To determine

(a)

The volume of traffic across the bridge.

Expert Solution
Check Mark

Answer to Problem 3P

The volume of traffic across the bridge is 333.33veh/hr.

Explanation of Solution

Given:

The total cost to travel across bridge except tolls is expressed as,

  C=50+0.5V.

Here, V is the number of vehicles per hour and C is the cost/veh in cents.

The demand to travel across the bridge is,

  V=250010C.

Calculations:

Calculate volume of traffic across the bridge.

The total cost to travel across bridge except tolls is,

  C=50+0.5V ....... (I)

The volume across the bridge is,

  V=250010C ....... (II)

Solve Equations (I) and (II).

  C=216.67

  V=333.33

Conclusion:

Therefore, the volume of traffic across the bridge is 333.33veh/hr.

To determine

(b)

The volume of traffic across the bridge if a toll of 25cents is added and for 50cents increase.

Expert Solution
Check Mark

Answer to Problem 3P

The volume of traffic across the bridge if a toll of 25cents is added is 291.67veh/hr and for 50cents increase is 327.49veh/hr.

Explanation of Solution

Concept used:

Write the expression to calculate the volume expected for a 50cents increase.

  V=V(V new50)

Here, Vnew is the volume of traffic across the bridge if toll is increased to 25cents and V is the volume of traffic across the bridge.

Calculations:

Calculate volume of traffic across the bridge if toll is increased to 25cents.

The new cost of the cost of travel across bridge is,

  C=50+0.5V+25

Substitute (50+0.5V+25) for C in Equation (II).

  V=2,50010(50+0.5V+25)V=2,5005005V2506V=1,750V=291.67

Calculate volume of traffic expected for a 50cents increase.

Substitute 333.33veh/hr for Vnew and 291.67veh/hr for V in Equation (II).

  V=333.33veh/hr( 291.67 veh/ hr 50)=333.33veh/hr5.8334veh/hr=327.49veh/hr

Conclusion:

Therefore, the volume of traffic across the bridge if a toll of 25cents is added is 291.67veh/hr and for 50cents increase is 327.49veh/hr.

To determine

(c)

The volume of traffic across the bridge.

Expert Solution
Check Mark

Answer to Problem 3P

The volume of traffic across the bridge is 666.67veh/hr.

Explanation of Solution

Given:

The total cost to travel across bridge including toll is expressed as,

  C=50+0.2V

Calculations:

Calculate volume of traffic across the bridge.

Substitute (50+0.2V) for C in equation (II).

  V=2,50010(50+0.2V)V=2,5005002V3V=2,000V=666.67

Conclusion:

Therefore, the volume of traffic across the bridge is 666.67veh/hr.

To determine

(d)

The toll to yield the highest revenue for demand and supply function and the associated demand and revenue.

Expert Solution
Check Mark

Answer to Problem 3P

The toll which yield the highest revenue for demand and supply function is $1.00, associated demand is 166.67veh/hr and revenue. $16,666,67 per hour.

Explanation of Solution

Concept used:

Write the expression to calculate the revenue generated.

  R=V×T ....... (III)

Here, R is the revenue and T is the toll.

Calculations:

Assume the toll rate as T to yield highest revenue.

The new cost of the cost of travel across bridge is,

  C=50+0.5V+T

Substitute (50+0.5V+T) for C in Equation (II).

  V=2,50010(50+0.5V+T)V=2,5005005V10T6V=2,00010TV=2,00010T6 ....... (IV)

Substitute (2,00010T6) for V in Equation (III).

  R=( 2,00010T6)×T=2,000T10T26 ....... (V)

From the above equation, the toll which would yield the maximum revenue is 100 cents or $1.00.

Substitute 100 for T in Equation (V).

  R=2,000( 100)10 ( 100 )26=2,00,0001,00,0006=1,00,0006=16,666,67

Calculate the demand for travel across the bridge for maximum revenue.

Substitute 100 for T in equation (IV).

  V=2,00010( 100)6=2,0001,0006=1,0006=166.67

Conclusion:

Therefore, the toll which yield the highest revenue for demand and supply function is $1.00, associated demand is 166.67veh/hr and revenue. $16,666,67 per hour.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A bridge has been constructed between the mainland and an island. The total cost (excludingtolls) to travel across the bridge is expressed as C = 50 + 0.5V, where V is the number ofveh/hr and C is the cost/veh in pesos. The demand for travel across the bridge is V = 2500 −10C.a. Determine the volume of traffic across the bridge.b. If a toll of 25 pesos is added, what is the volume across the bridge?c. A tollbooth is to be added, thus reducing the travel time to cross the bridge. The new costfunction is C = 50 + 0.2V. Determine the volume of traffic that would cross the bridge.
A bridge has been constructed between the mainland and an island. The total cost (excluding tolls) to travel across the bridge is expressed as C = 50 + 0.5V, where V is the number of veh/hr and C is the cost/vehicle in cents. The demand for travel across the bridge is V = 2500 - 10C.
A toll bridge carries 10,000 veh/day. The current toll is ₱150/vehicle. Studies shown that for eachincrease in toll of ₱25, the traffic volume will decrease by 1000 veh/day. It is desired to increasethe toll to a point where revenue will be maximized.a. Write the expression for travel demand on the bridge related to toll increase and currentvolume. b. Determine the toll charge to maximize revenues. c. Determine traffic in veh/day after toll increase. d. Determine the total revenue increase with new toll.
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning