a)

Summary Introduction

To solve: The linear programming problem and answer the questions.

Introduction:

Linear programming:

Linear programming is a mathematical modelling method where a linear function is maximized or minimized taking into consideration the various constraints present in the problem. It is useful in making quantitative decisions in business planning.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Minimize Z=1.80S+2.20TSubject to:5S+8T200gr(Potassium)15S+6T240gr(Carbohydrate)4S+12T180gr(Protein)T10gr(T)S,T0(Nonnegativity)

Calculation of coordinates for each constraint and objective function:

Constraint 1:

5S+8T200gr(Potassium)

Substituting S=0 to find T,

5(0)+8T=2008T=200T=2008T=25

Substituting T=0 to find S,

5S+8(0)=2005S=200S=2005S=40

Constraint 2:

15S+6T240gr(Carbohydrate)

Substituting S=0 to find T,

15(0)+6T=2406T=240T=2406T=40

Substituting T=0 to find S,

15S+6(0)=24015S=240S=24015S=16

Constraint 3:

4S+12T180gr(Protein)

Substituting S=0 to find T,

4(0)+12T=18012T=180T=18012T=15

Substituting T=0 to find S,

4S+12(0)=1804S=180S=1804S=45

Constraint 4:

T10gr(T)

Therefore T=10.

Objective function:

The problem is solved with iso-cost line method.

Let 1.80S+2.20T=99

Substituting S=0 to find T,

1.80(0)+2.20T=992.20T=99T=992.20T=45

Substituting T=0 to find S,

1.80S+2.20(0)=991.80S=99S=991.80S=55

Graph:

Operations Management (Comp. Instructor's Edition), Chapter 19, Problem 2P , additional homework tip  1

(1) Optimal value of the decision variables and Z:

The coordinates for the cost line is (45, 55). The cost line is moved towards the origin. The lowest at which the cost line intersects in the feasible region will be the optimum solution. The following equation are solved as simultaneous equation to find optimum solution.

5S+8T=200 (1)

15S+6T=240 (2)

Solving (1) and (2) we get,

S=8,T=20

The values are substituted in the objective function to find the objective function value.

Minimize Z=1.80(8)+2.20(20)=14.40+44=58.40

Optimal solution:

S=8T=20Z=58.4

(2)

None of the constraints are having slack. All ≤ constraints are binding.

(3)

Protein and T constraint have surplus.

Protein:

4(8)+12(20)180gr32+240180272180

The surplus is 92 (272 – 180).

T:

T102010

The surplus is 10 (20– 10).

(4)

The protein constraint is redundant because, it does not intersect at any point in the feasible region.

b)

Summary Introduction

To solve: The linear programming problem and answer the questions.

Introduction:

Linear programming:

Linear programming is a mathematical modelling method where a linear function is maximized or minimized taking into consideration the various constraints present in the problem. It is useful in making quantitative decisions in business planning.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Minimize Z=2x1+3x2Subject to:4x1+2x220(D)2x1+6x218(E)x1+2x212(F)x1,x20(Nonnegativity)

Calculation of coordinates for each constraint and objective function:

Constraint 1:

4x1+2x220(D)

Substituting x1=0 to find x2,

4(0)+2x2=202x2=20x2=202x2=10

Substituting x2=0 to find x1,

4x1+2(0)=204x1=20x1=204x1=5

Constraint 2:

2x1+6x218(E)

Substituting x1=0 to find x2,

2(0)+6x2=186x2=18x2=186x2=3

Substituting x2=0 to find x1,

2x1+6(0)=182x1=18x1=182x1=9

Constraint 3:

x1+2x212(F)

Substituting x1=0 to find x2,

(0)+2x2=122x2=12x2=122x2=6

Substituting x2=0 to find x1,

x1+2(0)=12x1=12x1=121x1=12

Objective function:

The problem is solved with iso-cost line method.

Let 2x1+3x2=24

Substituting x1=0 to find x2,

2(0)+3x2=243x2=24x2=243x2=8

Substituting x2=0 to find x1,

2x1+3(0)=242x1=24x1=242x1=12

Graph:

Operations Management (Comp. Instructor's Edition), Chapter 19, Problem 2P , additional homework tip  2

(1) Optimal value of the decision variables and Z:

The coordinates for the cost line is (12, 8). The cost line is moved towards the origin. The lowest at which the cost line intersects in the feasible region will be the optimum solution. The following equation are solved as simultaneous equation to find optimum solution.

4x1+2x2=20 (1)

2x1+6x2=18 (2)

Solving (1) and (2) we get,

x1=4.2,x2=1.6

The values are substituted in the objective function to find the objective function value.

Minimize Z=2(4.2)+3(1.6)=8.4+4.8=13.2

Optimal solution:

x1=4.2x2=1.6Z=13.2

(2)

Constraint F is having slack as shown below.

(4.2)+2(1.6)124.2+3.2127.412

The slack is 4.6 (12 – 7.4).

(3)

There are no surplus. D and E constraints with ≥ are binding.

(4)

There are no redundant constraints

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Gas sales across type: 80% of gas sales tend to be regular. 15% midgrade, 5% tend to be premium. $0.10 increase in price per gallon tends to decrease gallons sold by 1 to 3%. Jan-0.87, Feb-0.95, Mar-1.00, Apr-1.05, May-1.08, Jun1.15, Jul-1.13, Aug-1.07, Sep-1.02, Oct-0.94, Nov-0.89, Dec-0.85. You want the MAPE to be below 20%, if ypu can get it to or below 10% they'll throw in extra $10k. Wont get bonus if it is above 11% or 20%. It cannot be over 20%.
help me choose the correct path please. There are other options
Negotiators can gain several benefits from using the strategy of multiple equivalent simultaneous offers. By offering multiple options it reduces the chance of rejection. It also improves the chances of reaching reaching an agreement. By presenting multiple offers, it shows you are flexible.  agree with the post
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,