Concept explainers
Interpretation: The total project completion time is to be calculated along with the lowest cost solution if the project is to be completed
Concept Introduction:
Project
Explanation of Solution
The activity with their immediate predecessor and estimated time, crash time, crash cost and normal cost is tabulated below.
Activity | Immediate Predecessor | Estimated Normal Time | Crash Time | Normal Cost | Crash Cost |
A | - | ||||
B | A | ||||
C | A | ||||
D | - | ||||
E | B, D, C | ||||
F | D | ||||
G | D | ||||
H | E | ||||
I | F, G, H |
Table (1)
The network diagram for the activity shown in table (1) is shown below.
Figure (1)
Therefore, the network diagram of the given project is shown in Figure (1).
The expression for the cost slope is given by,
The cost slope for each activity is tabulated below.
Activity | Immediate Predecessor | Estimated Normal Time | Crash Time | Normal Cost | Crash Cost | Cost Slope |
A | - | |||||
B | A | |||||
C | A | |||||
D | - | |||||
E | B, D, C | |||||
F | D | |||||
G | D | |||||
H | E | |||||
I | F, G, H |
Table (2)
Consider figure (1), the different paths and their completion times is tabulated below.
Path | Completion time (weeks) |
Table (3)
From Table (3), the maximum completion time is taken by path
Therefore, the critical path is
Now the project is to be completed
Consider the critical path activities.
The lowest crash cost per week is of activity B and activity H.
Crash Activity B by
And,
Thus, the additional cost of crashing the activity by
The new network diagram is shown in figure below.
Figure (2)
Consider figure (2), the different paths and their completion times is tabulated below.
Path | Completion time (weeks) |
Table (4)
From Table (4), the maximum completion time is taken by path
Therefore, the critical path is
But the desired project duration is
Try different option.
Crash Activity B by
And,
And,
Thus, the additional cost of crashing the activity by
The new network diagram is shown in figure below.
Figure (3)
Consider figure (3), the different paths and their completion times is tabulated below.
Path | Completion time (weeks) |
Table (4)
From Table (4), the maximum completion time is taken by path
Therefore, the critical path are
Therefore, the crashing cost of the project is
Want to see more full solutions like this?
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs Activity A B С D E F G H Normal Time (weeks) 5 9 4 4 3 3 Activity A B с D Crash Time (weeks) 4 8 2 2 3 3 00000 6 Cost to Crash (5 per week) 250 350 881 18889 G 250 300 200 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers) Time according to schedule (weeks) 400 Activity F Immediate Predecessor(s) None None A A B C.D D, E F G Time according to schedule (weeks)arrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Activity Time (days) (days) AB А C D E 67555 5 BCD w 55 с 4 2 Activity A E 3 Normal Cost $800 $300 $600 $750 $1,200 Immediate Total Cost with Crashing Predecessor(s) $1,100 $500 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) $650 $1,500 $1,650 - Each Activity Should be Reduced BY (days) A Carrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. . Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) Predecessor(s) (S per week) 300 A 4 None None B 4 50 C 6. 300 250 A E 1 B. C.D D, E 4 200 H. 4 2 200 2. Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) 777arrow_forward
- Please do not give solution in image formate thanku. There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 4 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $400, E is $415 and all other activities is : $100 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1000 per week, E is $1200 per week and for all other activities is $200 per activity per week. You have a maximum crashing budget of $2505. The maximum possible reduction in the project duration will be: a. 2 weeks b. 3 weeks c. 4 weeks d. 5 weeks e. 6 weeksarrow_forwardA leading artist is working with a specialist metalworking firm to produce an ambitious piece of public art that will stand in the main square of a city. The project is controversial – many citizens feel the artwork will clash with the traditional architecture of surrounding buildings. However, the mayor is firmly behind the project. A large share of the cost of the artwork is being met by a donation from a successful local entrepreneur. They have made it clear that they will stop the funding at any time if they feel the project is not being properly managed and there is a risk that the artwork will have the kind of construction and public safety problems that similar artworks have had elsewhere. Suggest four ways you think would keep this person supporting the project as the work proceeds. For each of these ways, state who would be responsible for it. How, when and where would each way be done?arrow_forwardplease solve for question Carrow_forward
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Activity (weeks) Crash Time (weeks) Cost to Crash ($ per week) Immediate Predecessor(s) 59 5 4 4 82233-6 3337 ABCDEFGH - 4 200 None 300 None 200 A 250 A B C, D 1 150 D, E 350 F G 4 4 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) 3 1 Activity Time according to schedule (weeks) Activity A 4 F B 8 G C 3 H 6 D 3 4 E 3 The cost of shortening of project is $ ☐. (Enter your response as a whole number.)arrow_forwardProject B is the development of a facility in a remote area, of about GHS 5 million in value, of approximately 18 months’ planned duration. It is 30 per cent completed. Earned Value analysis shows that the project is not achieving its planned cost or progress targets. The project is also not achieving quality requirements. Some of the specialized components used for this project are only oSbtainable from overseas suppliers and are difficult to transport over the rough terrain near the project site. There has been a delay on ordering these components. The transportation of these components, which must be booked several months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the requisite set of skills to install them. There are also several other risks associated with this project, including a quite basic business case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks and the potential for…arrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project threethree weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity Normal Time (weekweeks) Crash Time (weekweeks) Cost to Crash ($ per weekweek) Immediate Predecessor(s) A 55 44 300300 None B 77 44 5050 None C 77 66 300300 A D 77 66 250250 A E 11 11 long dash— B F 33 33 long dash— C, D G 55 44 200200 D, E H 44 22 200200 F I 22 22 long dash— G Part 2 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as…arrow_forward
- What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A Carrow_forwardImage of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.arrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Activity Time (days) Time (days) A B C D E 580 4 (O ∞ 6 8 4 6 3 4 5 Normal Cost Activity A B C D E $800 $200 $600 $750 $1,200 Total Cost with Crashing Immediate Predecessor(s) $1,100 $500 $650 The total cost of crashing the project by 4 days is $ $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the tab below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) 1 0 1 2 3 | | | < 0 (Enter your response as a whole number.)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.