A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?

  1. a. 3 days, because this is the minimum time
  2. b. 7 days, because this is the maximum time
  3. c. 20 days, because this is the sum of the times
  4. d. It is not possible to determine the total completion time from the given information.
Expert Solution & Answer
Check Mark
Summary Introduction

To determine: The total completion time for the project.

Answer to Problem 1CQ

D. It is not possible to determine the total completion time from the given information.

Explanation of Solution

Given information:

Four activities of a project take 4, 3, 6 and 7 days respectively.

The given scenario lacks basic information to find the completion time of the project. Details like precedence relationship is not given which makes it impossible to find the sequence of activities in which the project must be done.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity A B с Time according to schedule (weeks) Activity F G H Time according to schedule (weeks) D E COE
Given the information below, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take 20 weeks or less. Refer to the standard normal table. Activity A Expected Time (weeks) Variance 3.5 1.00 BCDE 5.5 0.96 C 4.0 0.45 12.0 1.78 6.5 2.25 F G 9.0 2.78 4.5 0.69 The probability that this path will take more than 20 weeks to complete is (Enter your response rounded to four decimal places.)
You are the event manager of a wedding project that is behind schedule and over budget. The client has requested some additional features that were not in the original scope. How would you prioritize the additional features requested by the client? What strategies would you employ to adjust the project plan and budget to accommodate these changes effectively? Additionally, what specific tools and techniques would you utilize to monitor and control the progress and ensure the quality of the project?

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY