Question
Book Icon
Chapter 19, Problem 2P

a)

Summary Introduction

To solve: The linear programming problem and answer the questions.

Introduction:

Linear programming:

Linear programming is a mathematical modelling method where a linear function is maximized or minimized taking into consideration the various constraints present in the problem. It is useful in making quantitative decisions in business planning.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Minimize Z=1.80S+2.20TSubject to:5S+8T200gr(Potassium)15S+6T240gr(Carbohydrate)4S+12T180gr(Protein)T10gr(T)S,T0(Nonnegativity)

Calculation of coordinates for each constraint and objective function:

Constraint 1:

5S+8T200gr(Potassium)

Substituting S=0 to find T,

5(0)+8T=2008T=200T=2008T=25

Substituting T=0 to find S,

5S+8(0)=2005S=200S=2005S=40

Constraint 2:

15S+6T240gr(Carbohydrate)

Substituting S=0 to find T,

15(0)+6T=2406T=240T=2406T=40

Substituting T=0 to find S,

15S+6(0)=24015S=240S=24015S=16

Constraint 3:

4S+12T180gr(Protein)

Substituting S=0 to find T,

4(0)+12T=18012T=180T=18012T=15

Substituting T=0 to find S,

4S+12(0)=1804S=180S=1804S=45

Constraint 4:

T10gr(T)

Therefore T=10.

Objective function:

The problem is solved with iso-cost line method.

Let 1.80S+2.20T=99

Substituting S=0 to find T,

1.80(0)+2.20T=992.20T=99T=992.20T=45

Substituting T=0 to find S,

1.80S+2.20(0)=991.80S=99S=991.80S=55

Graph:

Operations Management (Comp. Instructor's Edition), Chapter 19, Problem 2P , additional homework tip  1

(1) Optimal value of the decision variables and Z:

The coordinates for the cost line is (45, 55). The cost line is moved towards the origin. The lowest at which the cost line intersects in the feasible region will be the optimum solution. The following equation are solved as simultaneous equation to find optimum solution.

5S+8T=200 (1)

15S+6T=240 (2)

Solving (1) and (2) we get,

S=8,T=20

The values are substituted in the objective function to find the objective function value.

Minimize Z=1.80(8)+2.20(20)=14.40+44=58.40

Optimal solution:

S=8T=20Z=58.4

(2)

None of the constraints are having slack. All ≤ constraints are binding.

(3)

Protein and T constraint have surplus.

Protein:

4(8)+12(20)180gr32+240180272180

The surplus is 92 (272 – 180).

T:

T102010

The surplus is 10 (20– 10).

(4)

The protein constraint is redundant because, it does not intersect at any point in the feasible region.

b)

Summary Introduction

To solve: The linear programming problem and answer the questions.

Introduction:

Linear programming:

Linear programming is a mathematical modelling method where a linear function is maximized or minimized taking into consideration the various constraints present in the problem. It is useful in making quantitative decisions in business planning.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Minimize Z=2x1+3x2Subject to:4x1+2x220(D)2x1+6x218(E)x1+2x212(F)x1,x20(Nonnegativity)

Calculation of coordinates for each constraint and objective function:

Constraint 1:

4x1+2x220(D)

Substituting x1=0 to find x2,

4(0)+2x2=202x2=20x2=202x2=10

Substituting x2=0 to find x1,

4x1+2(0)=204x1=20x1=204x1=5

Constraint 2:

2x1+6x218(E)

Substituting x1=0 to find x2,

2(0)+6x2=186x2=18x2=186x2=3

Substituting x2=0 to find x1,

2x1+6(0)=182x1=18x1=182x1=9

Constraint 3:

x1+2x212(F)

Substituting x1=0 to find x2,

(0)+2x2=122x2=12x2=122x2=6

Substituting x2=0 to find x1,

x1+2(0)=12x1=12x1=121x1=12

Objective function:

The problem is solved with iso-cost line method.

Let 2x1+3x2=24

Substituting x1=0 to find x2,

2(0)+3x2=243x2=24x2=243x2=8

Substituting x2=0 to find x1,

2x1+3(0)=242x1=24x1=242x1=12

Graph:

Operations Management (Comp. Instructor's Edition), Chapter 19, Problem 2P , additional homework tip  2

(1) Optimal value of the decision variables and Z:

The coordinates for the cost line is (12, 8). The cost line is moved towards the origin. The lowest at which the cost line intersects in the feasible region will be the optimum solution. The following equation are solved as simultaneous equation to find optimum solution.

4x1+2x2=20 (1)

2x1+6x2=18 (2)

Solving (1) and (2) we get,

x1=4.2,x2=1.6

The values are substituted in the objective function to find the objective function value.

Minimize Z=2(4.2)+3(1.6)=8.4+4.8=13.2

Optimal solution:

x1=4.2x2=1.6Z=13.2

(2)

Constraint F is having slack as shown below.

(4.2)+2(1.6)124.2+3.2127.412

The slack is 4.6 (12 – 7.4).

(3)

There are no surplus. D and E constraints with ≥ are binding.

(4)

There are no redundant constraints

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
View the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs.    2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent.   a) Compute the normal time for the job. b) Compute the standard time for the job.   Note: You could work out the problem by hand or use excel; in chapter 7,…
1) Noodles & Company   View the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs.    2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent.   a) Compute the normal time for the job. b) Compute the standard time for the job.   Note: You could work out the problem by hand or use…
An investigation of career development opportunities and job satisfaction at
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,