PRIN.OF CORPORATE FINANCE
13th Edition
ISBN: 9781260013900
Author: BREALEY
Publisher: RENT MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 19, Problem 14PS
APV Consider a project lasting one year only. The initial outlay is $1,000, and the expected inflow is $1,200. The
- a. What is the project’s base-case
NPV ? - b. What is its APV if the firm borrows 30% of the project’s required investment?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Firm Xy has an investment project with annual cash flows of 20,000, 18,500, 21,500, and 12,350. The discount rate is 11.55%.
What is the nominal payback period if the initial cost is 31,000?
what is the discounted payback period if the initial cost is $24,000?
The cash flows associated with an investment project are as follows:
Year
Project Y
0
(40 000)
1
10000
2
10000
3
15000
4
20000
The required return is 5 percent. Reinvestment rate 6%.
What’s the discount payback period of the projects? (compile a spreadsheet)
Calculate NPV, PI, IRR , MIRR of a projects
Should the firm accept the project?
A project that requires an initial investment of $340,000 is expected to have an after-tax cash flow of $70,000 per year for the first two years, $90,000 per year for the next two years, and $150,000 for the fifth year? Assume the required return for this project is 10%. Use formula solve Please!!!a. What is the NPV of the project?
b. What is the IRR of the project?
c. What is the MIRR of the project?
d. What is the PI of the project?
Chapter 19 Solutions
PRIN.OF CORPORATE FINANCE
Ch. 19.A - The U.S. government has settled a dispute with...Ch. 19.A - You are considering a five-year lease of office...Ch. 19 - WACC True or false? Use of the WACC formula...Ch. 19 - WACC The WACC formula seems to imply that debt is...Ch. 19 - Prob. 3PSCh. 19 - Prob. 4PSCh. 19 - WACC Whispering Pines Inc. is all-equity-financed....Ch. 19 - WACC Table 19.3 shows a book balance sheet for the...Ch. 19 - WACC Table 19.4 shows a simplified balance sheet...Ch. 19 - Prob. 8PS
Ch. 19 - WACC Nevada Hydro is 40% debt-financed and has a...Ch. 19 - Flow-to-equity valuation What is meant by the...Ch. 19 - APV True or false? The APV method a. Starts with a...Ch. 19 - APV A project costs 1 million and has a base-case...Ch. 19 - APV Consider a project lasting one year only. The...Ch. 19 - APV Digital Organics (DO) has the opportunity to...Ch. 19 - Prob. 17PSCh. 19 - Prob. 18PSCh. 19 - Prob. 19PSCh. 19 - Prob. 20PSCh. 19 - Prob. 22PSCh. 19 - Company valuation Chiara Companys management has...Ch. 19 - Prob. 26PSCh. 19 - Prob. 27PS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- A fim evaluates a project with the following cash flows. The firm has a 2 year payback period criteria and a required return of 11 percent. Year Cash flow |(OMR) -24,000 17,000 12,000 9,000 -8,000 11,000 2 3 4 5 11. What is the net present value for the project? 12. What is the payback period for the project? 13. What is the discounted payback period for the project? 14. What is the profitability index for the project? 15. Given your analysis, should the firm accept or reject the project?arrow_forwardYour firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) -$10 $5 $20 Cash Flow in One Year Project (millions) $20 $5 -$10 Suppose all cash flows are certain and the risk-free interest rate is 10%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose based on the NPV decision rule? c. If the firm can choose any two of these projects, which should it choose based on the NPV decision rule? ABCarrow_forwardConsider the following two investment alternatives: The firm's MARR is known to be 15%.(a) Compute the IRR of Project B.(b) Compute the PW of Project A. (c) Suppose that Projects A and B are mutually exclusive. Using the IRR, whichproject would you select?arrow_forward
- The project’s payback is 1.5 years, and it has a weighted average cost of capital of 10 percent. What is the project’s modified internal rate of return (MIRR)? MIRR>21%arrow_forwardConsider the following projects, X and Y where the firm can only choose one. Project X costs $600 and has cash flows of $400 in each of the next 2 years. Project Y also costs $600, and generates cash flows of $500 and $275 for the next 2 years, respectively. Which investment should the firm choose if the cost of capital is 15 percent? Project X, since it has a higher NPV than Project Y Project Y, since it has a higher NPV than Project X neither, since both the projects have negative NPV neither, since both the projects have positive NPVarrow_forwardBATA plc. is considering the following two projects. Only one of which maybe selected. Each project has a required rate of return of 15% for A and 10% for B with the following cash flowsYear Project A Project B0 K (200,000) K (175,000)1 68,700 50,0002 44,500 60,2503 56,500 45,2504 35,500 80,250Required:A. Calculate for each project:Payback period for each of the projects, Net present value for each of the projects and Internal rate of return for each of the projectsB. Explain which project you would recommend for acceptance for each of the three methods and overall. C. Briefly discuss the relative merits of the pay back and net present value methods of evaluation methods mentioned in (a) abovearrow_forward
- You are considering a risk-free investment that costs $4000 and pays $5000 in one year. You can either pay all cash for the investment or you can borrow part and pay cash for the other part. If you borrow $2000, you will be required to pay back $2080 in one year. The risk-free rate is 4%. What is the project’s NPV? Is the NPV affected if you borrow some of the funds?arrow_forwardYour firm has identified three potential investment projects. The projects and their cash flows are shown here: Project Cash Flow Today (millions) Cash Flow in One Year (millions) A −$13 $23 B $7 $3 C $25 -$15 Suppose all cash flows are certain and the risk-free interest rate is 6%. What is the NPV of each project? (Round to two decimal places.) If the firm can choose only one of these projects, which should it choose based on the NPV decision rule? (Round to two decimal places.) If the firm can choose any two of these projects, which should it choose based on the NPV decision rule? (Round to two decimal places.)arrow_forwardYou must analyze two projects, X and Y. Each project costs$10,000, and the firm’s WACC is 12%. The expected cash flows are as follows:a. Calculate each project’s NPV, IRR, MIRR, payback, and discounted payback.b. Which project(s) should be accepted if they are independent?c. Which project(s) should be accepted if they are mutually exclusive?d. How might a change in the WACC produce a conflict between the NPV and IRR rankingsof the two projects? Would there be a conflict if WACC were 5%? (Hint: Plot theNPV profiles. The crossover rate is 6.21875%.)e. Why does the conflict exist?arrow_forward
- Fusion Energy is evaluating a project that has the following annual free cash flows: Period 0 1 2 Free Cash Flow -500 250 300 If the project's discount rate is 27%, then what is the NPV of the project?arrow_forwardYour firm is considering a project that will cost $4.55 million up front, generate cash flows of $3.50 million per year for 3 years, and then have a cleanup and shutdown cost of $6.00 million in the fourth year. a. How many IRRs does this project have? b. Calculate a modified IRR for this project assuming a discount and compounding rate of 10.0%. c. Using the MIRR and a cost of capital of 10.0%, would you take the project? a. How many IRRs does this project have? The project has 2 IRRs. (Select from the drop-down menu.) b. Calculate a modified IRR for this project assuming a discount and compounding rate of 10.0%. The MIRR for this project is %. (Round to two decimal places.)arrow_forwardYour firm has identified three potential investment projects. The projects and their cash flows are shown here: Project Cash Flow Today ($) Cash Flow in One Year ($) A -10 20 В 20 -10 Suppose all cash flows are certain and the risk-free interest rate is 10%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c. If the firm can choose any two of these projects, which should it choose?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Working capital explained; Author: The Finance Storyteller;https://www.youtube.com/watch?v=XvHAlui-Bno;License: Standard Youtube License