Construction Management
5th Edition
ISBN: 9781119256809
Author: Daniel W. Halpin, Bolivar A. Senior, Gunnar Lucko
Publisher: WILEY
expand_more
expand_more
format_list_bulleted
Question
Chapter 2, Problem 10RQE
a)
To determine
The money that the contractor invests in the advertised project that is available for the bid at the time when the contractor goes to the AE’s office or checks the web to observe the plans and specifications.
b)
To determine
The money that the contractor invests in the advertised project that is available for the bid when deciding to obtain the set of drawings for considering it later.
c)
To determine
The money that the contractor invests in the advertised project that is available for the bid when the contractor decides to make the initial quantity takeoff.
d)
To determine
The money that the contractor invests in the advertised project that is available for the bid when the contractor makes full preparation of the bid for submission.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Write down the required documents to be submitted by the contractor during bidding phase and while signing the contract?
The process of submitting a proposal (tender) to manage a construction project
a. Negotiation
b. Value Engineering
c. Bidding
d. Project Management
Select a type of construction contract and make a brief discussion of its advantages and disadvantages to both the contractor and the owner.
Knowledge Booster
Similar questions
- Visit a local building contractor and determine how he orshe handles control of submittals from subcontractors toarchitect/engineer. What system does he or she use to ensurethe job will not be held up due to procurement and approvaldelays?arrow_forwardAs the project manager of your company, what will be your cinsideration during Tender adjustments for tender submission?arrow_forwardIs the final amount paid to a contractor under a unitprice contract limited by the quantities of materials or work shown in the original Bid Schedule?arrow_forward
- Question # 13, Case 3: Bid-design-build This general contractor has been awarded a two-story speculative office building project on a lump sum bid basis. The mechanical, electrical, and plumbing (MEP) systems, including the heating, ventilation, and air conditioning (HVAC) and fire protection systems, were also bid on a lump sum but design-build basis, with very little criteria information available for them to base their bids on. The subcontractors were responsible for preparing their own documents and having them stamped by a state-licensed engineer and obtain their own permits. The general contractor did not submit these documents to the owner for approval, as it was not specified that they had to do so. The MEP systems subcontractors have routinely received city inspections and approvals for work in place. As the project nears completion, the owner and his architect have just walked the project, and they have discovered that several areas of the design-build MEP subcontractors work…arrow_forwardFigure 2-2 shows the project organization chart for a Design-Bid-Build project delivery method. Assume the same project is to be delivered through design-build method - Project Architect (John James) and Western Construction Co. formed a partnership and competed for the project against other design-build teams and won the project. Prepare a project organization chart for the design-build delivery method. All design sub-consultants and subcontractors remain the same.arrow_forwardIf the specifications are silent on the subject, but a contractor asks you, as the Resident Project Representative or inspector, how to perform the work, which of the following is the recommended procedure? a. Be ready to help by telling the contractor your opinions,because as a member of the construction team,it is your responsibility. b. Politely decline because construction means andmethods are the sole prerogative of the contractor.c. Direct the contractor how to perform the workbecause you know that if the contractor asked you,it meant that he or she did not know how to execute the work, and the project may otherwise suffer delays or failures.arrow_forward
- What are the advantages and disadvantages of using a bid depository to (a) a general contractor and (b) a subcontractor?arrow_forwardWhy should the contractor submittals be handled carefully?arrow_forward247. To determine a subcontractor's probable financial stability, which of the following would be the most relevant area for inquiry? A. Bonding rate and capacity. B. Cost of general liability insurance. C. Experience of their project managers. D. History of completed projects. 248. The most effective procurement system includes which of the following? A. Submittal log maintained weekly. B. Management system which tracks the number of submittals still outstanding. C. Log system which tracks how long the design team takes to review each submittal. D. Log which maintains fabrication, estimated and actual delivery, and installation dates. 249. Which stage of the management process has the greatest impact on the success of a project? A. Staffing. B. Planning. C. Monitoring. D. Implementing.arrow_forward
- What are the responsibilities of a general contractor?arrow_forwardWhen does pre-construction take place?A. After the design is completeB. During the bidding processC. Before design is complete and construction beginsD. Prior to the design phasearrow_forwardMany contracts require that the contractor prepare and present the construction schedule and receive the owner's approval before any contract payments are made.Explain in detail what are the three elements of the contractor 's schedule that the owner will typically be interested in?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,