Traffic and Highway Engineering
Traffic and Highway Engineering
5th Edition
ISBN: 9781305156241
Author: Garber, Nicholas J.
Publisher: Cengage Learning
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 19, Problem 13P

Repeat Problem 19-7 using two different depths of untreated aggregate bases of 6 in. and 12 in. Highway contractors in your area can furnish rates for providing and properly laying an asphalt concrete surface and untreated granular base. Assume a structural coefficient of 0.12 for the base course. If these rates are available, determine the cost for constructing the different pavement designs if the highway section is 5 miles long and the lane width is 12 ft. Which design will you select for construction?

Expert Solution & Answer
Check Mark
To determine

The cost for constructing the different pavement designs.

Answer to Problem 13P

  $ 693792._

Explanation of Solution

Given information:

Following is the given information:

Equivalent single axle load, ESAL = 0.4354×106.,

CBR = 85.

Subgrade resilient modulus = 18,000lb/in2,

Sub-base layer coefficient = 0.13,

Granular base layer coefficient = 0.14,

Elastic modulus of asphalt concrete = 280,000lb/in2,

mi = 1, Percentage of traffic on design lane = 45%,

SN = 4, reliability level = 85%, standard deviation = 0.45,

and design serviceability loss = 2.0.

Calculation:

We have the following formula for the calculation of truck factor:

  ESAL =fd×Grn×AADT×365×Ni×FEi

Where, ESAL i= equivalent accumulated 18,000-lb (80-kN) single-axle load for the axle category i

fd= design lane factor,

G rn= growth factor for a given growth rate r and design period n

AADT i= first-year annual average daily traffic for axle category i

N i= number of axles on each vehicle in category i

F Ei= load equivalency factor for axle category i

Calculate ESAL for passenger car2000lb/axle single unit:

  ESAL =fd×Grn×AADT×365×Ni×FEiESAL =0.45×33.06×500×365×2×0.0002ESAL =1086.021ESAL =0.01086021×106

We have the following formula for the calculation of design serviceability :

  Δ=PiPt

Substitute the values in the required equation.

Initial serviceability index, Pi=4.5

Terminal serviceability index, Pt=2.5

  Δ=4.52.5Δ=2.0

Let's determine the resilient modulus of subgrade:

The resilient modulus of subgrade is 1500 times CBR

The value of resilient modulus is given as follows:

  Mr=85×1500lb/in2.Mr=127500lb/in2.

Now for the structural number, SN refer to figure 19.10

The reliability level is 90%. Starting from the point 90% in figure, extend this point to standard deviation 0.45. From standard deviation point, extend this line to line A as given in the figure.

From line A extend this line to 0.001×106ESAL

From ESAL extend this line to line B in the figure.

From line B extend this line to 127500lb/in2in Mr.

From M rextend this line till it touches the graph. From that point, draw a horizontal line to touch the design serviceability loss, which is 2.

Extend a line vertically and take the structural number SN3reading, which is 2.5 and SN2is 2.3

Then from figure 19.6, for layer coefficient and the resilient modulus for base layer is

  a2=0.12Es=25000lb/in2

From figure 19.10, resilient modulus is 25000lb/in2. In structural number SN1is 1.6

Refer figure 19.7 to determine layer coefficient a1, from figure 19.7 for resilient modulus of asphalt EAC=400,000lb/in2,a1=0.43

Traffic and Highway Engineering, Chapter 19, Problem 13P

Now, considering the thickness aggregate base as 6 inches.

Calculate the minimum thickness.

  D1=SN1a1

The layer coefficient, a2=0.14 from figure 19.6 and a1=0.43 from Figure 19.7 Chart for Estimating Structural Layer Coefficient of Dense-Graded/Asphalt Concrete

  SN1=1.6 from the figure 19.10

Substitute the values

  D1=SN1a1D1=1.60.43D1=3.7209D14inch.

Checking the values, we have

  SN1=a1D1SN1=0.43×4SN1=1.72

As the values match, thus the thickness of subgrade calculated is correct.

Calculate the required minimum thickness of base course D2is 6 inches.

Check whether the calculated thickness agrees with the calculated structural number using equation

  SN2=a2D2m2+SN1

Substituting the values, we have

  SN2=(0.12×6×1)+ 1.7SN2=0.72+1.7SN2=2.42

Which is compatible with the structural number calculated already.

And implies that the thickness of the surface calculated is correct.

Now, the required minimum thickness of the sub-base course D3 is

  D3SN3SN2a3m3

By substituting the values, we have

  D32.52.420.13×1D30.080.13D30.615lets take 1.00 inch

Now, check if the calculated thickness agrees with the calculated structural number of using the following equation:

  SN3=a3D3m3+SN2+SN1

Substituting the values

  SN3=(0.13×1×1)+ 2.42+1.7SN3=0.13+4.12SN3=4.25

Which is compatible with the structural number calculated already.

And implies that the thickness of the surface calculated is correct.

The thickness of surface 4.25 inches.

Now, considering the thickness aggregate base as 12 inches.

Calculate the minimum thickness.

  D1=SN1a1

Substitute the values, we have

  D1=SN1a1SN1=D1×a1SN1=0.43×4SN11.7inch.

Thus, the thickness of sub grade is 1.7 in.

Now, the thickness of the base course is given as follows:

  SN2=a2D2m2+SN1

Substitute the values.

  SN2=a2D2m2+SN1SN2=(0.12×12×1)+(1.7)SN2=(0.12×12)+(1.7)SN2=(1.44)+(2.57)SN2=4.01

Which is greater than 2.7, i.e., structural number.

Now, the required minimum thickness of the sub-base course D3 is

  D3SN3SN2a3m3

By substituting the values,

  D32.54.010.13×1D31.510.13D311.62lets take 12 inch

Now, check if the calculated thickness agrees with the calculated structural number of using the following equation

  SN3=a3D3m3+SN2+SN1

Substituting the values,

  SN3=(0.13×12×1)+ 4.01+1.7SN3=1.56+5.71SN3=4.15

Which is compatible with the structural number calculated already.

And implies that the thickness of the surface calculated is correct.

Calculate construction cost for the highway considering thickness of base layer as 6 inches and 12 inches.

The cost is calculated by multiplying the measurement of road with the cost per rate.

Assume cost of surface layer as D1=$1/ft.

For cost of base layer D2=$2/ft.

For cost of sub-base layer D3=$2/ft.

The construction cost of the highway is as follows:

Cost = L X B X t X C

For surface layer :

Substitute the values

5 miles is equal to 26400

  Cost = L× B × t× CCost = 26400× 12× 0.17× 1Cost = $ 53856.

For base layer :

Substitute the values

  Cost = L× B × t× CCost = 26400× 12× 0.5×2Cost = $ 316800.

For sub-base layer :

Substitute the values

  Cost = L× B × t× CCost = 26400× 12× 0.34×3Cost = $ 323136.

Now, calculate the total cost as follows:

  Total cost = $ 53856+$ 316800+$ 323136.Total cost = $ 693792.

The construction cost of the highway is as follows:

Cost = L X B X t X C

For surface layer :

Substitute the values

5 miles is equal to 26400

  Cost = L× B × t× CCost = 26400× 12× 0.34× 1Cost = $ 107712.

For base layer :

Substitute the values

  Cost = L× B × t× CCost = 26400× 12× 1×2Cost = $ 633600.

For sub-base layer :

Substitute the values

  Cost = L× B × t× CCost = 26400× 12× 0.42×3Cost = $ 399168.

Now, calculate the total cost as follows:

  Total cost = $ 107712+$ 633600+$ 399168.Total cost = $ 1140480.

Conclusion:

Therefore, out of two cases the construction cost is $ 693792. As the cost in this case is less and the thickness of the layers calculated are more accurate.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Discuss various tests used for the quality of aggregate used in flexible pavements.
50 KPa is equivalent to: O A) 5x 10^6 N/m^2 O B) 5 x 10^5 N/m^2 O0 5 x 10^3 N/m^2 O D) 5 x 10^4 N/m^2 Concrete is required for a plain concrete pavement to be constructed in Southern Alberta. The pavement will be exposed to freezing, thawing, and deicers. If aggregates with a nominal maximum size of 20 mm are used, what is the minimum cement content per cubic meter of concrete as per the CSA Standard? OA) 320 kg O B) 335 kg OO 390 kg OD) 420 kg During Lab 5, the relative density of a coarse aggregate sample was determined. The sample of coarse aggregate was towel dryed to represent this moisture state: O A) OD B) Wet OC SSD O D) Air Dry When performing the slump test, each layer of concrete is rodded times as per CSA specifications: OA) 20 O B) 25 OO 30 O D) 12
As a materials engineer working for a highway department, what standard PG asphalt binder grade would you specify for each of the conditions show in the table. Seven-Day Мaximum Minimum Pavement Recommended PG Grade Pavement Temperature, °C Temperature, "C Case 50% 98% Mean, °C Std. Dev., "C Mean, "C Std. Dev., °C Reliability Reliability 39 1 -32 3.5 54 1.5 -17 2 69 2.5 1.
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License