Concept explainers
(a)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project
(a)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(b)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(b)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(c)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(c)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(d)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(d)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
There is no value for
Hence, the probability that the project is completed within
Want to see more full solutions like this?
- Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table. Question Viewer Activity Expected Time (weeks) Variance A 4.0 1.00 B 5.5 0.96 C 4.0 0.15 D 11.5 1.52 E 6.5 2.40 F 8.5 2.55 G 5.0 0.69 The probability that this path will take more than 15 weeks to complete is ☐. (Enter your response rounded to four decimal places.)arrow_forwardCan you help me with part Barrow_forwardyou can solve it on table and i will copy itarrow_forward
- By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B Barrow_forward3.1 Use the generated information to calculate the NPV of the project, to decide whether to go ahead with the project. Investment required Expected economic lifetime R200 000 5 years. Minimum required rate of return 10% Net annual cash inflows 1st year 2nd year R40 000 R100 000 R90 000 3rd year R40 000 4th year R30 000 5th yeararrow_forwardThe activities necessary for the completion of this project are listed in the following table: Normal Crash Time Time Normal Crash Immediate Predecessor(S) Activity (Weeks) (Weeks) Cost Cost 6 3 $2,100 $2,700 -- 1 1,900 2,400 -- 3 400 800 6 1,950 2,500 с 3 1,100 1,200 A, B 1 3,100 4,000 D, E a. What is the project completion date? [Select] weeks b. What is the total cost required for completing this project on normal time? [Select] c. If you wish to reduce the time required to complete this project by 2 weeks, which activity(s) should be crashed? [Select] V and how much will this increase the total cost by? $ [Select] d. If you required an additional week reduction, what activity would you crash? [Select] and how much is the total 3 week cost of " crashing? $ [Select] ABCDEF 2003 12 4 8 4arrow_forward
- Example: Undertaking by a contractor to implement a contracting for excavation works according to the scheme below, undertaking to complete the work within a period of 36 weeks with a probability of 99% between in light of the contractor's probability. The actual time period for the completion of the project within the PERT technology? Act. a b te u C.P 1-2 7 8. 6.33 1 1 *1,2 2-3 6. 9 6.33 0.66 0.443 *2 2-4 3 7 8. 6.5 0.83 .693 *1 2-5 4 6. 0.33 3-6 9. 10 8.66 0.66 0.443 *2 4-7 6. 8 11 8.166 0.83 .693 *1 5-7 4 7 5.83 0.5 6-8 7 10 7.16 0.83 .693 *2 7-8 4 8 7.5 0.83 .693 *1 8-9 4 7 9 6.83 0.83 .693 *1,2arrow_forwardThe following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is the probability that the project will be completed 18 weeks before its expected completion date? 2- Draw Normal Curve & Analysis your solution with conclusionarrow_forwardWe are planning to develop a room reservation system that is estimated to have 400 story points of features. Let’s say our team’s velocity on two-week sprints ranges between 20 and 25 story points. Our project will start on Dec 1, 2021. If our customer wants the project to be in production by end of June 22, how likely will the project be successful? Why? Show your calculations.arrow_forward
- An electrical engineer wants to finish his new device production project within 47 days to meet his contract deadline. Explain what he should do to meet his plan . The project information is listed below. Please ignore the indirect cost.arrow_forwardEarned Value Analysis of the project supported by cost Performance Index and Schedule Performance Index readings. Comment on the progress of each activity and overall health of the project. Activity BCWS ACWP 1- Percentage Completion 80% Rs. 30,000 Rs. 25,000 2- Percentage Completion 40% Rs. 60,000 Rs. 80,000 3- Percentage Completion 100% Rs. 80,000 Rs. 78,000 Cumulative Rs. 170,000 Rs. 183,000arrow_forwardUsing the information given and the project completiontime calculated in Problem 9(a), reduce the completion time ofthe project by 5 weeks in the most economical wayarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.