Textbook Question
Chapter 18, Problem 3QS
Cost behavior estimation---high-low method P1
The following information is available for a company’s maintenance cost over the last seven months. Using the high-low method. Estimate both fixed and variable components of its maintenance cost.
Month | Maintenance Hours | Maintenance Cost |
June…………………………………… | 9 | $5,450 |
July…………………………………… | 18 | 6,900 |
August………………………………... | 12 | 5,100 |
September……………………………... | 15 | 6,000 |
October………………………………... | 21 | 6,900 |
November……………………………… | 24 | 8,100 |
December……………………………… | 6 | 3,600 |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Answer 7,8,9
Assistance with d and e plz
₱1.14
₱1.84
₱1.30
₱0.83
Chapter 18 Solutions
Loose-Leaf for Financial and Managerial Accounting
Ch. 18 - Prob. 1MCQCh. 18 - Prob. 2MCQCh. 18 - Prob. 3MCQCh. 18 - Prob. 4MCQCh. 18 - Prob. 5MCQCh. 18 - Prob. 1DQCh. 18 - Prob. 2DQCh. 18 - When output volume increases, do fixed costs per...Ch. 18 - How is the cost-volume-profit analysis useful?Ch. 18 - Prob. 5DQ
Ch. 18 - Prob. 6DQCh. 18 - Prob. 7DQCh. 18 - Prob. 8DQCh. 18 - Prob. 9DQCh. 18 - Prob. 10DQCh. 18 - Prob. 11DQCh. 18 - Prob. 12DQCh. 18 - Prob. 13DQCh. 18 - Prob. 14DQCh. 18 - Prob. 15DQCh. 18 - Prob. 16DQCh. 18 - Prob. 17DQCh. 18 - Prob. 18DQCh. 18 - Prob. 19DQCh. 18 - APPLE Should Apple use single product or...Ch. 18 - Prob. 21DQCh. 18 - Prob. 22DQCh. 18 - Prob. 1QSCh. 18 - Prob. 2QSCh. 18 - Cost behavior estimation---high-low method P1 The...Ch. 18 - Prob. 4QSCh. 18 - Prob. 5QSCh. 18 - Prob. 6QSCh. 18 - Prob. 7QSCh. 18 - Prob. 8QSCh. 18 - Prob. 9QSCh. 18 - Prob. 10QSCh. 18 - Prob. 11QSCh. 18 - Prob. 12QSCh. 18 - Prob. 13QSCh. 18 - Prob. 14QSCh. 18 - Prob. 15QSCh. 18 - Prob. 16QSCh. 18 - Prob. 17QSCh. 18 - Prob. 18QSCh. 18 - Prob. 19QSCh. 18 - Prob. 20QSCh. 18 - Prob. 21QSCh. 18 - Following are five graphs representing various...Ch. 18 - Prob. 2ECh. 18 - Prob. 3ECh. 18 - Prob. 4ECh. 18 - Prob. 5ECh. 18 - Prob. 6ECh. 18 - Prob. 7ECh. 18 - Prob. 8ECh. 18 - Prob. 9ECh. 18 - Prob. 10ECh. 18 - Prob. 11ECh. 18 - Prob. 12ECh. 18 - Prob. 13ECh. 18 - Prob. 14ECh. 18 - Prob. 15ECh. 18 - Prob. 16ECh. 18 - Prob. 17ECh. 18 - Prob. 18ECh. 18 - Prob. 19ECh. 18 - Prob. 20ECh. 18 - Prob. 21ECh. 18 - Prob. 22ECh. 18 - Prob. 23ECh. 18 - Prob. 24ECh. 18 - Prob. 25ECh. 18 - Prob. 26ECh. 18 - Prob. 27ECh. 18 - Prob. 1PSACh. 18 - Prob. 2PSACh. 18 - Prob. 3PSACh. 18 - Prob. 4PSACh. 18 - Prob. 5PSACh. 18 - Prob. 6PSACh. 18 - Prob. 7PSACh. 18 - Prob. 1PSBCh. 18 - Prob. 2PSBCh. 18 - Prob. 3PSBCh. 18 - Prob. 4PSBCh. 18 - Prob. 5PSBCh. 18 - Prob. 6PSBCh. 18 - Prob. 7PSBCh. 18 - Prob. 18SPCh. 18 - Apple offers extended service contracts that...Ch. 18 - Prob. 2BTNCh. 18 - Prob. 3BTNCh. 18 - Prob. 4BTNCh. 18 - Prob. 5BTNCh. 18 - Prob. 6BTNCh. 18 - Prob. 7BTNCh. 18 - Prob. 8BTNCh. 18 - Prob. 9BTN
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- 7arrow_forwardQS 18-4 (Algo) Measuring costs using high-low method LO P1 The following information is available for a company's maintenance cost over the last seven months. Month Units Produced June 110 July 170 August 138 September 160 October 220 November December 250 70 Maintenance Cost $ 5,050 6,850 5,650 6,550 8,350 9.250 3,850 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High-Low method - Calculation of variable cost per unit produced Total cost at the high point Variable costs at the high point: Volume at the high point Variable cost per unit produced Total variable costs at the high point Total fixed costs Total cost at the low point Variable costs at the low point: Volume at the low point: Variable cost per unit produced Total variable costs at the low point Total fixed costsarrow_forward7arrow_forward
- Electronio ExperGecupancy Percentage 62 Month January April August 6,200 6,600 68 7,200 78 December 5,500 50 Jsing the highllow two point method to: 1 Determine the variable cost per 1poercent of occupancy 2 Estimate the fixed costs per month 3 What is the estimated total electric expense at 62 pecent of ocoupancy? ANSWER Month Electronic Expenses Oooupanoy Percentage High August 7,200 78 Low December 5,500 50 Difference 1,700 28 1 Variable cost per 1% of ocoupanoy = 61 2 Total variable cost of electric expense for December = Total fixed cost of electric expense for December = 3,035.71 2,464.29 Total variable cost of electric expense for August = Total fixed cost of electrio expense for August = 4,735.71 2,464.29 3 Using the fixed cost for December as the total fixed cost for estimation Total variable cost of electric expense at 62%. oooupancy = Total fixed oost of electric expense at 62% occupanoy Estimated total electric expense at 62% occupancy =arrow_forwardQuestion 26arrow_forward4arrow_forward
- Total Maintenance Production Volume (units) 1,850 units 1,500 units 2,600 units 2,275 units 2,750 units Month Cost $1,980 $1,800 $2,200 $2,180 $2,300 January February March April May Using the high-low method, the variable rate for maintenance is: Multiple Choice $0.75. $0.40. $2.00. $1.50.arrow_forward8 The following data are average times per order over the last month. Wait time to start production Inspection time 16.2 days 1.8 days Process time 2.7 days Move time 2.6 days Queue time 8.2 days The manufacturing cycle efficiency (MCE) would be closest to: А. 29%. В. 82%. С. 46%. D. 18%. Е. None of the abovearrow_forwardDiscussion Question The table below shows monthly data collected on production costs and on the number of units produced over a twelve month period. Level of Activity (Units Produced) Month Total Production Costs July $230,000 3,500 August 250,000 3,750 September October 260,000 3,800 220,000 3,400 November 340,000 5,800 December 330,000 5,500 January 200,000 2,900 February 210,000 3,300 March 240,000 3,600 April 380,000 5,900 May 350,000 5,600 June 290,000 5,000 a) Determine the variable cost per unit and the fixed cost using the high-low method. b) What is the equation of the total mixed cost function? c) Prepare the scatter diagram, clearly showing any outliers. d) Using the line of best-fit, determine the company's fixed cost per month and the variable cost per unit. (use o 5 5,000 units.) e) In view of the department's cost behaviour pattern, which of the two methods appear more appropriate? Explain your answer.arrow_forward
- Discussion Question The table below shows monthly data collected on production costs and on the number of units produced over a twelve-month period. Month Total Production Cost Level of Activity (Units Produced) July $230,000 3,500 August 250,000 3,750 September 260,000 3,800 October 220,000 3,400 November 340,000 5,800 December 330,000 5,500 January 200,000 2,900 February 210,000 3,300 March 240,000 3,600 April 380,000 5,900 May 350,000 5,600 June 290,000 5,000 d) Prepare the scatter diagram and insert the trendline or line of best-fit. Use a scale of 2 cm to represent 1,000 units on the x-axis & 2 cm to represent $50,000 on the y-axis. e) Using the line of best-fit, determine the company’s fixed cost per month and the variable cost per unit. (Use 0 & 5,000 units.) f) Which of the two methods appear more appropriate? Explain your answer.arrow_forwardExercise 18-3 (Part Level Submission) The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs Total Maintenance Costs Total Month January February March April May June $2,590 2,890 3,490 4,390 3,090 5,530 Machine Hours 330 380 530 660 530 730 (a1) Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g 12.250.) Variable cost per machine hourarrow_forwardUsing Least Square method compute for the variable and fixed cost Month Direct Labor Cost of Electricity Jan 170 4500 Feb 160 4225 Mar 150 4321 Apr 180 5250 May 173 4800 Jun 190 5100 Jul 210 4450 Aug 152 4200 Sep 220 5475 Oct 181 4760 Nov 177 4325 Dec 100 3975arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Pkg Acc Infor Systems MS VISIO CDFinanceISBN:9781133935940Author:Ulric J. GelinasPublisher:CENGAGE L
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:9781133935940
Author:Ulric J. Gelinas
Publisher:CENGAGE L
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license