Textbook Question
Book Icon
Chapter 19, Problem 1CQ

A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?

  1. a. 3 days, because this is the minimum time
  2. b. 7 days, because this is the maximum time
  3. c. 20 days, because this is the sum of the times
  4. d. It is not possible to determine the total completion time from the given information.
Expert Solution & Answer
Check Mark
Summary Introduction

To determine: The total completion time for the project.

Answer to Problem 1CQ

D. It is not possible to determine the total completion time from the given information.

Explanation of Solution

Given information:

Four activities of a project take 4, 3, 6 and 7 days respectively.

The given scenario lacks basic information to find the completion time of the project. Details like precedence relationship is not given which makes it impossible to find the sequence of activities in which the project must be done.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Assess what led to such logistical inefficiencies / collapse of a previously world class freight network
Which of the following statements concerning the evaluation of training programs is true?   Most companies thoroughly evaluate the return on investment of their training programs   It is relatively easy to establish a control group and a treatment group for evaluation   Results level of evaluation measures how well participants liked the program   Behavior level criteria measure whether skills learned in training result in behavior changes back on the job
Eligibility testing is   an disparate impact validation method   none of the above   a method to validate promotions and progressive discipline activity   a test an employee administers to ensure that the potential employee is capable and qualified to perform the requirements of the position

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY