EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 18, Problem 12PA
Summary Introduction

Interpretation: The total project completion time is to be calculated along with the lowest cost solution if the project is to be completed 3 weeks early.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

Expert Solution & Answer
Check Mark

Explanation of Solution

The activity with their immediate predecessor and estimated time, crash time, crash cost and normal cost is tabulated below.

    ActivityImmediate PredecessorEstimated Normal TimeCrash TimeNormal CostCrash Cost
    A-54400750
    BA8618002200
    CA768001100
    D-656001000
    EB, D, C8617002200
    FD328001000
    GD32500650
    HE43400600
    IF, G, H659001300

Table (1)

The network diagram for the activity shown in table (1) is shown below.

  EBK OM, Chapter 18, Problem 12PA , additional homework tip  1

Figure (1)

Therefore, the network diagram of the given project is shown in Figure (1).

The expression for the cost slope is given by,

  Cost Slope=Crash CostNormal CostNormal TimeNormal Cost

The cost slope for each activity is tabulated below.

    ActivityImmediate PredecessorEstimated Normal TimeCrash TimeNormal CostCrash CostCost Slope
    A-54400750350
    BA8618002200200
    CA768001100300
    D-656001000400
    EB, D, C8617002200250
    FD328001000200
    GD32500650150
    HE43400600200
    IF, G, H659001300400

Table (2)

Consider figure (1), the different paths and their completion times is tabulated below.

    PathCompletion time (weeks)
    A-B-E-H-I5+8+8+4+6=31
    A-C-E-H-I5+7+8+4+6=30
    D-E-H-I6+8+4+6=24
    D-G-I6+3+6=15
    D-F-I6+3+6=15

Table (3)

From Table (3), the maximum completion time is taken by path A-B-E-H-I . So, this is the critical path.

Therefore, the critical path is A-B-E-H-I and its duration is 31weeks .

Now the project is to be completed 3 weeks earlier.

Consider the critical path activities.

The lowest crash cost per week is of activity B and activity H.

Crash Activity B by 2 weeks and activity H by 1week .

  Crash B=2×200=400

And,

  Crash H=1×200=200

Thus, the additional cost of crashing the activity by 3weeks is,

  Additional cost=200+400=600

The new network diagram is shown in figure below.

  EBK OM, Chapter 18, Problem 12PA , additional homework tip  2

Figure (2)

Consider figure (2), the different paths and their completion times is tabulated below.

    PathCompletion time (weeks)
    A-B-E-H-I5+7+7+3+6=28
    A-C-E-H-I5+7+8+3+6=29
    D-E-H-I6+8+3+6=23
    D-G-I6+3+6=15
    D-F-I6+3+6=15

Table (4)

From Table (4), the maximum completion time is taken by path A-C-E-H-I . So, this is the critical path.

Therefore, the critical path is A-C-E-H-I and its duration is 29weeks .

But the desired project duration is 28 weeks .

Try different option.

Crash Activity B by 1 week, activity E by 1week and activity H by 1week .

  Crash B=1×200=200

And,

  Crash H=1×200=200

And,

  Crash E=1×250=250

Thus, the additional cost of crashing the activity by 3weeks is,

  Additional cost=200+200+250=650

The new network diagram is shown in figure below.

  EBK OM, Chapter 18, Problem 12PA , additional homework tip  3

Figure (3)

Consider figure (3), the different paths and their completion times is tabulated below.

    PathCompletion time (weeks)
    A-B-E-H-I5+7+7+3+6=28
    A-C-E-H-I5+7+7+3+6=28
    D-E-H-I6+7+3+6=22
    D-G-I6+3+6=15
    D-F-I6+3+6=15

Table (4)

From Table (4), the maximum completion time is taken by path A-C-E-H-I and A-B-E-H-I So, this are the critical path.

Therefore, the critical path are A-C-E-H-I and A-B-E-H-I and its duration is 28weeks .

Therefore, the crashing cost of the project is $650 .

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Activity (weeks) (weeks) Cost to Crash ($ per week) Immediate Predecessor(s) A 5 4 200 B 9 8 300 None None C 4 2 200 A 4 2 250 A E 3 3 B F 3 3 C, D G 3 1 150 D, E 6 4 350 F G 7 4 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity A Time according to schedule (weeks) Activity Time according to schedule (weeks) F G B C D E
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) ($ per week) Predecessor(s) А 5 4 200 None В 9 8. 300 None C 4 200 А 4 2 250 A 3 3 В F 3 С, D G 3 1 150 D, E 7 350 F 4 4 G Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) Activity Activity A В G C H E
IFS233 Donell Consulting recently completed an IT training platform implementation with a public firm. The project concluded after the completion of a testing, piloting and sign-off from the project stakeholders. Though completed, the project manager was reviewing their notes, in which they listed all the important occurrences that were recorded during various project phases: ● The pilot of the training platform is about to begin, and the COO of the firm has informed the project team that they want an additional 1000 staff trained and included, and the firm will be increasing budget accordingly. The new systems analyst replacement just found an issue with the way in which the training platform is recording information inputted from users. Apparently, it does note read or collate all the metadata produced during user inputs, and only considers metadata that leads to a complete sequence of inputs. This is going to cause issues in how we record the users' activities as the client wants to…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY