
a.
Calculate the target cost for Product K and Product Q.
a.

Explanation of Solution
Target costing:
Target costing is a business procedure that targets at the earliest stages of new product and service development, before creating and designing of production techniques.
Calculate the target cost for Product K.
Working note:
(1)
Calculate the target cost of the product Q.
Working note:
(2)
Therefore, the target cost of product K is $102 and product Q is $187.
b.
Estimate the total
b.

Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the total manufacturing cost per unit:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (3) | $50 | $50 |
Total manufacturing cost per unit | $110 | $170 |
Table (1)
- The cost per unit of Product K is above its target cost of $102, thus it is not earnings the desired 15% return.
- The cost per unit of Product Q is below its target cost of $187, thus it is earnings a greater return than the desired rate.
Working note:
Calculate the fixed overhead cost per unit:
(3)
- The manufacturing cost per unit of product K is $110 and for product Q is $170.
- Product Q is earning the desired income from the above estimation.
c.
Recalculate the total manufacturing cost per unit if fixed overhead costs are assigned to products on the basis of direct labor hours and identify the product that is earning the desired income.
c.

Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Recalculate the total manufacturing cost per unit of the products:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost | $32 | $80 |
Total manufacturing cost per unit | $92 | $200 |
Table (2)
- The cost per unit of Product K is below its target cost of $102 thus, it is earning a greater return than the desired rate.
- The cost per unit of Product Q is above its target cost of $187 thus, it is not earnings the desired return.
Working notes:
Calculate the time taken to produce each unit of Product K:
(4)
Calculate the time taken to produce each unit of Product Q:
(5)
Calculate the total time taken to produce the estimated production of Product K:
(6)
Calculate the total time taken to produce the estimated production of Product Q:
(7)
Calculate the allocation rate per hour:
Note:
(8)
Calculate the fixed overhead cost of product K:
(9)
Calculate the fixed overhead cost of product Q:
(10)
d.
Estimate the total manufacturing cost per unit of each product if activity-based costing is used for assigning fixed overhead costs and state the product that is earning the desired income under this method.
d.

Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the total manufacturing cost per unit of the products:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (11) | $36.40 | $72.67 |
Total manufacturing cost per unit | $96.40 | $192.67 |
Table (3)
Therefore, the total manufacturing cost per unit of product K and Product Q is $96.40 and $192.67.
Working note:
Calculate the fixed overhead allocation per unit:
Particulars | Product K (In numbers) | Product Q (In numbers) |
Allocation rate per unit | Total fixed overhead cost | |
Activity cost pools | (a) | (b) | (c) | Product K (d) = (a) × (c) | Product Q (d) = (b) × (c) |
Setup costs | 100 | 400 | $800 | $80,000 | $320,000 |
Purchase orders | 200 | 100 | $2,000 | $400,000 | $200,000 |
Machining | 2,000 | 6,000 | $63 | $125,000 | $375,000 |
Inspection | 50 | 30 | $2,500 | $125,000 | $75,000 |
Shipping | 300 | 200 | $600 | $180,000 | $120,000 |
Total fixed overhead allocated units produced | $910,000 | $1,090,000 | |||
÷Units produced | ÷25000 | ÷15000 | |||
Fixed overhead cost per unit | $36.40 | $72.67 |
Table (4)
Note: For the calculation of allocation rate per unit refer Table (5)
(11)
Calculate the allocation rate of each overhead:
Overhead costs (a) |
Rate per set up ( Product k) (b) |
Rate per set up ( Product Q) (c) |
Total rate per set up (d)=(b)+(c) |
Allocation rate per unit activity (e) = (a) ÷ (d) |
Machine setups $400,000 | $100 | $400 | $500 | $800 |
Purchase orders $600,000 | $200 | $100 | $300 | $2,000 |
Machining rate $500,000 | $2,000 | $6,000 | $8,000 | $62.50 (or) $63 |
Inspection $200,000 | $50 | $30 | $80 | $2,500 |
Shipping $300,000 | $300 | $200 | $500 | $600 |
Table (5)
(12)
- The cost per unit of Product K is below the target cost of $102, thus it is earning a return greater than the desired rate.
- The cost per unit of Product Q is above the target cost of $187, thus it is not earnings the desired return.
e.
State the proportion of fixed overhead that is value added, and mention the activity which can be improved first.
e.

Explanation of Solution
- Machining and shipping are the two fixed overhead activities that are value added and the proportion of these costs to total fixed overhead is calculated below:
- Therefore, the proportion of machining and shipping overheads to total fixed costs is 40%.
- The number of steps taken to produce product Q can be reduced and this appears to be a logical activity.
f.
Ascertain the impact of the design changes on the manufacturing costs of both products and mention the products that will earn the desired return.
f.

Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the manufacturing costs of product K and Product Q:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (13) | $46 | $57 |
Total manufacturing cost per unit | $106 | $177 |
Table (6)
Working note:
Calculate the fixed overhead cost of product K and product Q:
Particulars | Product K (In numbers) | Product Q (In numbers) |
Allocation rate per unit | Total fixed overhead cost | |
Activity cost pools | (a) | (b) | (c) | Product K (d) = (a) × (c) | Product Q (d) = (b) × (c) |
Setup costs | $100 | $25 | (14)$3,200 | $320,000 | $80,000 |
Purchase orders | $200 | $100 | $2,000 | $400,000 | $200,000 |
Machining | $2,000 | $6,00 | $62.50 | $125,000 | $375,000 |
Inspection | $50 | $30 | $2,500 | $125,000 | $75,000 |
Shipping | $300 | $200 | $600 | $180,000 | $120,000 |
Total fixed overhead allocated units produced | $1,150,000 | $850,000 | |||
÷Units produced | ÷25,000 | ÷15,000 | |||
Fixed overhead cost per unit | $46 | $56.67 |
Table (7)
Note: For the calculation of allocation rate per unit except for setup costs refer Table (5)
(13)
Calculate the new allocation rate per machine setup:
(14)
Note: Units of production for product Q is reduced to 25 units.
- The cost per unit of Product K is above the target cost of $102 thus, it will not earn the desired 15% return.
- The cost per unit of Product Q is below the target cost of $187 thus, it will earn a return greater than the desired rate.
g.
Calculate the manufacturing costs for each product if the machine is purchased and find out whether the Product Q should be redesigned or should the machine be purchased.
g.

Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the manufacturing costs for each product if a new machine is purchased:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (15) | $34.80 | $62 |
Total manufacturing cost per unit | $94.80 | $182 |
Table (8)
Working note:
Calculate the total fixed overhead allocated per unit:
Particulars | Product K | Product Q |
Allocation rate per unit | Total fixed overhead cost | |
Activity cost pools | (a) | (b) | (c) | Product K (d) = (a) × (c) | Product Q (d) = (b) × (c) |
Setup costs | $20 | $80 | (16)$2,000 | $40,000 | $160,000 |
Purchase orders | $200 | $100 | $2,000 | $400,000 | $200,000 |
Machining | $2,000 | $6,00 | $62.50 | $125,000 | $375,000 |
Inspection | $50 | $30 | $2,500 | $125,000 | $75,000 |
Shipping | $300 | $200 | $600 | $180,000 | $120,000 |
Total fixed overhead allocated units produced | $870,000 | $930,000 | |||
÷Units produced | ÷25,000 | ÷15,000 | |||
Fixed overhead cost per unit | $34.80 | $62 |
Table (9)
Note: For the calculation of allocation rate per unit except for setup costs refer Table (5)
(15)
Calculate the new allocation rate per machine setup:
(16)
Note: Units of production for product K is reduced to 20 units and for product Q is 80 units.
- The machine is purchased because the total manufacturing costs is reduced by $200,000 that will increase profits by $200,000.
- If Product Q is redesigned, there is no increase in profits, just a reallocation of fixed costs between the two products occurs.
Want to see more full solutions like this?
Chapter 19 Solutions
Financial & Managerial Accounting
- Black Oil Company is trying to decide whether to lease or buy a new computer-assisted drilling system for its extraction business. Management has already determined that acquisition of the system has a positive NPV. The system costs $9.4 million and qualifies for a 25% CCA rate. The equipment will have a $975,000 salvage value in five years. Black Oil’s tax rate is 36%, and the firm can borrow at 9%. Cape Town Company has offered to lease the drilling equipment to Black Oil for payments of $2.15 million per year. Cape Town’s policy is to require its lessees to make payments at the start of the year. Suppose it is estimated that the equipment will have no savage value at the end of the lease. What is the maximum lease payment acceptable to Black Oil now?arrow_forwardI need help with this general accounting question using the proper accounting approach.arrow_forwardSpace Exploration Technology Corporation (Space X), is an aerospace manufacturer that sells stock engine components and tests equipment for commercial space transportation. A new customer has placed an order for eight high-bypass turbine engines, which increase fuel economy. The variable cost is $1.6 million per unit, and the credit price is $1.725 million each. Credit is extended for one period, and based on historical experience, payment for about one out of every 200 such orders is never collected. The required return is 1.8% per period. Required Assuming that this is a one-time order, should it be filled? The customer will not buy if credit is not extended. What is the break-even probability of default in part 1? Suppose that customers who don’t default become repeat customers and place the same order every period forever. Further assume that repeat customers never default. Should the order be filled? What is the break-even probability of default?arrow_forward
- Can you explain the correct methodology to solve this general accounting problem?arrow_forwardPlease help me solve this general accounting question using the right accounting principles.arrow_forwardSuppose during 2025 that Federal Express reported the following information (in millions): net sales of $82,500 and net income of $185. Its balance sheet also showed total assets at the beginning of the year of $27,000 and total assets at the end of the year of $23,000. Calculate the asset turnover and return on assets. (Round answers to 2 decimal places, e.g. 6.25 or 6.25%.) Asset turnover Return on assets times %arrow_forward
- The shareholders of Barley Corporation have voted in favor of a buyout offer from Wheat Corporation. Information about each firm is given here: Barley Wheat Price/earnings ratio 13.5 21 Shares outstanding 90,000 210,000 Earnings $180,000 $810,000 Barley shareholders will receive one share of Wheat stock for every three shares they hold of Barley. Required What will the EPS of Wheat be after the merger? What will be the P/E ratio if the NPV of the acquisition is 0? What must Wheat feel is the value of the synergy between these two firms? Explain how your answer can be reconciled with the decision to go ahead with the takeover?arrow_forwardI am trying to find the accurate solution to this general accounting problem with the correct explanation.arrow_forwardPlease provide the answer to this general accounting question with proper steps.arrow_forward
- Respond to jane Plant assets of DTPW are essential to the County’s transportation services and infrastructure. These assets consist of physical, long-term resources including our vast Metrorail and Metromover systems, maintenance facilities, administrative buildings, bus depots, and train stations. DTPW depends greatly on machinery such as fare collection machines, elevators, escalators, signaling devices, and track systems which are necessary to ensure that our daily operations go off without a hitch. For example, our buses and service trucks are regarded as plant assets since they help the department fulfill its goal of providing dependable and effective transportation across the County. These assets are valuable in addition to being physically noteworthy because they reflect large investments made to preserve accessibility, safety, and public transportation. For long-term planning and financial reporting, these assets have to be properly managed and their depreciation tracked.…arrow_forwardCan you solve this general accounting question with accurate accounting calculations?arrow_forwardPlease explain the correct approach for solving this general accounting question.arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education





