Concept explainers
(1)
Predetermined factory
Normally,
To Calculate: The predetermined factory overhead rate for each alternative base for M Industries.
(1)
Answer to Problem 19.5CP
The predetermined overhead rate for alternative activity base is prepared as follows:
Direct labor cost:
Machine hours:
Working notes:
Total overhead for (2012 – 2016) is calculated as follows:
Factory Overhead (Actual) | Amount ($) |
2012 | 790,000 |
2013 | 870,000 |
2014 | 935,000 |
2015 | 845,000 |
2016 | 760,000 |
4,200,000 |
Table (1)
Total direct labor cost, (2012 – 2016) is computed as below:
Direct labor cost | Amount ($) |
2012 | 3,885,000 |
2013 | 4,410,000 |
2014 | 4,620,000 |
2015 | 4,200,000 |
2016 | 3,885,000 |
21,000,000 |
Table (2)
Total machine hours, (2012 – 2016) is computed as follows:
Machine hours | Hours |
2012 | 93,000 |
2013 | 104,000 |
2014 | 111,000 |
2015 | 100,400 |
2016 | 91,600 |
500,000 |
Table (3)
Explanation of Solution
The total factory overhead is calculated by totaling all year’s actual overhead incurred in production. There are two activity bases. One is direct labor cost and another is machine hours. The total direct labor cost is determined by adding all year’s direct labor cost incurred. The total machine hours spent is determined by adding all year’s machine hours.
The predetermined overhead rate for direct labor cost is 20% of direct labor cost and predetermined overhead rate for machine hours is$8.40 per machine hour.
(2)
The over- or under applied overhead based on two predetermined overhead rates.
(2)
Answer to Problem 19.5CP
Actual Overhead ($) | Applied Overhead ($) | (Over-) underapplied ($) | ||
(a) | (b) | (c) = (a) – (b) | ||
2016 | Direct Labor cost | 790,000 | 777,000 (1) | 13,000 |
Machine Hours | 790,000 | 781,200 (6) | 8,800 | |
2015 | Direct Labor cost | 870,000 | 882,000 (2) | (12,000) |
Machine Hours | 870,000 | 873,600 (7) | (3,600) | |
2014 | Direct Labor cost | 935,000 | 924,000 (3) | 11,000 |
Machine Hours | 935,000 | 932,400 (8) | 2,600 | |
2013 | Direct Labor cost | 845,000 | 840,000 (4) | 5,000 |
Machine Hours | 845,000 | 843,360 (9) | 1,640 | |
2012 | Direct Labor cost | 760,000 | 777,000 (5) | (17,000) |
Machine Hours | 760,000 | 769,440 (10) | (9,440) |
Table (4)
Working note:
The applied overhead for direct labor activity base is calculated as follows:
The applied overhead for machine hour’s activity base is calculated as follows:
Explanation of Solution
When actual overhead incurred is less than applied overhead, the overhead is said to be overapplied. Alternatively, when actual overhead incurred is greater than applied overhead, the overhead is said to be under applied.
(3)
To Discuss: In applying the best predetermined overhead rate as computed.
(3)
Explanation of Solution
The best predetermined overhead rate is machine hours. The total overhead applied is based on both machine hours and direct labor cost. The over- or underapplied overhead ranges from $9,440 (Overapplied) to $8,800 (Underapplied) when the rates are based on machine hours. The over- or underapplied overhead ranges from $17,000 (Overapplied) to $13,000 (Underapplied) when the rates are based on machine hours.
When comparing both, we could see less fluctuation in under or over applied overhead based on predetermined overhead rate based on machine hours in the year by year basis.
Want to see more full solutions like this?
Chapter 19 Solutions
2 Semester Cengage Now, Warren Accounting
- General accountingarrow_forwardGantner Company had the following department information about physical units and percentage of completion: Work in process May1 (60%) Completed and transferred out Work in process, May 31 (40%) Physical Units 48,000 1,20,000 40,000 If materials are added at the beginning of the production process, what is the total number of equivalent units for materials during May? A. 155,200 B. 136,000 C. 168,000 D. 160,000arrow_forwardI need this question answer general Accountingarrow_forward
- Quick answer of this accounting questionsarrow_forwardThe following refers to units processed by an ice cream maker in July. Compute the total equivalent units of production with respect to conversion for July using the weighted-average method. Gallons of Percent of Conversion Product Added Beginning work in process Goods started 4,08,000 35% 7,96,000 100 Goods completed 8,56,000 100 Ending work in 3,48,000 65 processarrow_forwardCalculate the company's profit margin??arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning