EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 18, Problem 14PA

(a)

Summary Introduction

Interpretation: The probability that the project is completed within 33weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(a)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 33weeks deadline.

  z=33321.69=11.3=0.769

Refer probability distribution table.

For z0.769 .

  P(z0.769)=0.77935 .

Hence, the probability that the project is completed within 33weeks is 0.77935 .

(b)

Summary Introduction

Interpretation: The probability that the project is completed within 30weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(b)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 30weeks deadline.

  z=30321.69=21.3=1.539

Refer probability distribution table.

For z1.539 .

  P(z1.539)=0.06178 .

Hence, the probability that the project is completed within 30weeks is 0.06178 .

(c)

Summary Introduction

Interpretation: The probability that the project is completed within 35weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(c)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 35weeks deadline.

  z=35321.69=31.3=2.308

Refer probability distribution table.

For z2.308 .

  P(z2.308)=0.99134 .

Hence, the probability that the project is completed within 35weeks is 0.99134 .

(d)

Summary Introduction

Interpretation: The probability that the project is completed within 32weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(d)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 32weeks deadline.

  z=32321.69=01.3=0

Refer probability distribution table.

There is no value for z=0 .

Hence, the probability that the project is completed within 32weeks cannot be determined.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Since the end of World War II, globalization has steadily increased with rapid expansion around the turn of the 21st century. What are some of the forces driving globalization and international business? What are some of the challenges of engaging in international business compared to doing business in your home country?
PS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…
Choose one major approach to job design, and then discuss how best that approach can be utilized in either your current or previous employer, including a discussion of its strengths and weaknesses.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY