OPERATIONS MANAGEMENT (LL) W/CONNECT
14th Edition
ISBN: 9781265502942
Author: Stevenson
Publisher: MCG CUSTOM
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 17, Problem 6P
PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.
Reconsider the network diagram of Problem 1a. Suppose that after 12 weeks, activities 1-2, 1-3, and 2-4 have been finished; activity 2-5 is 75 percent finished; and activity 3-6 is half finished. How many weeks after the original start time should the project be finished?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature
could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Immediate Predecessor(s)
Activity
A
B
C
D
E
F
G
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are A-E-G
c) The project length for the leadership training program development project = 22 days.
d) Slack time for each of the activities is:
B
A, D
C
E, F
Activity
A
B
Slack Time
0
Time (days)
10
6
3
2
4
8
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature
could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Immediate Predecessor(s)
Activity
ABCDEFG
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
B
A, D
C
E, F
Time (days)
4
5
3
10
4
6
10
Preceding
Activity
Crashed Cost per
week
$600
$700
$400
Activity
Normal Completion
Time (week)
Crashed Completion
time (week)
A
7
5
B
12
10
A
8
2
$800
$300
$500
E
C, D
5
4
F
E
9
8
D. F
10
10
i.
Draw the network diagram linking all the activities in a way that it shows if there exist any
preceding activity/activities before starting each of the mentioned activities in the above
table,
ii.
Showing the earliest start time, the earliest finish time, the latest start time and the latest
finish time of each of the activities in the project determine the completion time of the
project and the critical path.
ii.
Find the slack time (delay time) of each of the activities, the critical and the non-critical
activities.
Find the minimum possible completion time of the project by considering the crashed
completion times and the minimal total cost of that crashing the project.
iv.
Need proper handwritten answers. Thank you!
Chapter 17 Solutions
OPERATIONS MANAGEMENT (LL) W/CONNECT
Ch. 17.3 - Will the AI technology render project managers...Ch. 17.3 - Prob. 1.2RQCh. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...
Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - Prob. 9PCh. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Please do not give solution in image format thankuarrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) B A, D C E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B - D - E - G. c) The project length for the leadership training program development project = 28 days. d) Slack time for each of the activities is: ABCDEFG Activity A Slack Time ∞ or w w w 10arrow_forward1. A project has been defined to contain the following list of activities along with their required times for completion. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.arrow_forward
- i need the answer quicklyarrow_forwardPlz sir solve this for mearrow_forwardOmar has recently been hired as the HIM director at a large medical center. He realizes that he has a number of employees whose job duties would allow them to work from home. Because his boss has asked him for a space reduction proposal, he recognizes the need to implement a work-at-home program for his employees. What steps should Omar take in developing a security program for the employees who will work from home? Develop a checklist of considerations, along with a list of resources that would facilitate his security program.arrow_forward
- The table below contains scheduling data for a software development project to be undertaken in an IT company. (i) Identify the critical activities and total duration for the project. (ii) Draw a network diagram using the Activity-on-Arrow (AOA) method to depict the flow of the activities showing interdependencies (iii) Using the data provided in the above table, create a float table for the project.arrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G H IMG_A2D52FAF8F3D-1.jpeg Activity This answer has not been graded yet. A B с (c) Develop the activity schedule for the project. D Survey building site Develop initial design Obtain board approval E F G Description H Select architect Establish budget Finalize design Obtain financing 0 Hire contractor L L | (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Immediate Predecessor Earliest Start (b) Identify the critical path. (Enter your answers as a comma-separated list.) 4 A, B с Latest Start с D, E E F, G Time (weeks) 5 5 9 Earliest Finish 13 4 7 15 11 6 9 Latest Finish 4 Slack (d) Does it appear…arrow_forwardPlease do not give solution in image format thankuarrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Predecessor (S) Time (Days) A - 2 B - 5 C - 1 D B 10 E A;D 3 F C 6 G E;F 8 Which activity has the highest slack timearrow_forwardCan anybody draw a network analysis diagram of this problem?arrow_forwardOnly typed explanation otherwise leave itarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY