0006=16,666,67

Calculate the demand for travel across the bridge for maximum revenue.

Substitute 100 for T in equation (IV).

  V=2,00010( 100)6=2,0001,0006=1,0006=166.67

Conclusion:

Therefore, the toll which yield the highest revenue for demand and supply function is $1.00, associated demand is 166.67veh/hr and revenue. $16,666,67 per hour.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Hi! Kindly help me compute the following based on the attached elevation plan and floor plan: Total Perimeter of the building – to be used for layouting. Total Length of Batter Board – include all sides where batter boards will be installed. Number and spacing of Stakes – assuming a stake is placed every 1.2 meters along the perimeter. Please show the complete solution and breakdown of your computation. Thank you!
E D (B) (<) 2945 3725 250 2225 Car Port 5000 2500 Pool Area 2 3925 3465 2875 13075 Staff Room Bar Counter 1 GROUND FLOOR PLAN SCALE 1:100 Hallway 3 1560 4125 3125 $685 Laundry & Service Area 5 A Common T&B Kitchen & Dining Arear B Living Area 2425 Terrace E 2 12150 1330 2945 4150 5480 1800 3725 1925 3800 3465 2 3 9150 4125 3575 3925 Terrace Toilet & Bathroom Toilet Bathroom Bedroom 1 Bedroom 2 SECOND FLOOR PLAN SCALE Hallway 1:100 OPEN TO BELOW E B A 3 3725 2150 1330 2945 5480 4150 1925 ⑨ 2 9150 3800 4125 3465 3575 3925 Terrace R Toilet & Bathroom Toilet & Bathroom SECOND FLOOR PLAN SCALE Hallway 1:100 OPEN TO BELOW +
Q2/ In a design of a portable sprinkler system, the following information is given: • • The sprinklers are distributed in a square pattern with radius of the wetted circle of the sprinkler=15 m Consumption rate = 10 mm/day Efficiency of irrigation = 60% Net depth of irrigation (NDI)= 80 mm. Find the following: 1-Sprinkler application rate if HRS = 11. 2-Number of pipes required for irrigation. (50 Marks) 3-Discharge of sprinkler, diameter of nozzle, and the working head pressure if C=0.90. 4-Diameter of the sprinkler pipe for Slope=0. 5-Pressure head at the inlet and at the dead end of the sprinkler pipe for Slope=0. (F² + L²)((SF)² + L²) L² 2L² ≤ D² L² + S² ≤ D² A, = * 1000 S*L ≤D² N W Af m-11-P L' Hf = 1.14*109 * 1.852 * L *F,where c=120 D4.87 Source main pipe 180 m 540 m N 1 1 √m-1 F = im/Nm+1 = + + m+1 2N 6N2 i=1 Nozzle diameter (mm) 3< ds 4.8 4.8< ds 6.4 6.4
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning