a.
Calculate the target cost for Product K and Product Q.
a.
Explanation of Solution
Target costing:
Target costing is a business procedure that targets at the earliest stages of new product and service development, before creating and designing of production techniques.
Calculate the target cost for Product K.
Working note:
(1)
Calculate the target cost of the product Q.
Working note:
(2)
Therefore, the target cost of product K is $102 and product Q is $187.
b.
Estimate the total
b.
Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the total manufacturing cost per unit:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (3) | $50 | $50 |
Total manufacturing cost per unit | $110 | $170 |
Table (1)
- The cost per unit of Product K is above its target cost of $102, thus it is not earnings the desired 15% return.
- The cost per unit of Product Q is below its target cost of $187, thus it is earnings a greater return than the desired rate.
Working note:
Calculate the fixed overhead cost per unit:
(3)
- The manufacturing cost per unit of product K is $110 and for product Q is $170.
- Product Q is earning the desired income from the above estimation.
c.
Recalculate the total manufacturing cost per unit if fixed overhead costs are assigned to products on the basis of direct labor hours and identify the product that is earning the desired income.
c.
Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Recalculate the total manufacturing cost per unit of the products:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost | $32 | $80 |
Total manufacturing cost per unit | $92 | $200 |
Table (2)
- The cost per unit of Product K is below its target cost of $102 thus, it is earning a greater return than the desired rate.
- The cost per unit of Product Q is above its target cost of $187 thus, it is not earnings the desired return.
Working notes:
Calculate the time taken to produce each unit of Product K:
(4)
Calculate the time taken to produce each unit of Product Q:
(5)
Calculate the total time taken to produce the estimated production of Product K:
(6)
Calculate the total time taken to produce the estimated production of Product Q:
(7)
Calculate the allocation rate per hour:
Note:
(8)
Calculate the fixed overhead cost of product K:
(9)
Calculate the fixed overhead cost of product Q:
(10)
d.
Estimate the total manufacturing cost per unit of each product if activity-based costing is used for assigning fixed overhead costs and state the product that is earning the desired income under this method.
d.
Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the total manufacturing cost per unit of the products:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (11) | $36.40 | $72.67 |
Total manufacturing cost per unit | $96.40 | $192.67 |
Table (3)
Therefore, the total manufacturing cost per unit of product K and Product Q is $96.40 and $192.67.
Working note:
Calculate the fixed overhead allocation per unit:
Particulars | Product K (In numbers) | Product Q (In numbers) |
Allocation rate per unit | Total fixed overhead cost | |
Activity cost pools | (a) | (b) | (c) | Product K (d) = (a) × (c) | Product Q (d) = (b) × (c) |
Setup costs | 100 | 400 | $800 | $80,000 | $320,000 |
Purchase orders | 200 | 100 | $2,000 | $400,000 | $200,000 |
Machining | 2,000 | 6,000 | $63 | $125,000 | $375,000 |
Inspection | 50 | 30 | $2,500 | $125,000 | $75,000 |
Shipping | 300 | 200 | $600 | $180,000 | $120,000 |
Total fixed overhead allocated units produced | $910,000 | $1,090,000 | |||
÷Units produced | ÷25000 | ÷15000 | |||
Fixed overhead cost per unit | $36.40 | $72.67 |
Table (4)
Note: For the calculation of allocation rate per unit refer Table (5)
(11)
Calculate the allocation rate of each overhead:
Overhead costs (a) |
Rate per set up ( Product k) (b) |
Rate per set up ( Product Q) (c) |
Total rate per set up (d)=(b)+(c) |
Allocation rate per unit activity (e) = (a) ÷ (d) |
Machine setups $400,000 | $100 | $400 | $500 | $800 |
Purchase orders $600,000 | $200 | $100 | $300 | $2,000 |
Machining rate $500,000 | $2,000 | $6,000 | $8,000 | $62.50 (or) $63 |
Inspection $200,000 | $50 | $30 | $80 | $2,500 |
Shipping $300,000 | $300 | $200 | $500 | $600 |
Table (5)
(12)
- The cost per unit of Product K is below the target cost of $102, thus it is earning a return greater than the desired rate.
- The cost per unit of Product Q is above the target cost of $187, thus it is not earnings the desired return.
e.
State the proportion of fixed overhead that is value added, and mention the activity which can be improved first.
e.
Explanation of Solution
- Machining and shipping are the two fixed overhead activities that are value added and the proportion of these costs to total fixed overhead is calculated below:
- Therefore, the proportion of machining and shipping overheads to total fixed costs is 40%.
- The number of steps taken to produce product Q can be reduced and this appears to be a logical activity.
f.
Ascertain the impact of the design changes on the manufacturing costs of both products and mention the products that will earn the desired return.
f.
Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the manufacturing costs of product K and Product Q:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (13) | $46 | $57 |
Total manufacturing cost per unit | $106 | $177 |
Table (6)
Working note:
Calculate the fixed overhead cost of product K and product Q:
Particulars | Product K (In numbers) | Product Q (In numbers) |
Allocation rate per unit | Total fixed overhead cost | |
Activity cost pools | (a) | (b) | (c) | Product K (d) = (a) × (c) | Product Q (d) = (b) × (c) |
Setup costs | $100 | $25 | (14)$3,200 | $320,000 | $80,000 |
Purchase orders | $200 | $100 | $2,000 | $400,000 | $200,000 |
Machining | $2,000 | $6,00 | $62.50 | $125,000 | $375,000 |
Inspection | $50 | $30 | $2,500 | $125,000 | $75,000 |
Shipping | $300 | $200 | $600 | $180,000 | $120,000 |
Total fixed overhead allocated units produced | $1,150,000 | $850,000 | |||
÷Units produced | ÷25,000 | ÷15,000 | |||
Fixed overhead cost per unit | $46 | $56.67 |
Table (7)
Note: For the calculation of allocation rate per unit except for setup costs refer Table (5)
(13)
Calculate the new allocation rate per machine setup:
(14)
Note: Units of production for product Q is reduced to 25 units.
- The cost per unit of Product K is above the target cost of $102 thus, it will not earn the desired 15% return.
- The cost per unit of Product Q is below the target cost of $187 thus, it will earn a return greater than the desired rate.
g.
Calculate the manufacturing costs for each product if the machine is purchased and find out whether the Product Q should be redesigned or should the machine be purchased.
g.
Explanation of Solution
Manufacturing overhead costs:
Manufacturing overhead costs are costs that are not directly related with the manufacturing of the products and it is also known as indirect costs. For example, indirect materials, indirect labour, indirect supplies.
Calculate the manufacturing costs for each product if a new machine is purchased:
Particulars | Product K | Product Q |
Direct materials cost per unit | $30 | $45 |
Direct labor cost per unit | $24 | $60 |
Variable overhead cost | $6 | $15 |
Fixed overhead cost (15) | $34.80 | $62 |
Total manufacturing cost per unit | $94.80 | $182 |
Table (8)
Working note:
Calculate the total fixed overhead allocated per unit:
Particulars | Product K | Product Q |
Allocation rate per unit | Total fixed overhead cost | |
Activity cost pools | (a) | (b) | (c) | Product K (d) = (a) × (c) | Product Q (d) = (b) × (c) |
Setup costs | $20 | $80 | (16)$2,000 | $40,000 | $160,000 |
Purchase orders | $200 | $100 | $2,000 | $400,000 | $200,000 |
Machining | $2,000 | $6,00 | $62.50 | $125,000 | $375,000 |
Inspection | $50 | $30 | $2,500 | $125,000 | $75,000 |
Shipping | $300 | $200 | $600 | $180,000 | $120,000 |
Total fixed overhead allocated units produced | $870,000 | $930,000 | |||
÷Units produced | ÷25,000 | ÷15,000 | |||
Fixed overhead cost per unit | $34.80 | $62 |
Table (9)
Note: For the calculation of allocation rate per unit except for setup costs refer Table (5)
(15)
Calculate the new allocation rate per machine setup:
(16)
Note: Units of production for product K is reduced to 20 units and for product Q is 80 units.
- The machine is purchased because the total manufacturing costs is reduced by $200,000 that will increase profits by $200,000.
- If Product Q is redesigned, there is no increase in profits, just a reallocation of fixed costs between the two products occurs.
Want to see more full solutions like this?
Chapter 19 Solutions
Financial & Managerial Accounting
- General Accountingarrow_forwardThe Dakota Corporation had a 2015 taxable income of $33,000,000 from operations after all operating costs but before (1) interest charges of $9,300,000; (2) dividends received of $860,000; (3) dividends paid of $5,800,000; and (4) income taxes. What are Dakota's average and marginal tax rates on taxable income?arrow_forwardVariable costing?? Sub. General Accountarrow_forward
- Hello tutor please give answer the financial accounting questionarrow_forwardQuestion: BigBoss Inc. provides the following extracts from income statement for the year 2009: Net sales $500,000, Cost of Goods Sold (150,000), Gross profit $350,000, Calculate the gross profit percentage.arrow_forwardGeneral Accounting provide correct solutionarrow_forward
- 3 Red Oil Corp. has two divisions, Refining and Production. The company's primary product is Clean Oil. Each division's costs are provided below: Refining: Variable costs per litre of oil $30 Fixed costs per litre of oil $24 Production: Variable costs per litre of oil $6 Fixed costs per litre of oil $4 The Production Division is able to sell the oil to other areas for $24 per litre. The Refining Division has been operating at a capacity of 80,000 litres a day, using oil from the Production Division and oil purchased from other suppliers. The Refining Division usually purchases 50,000 litres of oil, on average, from the Production Division and 30,000 litres, on average, from other suppliers at $40/litre. What is the Production Division's operating income per 200 litres of oil reported under the 175% of variable costs method? Select one: a. $1,500 b. $100 c. $1,200 d. $(100) e. $880arrow_forward15 Green Thumb Rentals Ltd. incurred $60,000 of common fixed costs and $90,000 of common variable costs. Data are provided below for the capacity allowed and the capacity used. Department Capacity Available in Hours Capacity Used in Hours Tools Department 3,600 3,200 Equipment Department 1,800 1,800 For both departments, common fixed costs are to be allocated on the basis of capacity available and common variable costs are to be allocated on the basis of capacity used. The fixed and variable costs allocated to the Tools Department are Select one: a. $31,756 and $45,000, respectively b. $60,000 and $90,000, respectively c. $20,000 and $32,400, respectively d. $30,000 and $45,000 respectively e. $40,000 and $57,600, respectivelyarrow_forward25. What purpose does structural dependency analysis serve? a) Independent treatment works better b) Business relationship impacts guide reporting choices c) Dependencies add confusion d) Standard methods sufficearrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education