Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN: 9781337788281
Author: James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 17, Problem 23E
1.
To determine
Prepare a schedule showing the amount of gross profit recognized by Company T by assuming that performance obligation is ascertained to be satisfied over time.
2.
To determine
Prepare a schedule showing the amount of gross profit recognized by Company T by assuming that performance obligation is ascertained at a point in time.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019 through 2021). The contract price is $1,200,000, and the construction costs (both actual and estimated) total $705,000 for the 3 years. Tarlo's estimate of progress toward satisfaction of the performance obligation at the end of each year is as follows: 2019, 20%; 2020, 75%; 2021, 100%.
Required:
1. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is determined to be satisfied over time.
Tarlo Company
Gross Profit: Percentage-of Completion Method
2019 through 2021
Amount
2019
$
2020
2021
Total gross profit
$
2. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is satisfied at a point in time. If an amount is zero, enter "0".
Tarlo Company
Gross Profit: Completed-Contract Method
2019 through 2021…
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,510,000 $ 2,316,600 Estimated costs to complete as of year-end 5,616,000 2,106,000 0 Billings during the year 2,120,000 3,574,000 4,306,000 Cash collections during the year 1,860,000 3,400,000 4,740,000 Westgate recognizes revenue over time according to percentage of completion. rev:
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,860,000 $ 3,260,000 Estimated costs to complete as…
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:
Cost incurred during the year
$
2,016,000
$
2,808,000
$
2,613,600
Estimated costs to complete as of year-end
5,184,000
2,376,000
0
Billings during the year
2,180,000
2,644,000
5,176,000
Cash collections during the year
1,890,000
2,500,000
5,610,000
Westgate recognizes revenue over time according to percentage of completion.
4. Compute the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
Cost incurred during the year
$
2,016,000
$
3,890,000
$
3,290,000…
Chapter 17 Solutions
Intermediate Accounting: Reporting And Analysis
Ch. 17 - Prob. 1GICh. 17 - Prob. 2GICh. 17 - When a company recognizes revenue during a period,...Ch. 17 - Prob. 4GICh. 17 - Prob. 5GICh. 17 - What is the proper accounting for a wholly...Ch. 17 - If a seller enters into more than one contract...Ch. 17 - Prob. 8GICh. 17 - Prob. 9GICh. 17 - Prob. 10GI
Ch. 17 - Prob. 11GICh. 17 - Prob. 12GICh. 17 - Prob. 13GICh. 17 - Prob. 14GICh. 17 - Prob. 15GICh. 17 - Prob. 16GICh. 17 - If the standalone selling price of a good or...Ch. 17 - Prob. 18GICh. 17 - Prob. 19GICh. 17 - If the sellers performance creates on asset (e.g.,...Ch. 17 - Describe input and output methods used to measure...Ch. 17 - Prob. 22GICh. 17 - Prob. 23GICh. 17 - Prob. 24GICh. 17 - Prob. 25GICh. 17 - A company should recognize revenue when a. the...Ch. 17 - A contract between one or more parties creates: a....Ch. 17 - Morgan Company and its customer agree to modify...Ch. 17 - Chlorine Corp. has a contract to deliver pool...Ch. 17 - Prob. 5MCCh. 17 - Prob. 6MCCh. 17 - In accounting for a long-term construction...Ch. 17 - Prob. 9MCCh. 17 - Prob. 10MCCh. 17 - CustomTee Inc. contracts with various customers to...Ch. 17 - Yankee Corp. agrees to provide Albany Company 24...Ch. 17 - Prob. 3RECh. 17 - Prob. 4RECh. 17 - LongDrive sells a specialized golf club that has...Ch. 17 - Prob. 6RECh. 17 - VolleyElite runs a volleyball program consisting...Ch. 17 - Enterprise Solutions Inc. licenses its...Ch. 17 - Prob. 9RECh. 17 - Magical Memories sells Florida theme park vacation...Ch. 17 - Prob. 11RECh. 17 - Robotics Inc. contracts with a customer to build a...Ch. 17 - CoolShoes sells its elite tennis shoes to sports...Ch. 17 - Using the information in RE17-13, what journal...Ch. 17 - GameDay sells recreational vehicles along with...Ch. 17 - Prob. 16RECh. 17 - Using the information provided in RE17-16, prepare...Ch. 17 - Prob. 18RECh. 17 - Prob. 19RECh. 17 - Company enters into a contract with Dearborn Inc....Ch. 17 - Consider each of the following scenarios: a. A...Ch. 17 - On August 1, 2019, Aiken Corp. enters into a...Ch. 17 - On January 1, 2019, Spring Fashions Inc. enters...Ch. 17 - On January 1, 2019, Loud Company enters into a...Ch. 17 - Assume the same facts as in El7-5. On July 1,...Ch. 17 - Assume the same facts as in E17-5 and ignore...Ch. 17 - Prob. 8ECh. 17 - GrillMaster Inc. sells an industry-leading line of...Ch. 17 - WaterWorld Inc. operates an aquarium and water...Ch. 17 - Prob. 11ECh. 17 - Jonas Consulting enters into a contract to provide...Ch. 17 - On March 1, 2019, Elkhart enters into a new...Ch. 17 - On January 5, 2019, ShoeKing Corp. sells for cash...Ch. 17 - On January 1, 2019, Piper Company entered into an...Ch. 17 - On January 1, 2019, Fulton Inc. enters into a...Ch. 17 - Prob. 17ECh. 17 - On December 1, 2019, AwakcAllNight Inc. sells...Ch. 17 - Rix Company sells home appliances and provides...Ch. 17 - Assume the same facts as in E17-19, except that...Ch. 17 - Crazy Computer Store sells a back-to-school bundle...Ch. 17 - Each of the following is an independent situation...Ch. 17 - Prob. 23ECh. 17 - Prob. 24ECh. 17 - Koolman Construction Company began work on a...Ch. 17 - Prob. 26ECh. 17 - Each of the following independent situations...Ch. 17 - JustKitchens Inc. provides services to restaurants...Ch. 17 - On January 1, 2019, ForeRunner Inc. enters into a...Ch. 17 - January 2, 2019, TI enters into a contract with...Ch. 17 - Prob. 5PCh. 17 - Prob. 6PCh. 17 - Fender Construction Company receives a contract to...Ch. 17 - SoccerHawk Merchandise Inc. enters into a 6-month...Ch. 17 - Prob. 9PCh. 17 - Prob. 10PCh. 17 - Blackmon Company provides locator services to the...Ch. 17 - Prior to ASU 2014-09 changing the principles...Ch. 17 - The first step in the revenue recognition process...Ch. 17 - Prob. 3CCh. 17 - One of the more difficult issues that companies...Ch. 17 - Prob. 5CCh. 17 - On October 1, 2019, Grahams WeedFeed Inc. signs a...Ch. 17 - On January 1, 2019, Mopps Corp. agrees to provide...Ch. 17 - Prob. 8CCh. 17 - Revenue for a company is recognized for accounting...Ch. 17 - Prob. 10C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?arrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Costs incurred during the year Estimated costs to complete as of year-end Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2022 2021 $2,184,000 $3,510,000 5,616,000 2,106,000 2021 2,120,000 1,860,000 2022 . Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs curred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest hole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 $2,184,000 5,616,000 2023 2023 $2,316,600 3,574,000 4,306,000…arrow_forwardIn 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 2020. Information related to the contract is as follows:2018 2019 2020Cost incurred during the year $2,400,000 $3,600,000 $2,200,000Estimated costs to complete as of year-end 5,600,000 2,000,000 –0–Billings during the year 2,000,000 4,000,000 4,000,000Cash collections during the year 1,800,000 3,600,000 4,600,000Westgate recognizes revenue over time according to percentage of completion.Required:1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.2. Prepare all necessary journal entries for each of the years (credit “various accounts” for construction costsincurred).3. Prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. Indicate whetherany of the amounts shown are contract assets or contract liabilities.4. Calculate the amount of revenue and gross…arrow_forward
- In 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2021 $ 135 Cash collected on project during 2021 $ 105 Construction in progress, 12/31/2021 $ 207 Estimated percentage of completion during 2021 60 % How much cash remains to be collected by CCC on the project?arrow_forwardAt the beginning of 2021, Florida Road Construction entered into a contract to build a road for the government. Construction will take four years. The following information as of December 31, 2021 is available: Revenue according to contract 10,000,000 Total expected cost 8,000,000 Cost incurred during 2021 1,200,000 Cost incurred during 2022 2,400,000 Cost incurred during 2023 Cost incurred during 2024 1,600,000 2,800,000 Compute for the reported Gross Profit of Florida using: Year 2021 2022 2023 2024 Completed Contract Method Zero Profit Method Percentage of Completion Methodarrow_forwardDiamond Construction which has a calendar year end, has entered into a non-cancellable fixed priced contract of $4,200,000 beginning May 1, 2019 to build a road for a municipality. It has been estimated that the road will be complete by April 2021. The following data pertains to the construction period: 2019 2020 2021 Costs during the year 1,850,000 1,700,000 500,000 Estimated costs to complete 2,050,000 700,000 - Total Required Assuming the company uses the percentage of completion method based on input, calculate and record the revenue and profit for each year (i.e. prepare only the annual journal entry reporting the revenue / profit for the year).arrow_forward
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,344,000 $ 3,960,000 $ 1,645,600 Estimated costs to complete as of year-end 5,456,000 1,496,000 0 Billings during the year 2,800,000 4,504,000 2,696,000 Cash collections during the year 2,600,000 4,400,000 3,000,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.Required:1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries…arrow_forwardOn September 30, 2019, STONE REACH Co., Inc. was awarded the contract to build a 1,000 room hotel for P24,000,000. Among others, the parties agreed to the following:1.Ten percent mobilization fee (deductible from "final billing") payable within ten days from the signing of the contract.2.Retention of ten per cent on all billings (to be paid with the final billing, upon completion and acceptance of the project); and 3.Progress billings are to be paid within 2 weeks upon acceptance. By the end of 2019, the company had presented one progress billing, corresponding to 10% completion, which was evaluated and accepted by the client on December 29, 2019 for payment in January of the next year. In 2019, assuming use of the percentage-of-completion method of accounting STONE REACH Co., Inc. received a total fee ofarrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time according to percentage of completion. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Costs incurred…arrow_forward
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time according to percentage of completion. 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)arrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2021. Information related to the contract is as follows. Cost incurred during year $2,016,000 $2,808,000 $2,613,000 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion Required 1.- Calculate the amount of revenue and gross profit (loss) to be organized in each of three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)…arrow_forwardIn 2021, Crane Corporation began construction work under a three-year contract. The contract price is $ 480000. Crane uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2021, follow: Balance Sheet Accounts receivable—construction contract billings $ 192000 Construction in progress $ 600000 Less contract billings 480000 Costs and recognized profit in excess of billings 120000 Income Statement Income (before tax) on the contract recognized in 2021 $ 120000 How much cash was collected in 2021 on this contract? $ 480000 $ 48000 $ 288000 $ 192000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning