Concept explainers
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
a. Construct a network diagram. You can use either AOA or AON (see Example 5).
b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus.
a)
To construct: A network diagram.
Answer to Problem 12P
Answer
Network diagram:
Explanation of Solution
Given information:
Activity | Immediate predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 2 | 4 | 6 | |
D | A | 6 | 8 | 10 |
E | D | 7 | 9 | 12 |
H | E | 2 | 3 | 5 |
F | A | 3 | 4 | 8 |
G | F | 5 | 7 | 9 |
B | 2 | 2 | 3 | |
I | B | 2 | 3 | 6 |
J | I | 3 | 4 | 5 |
K | J | 4 | 5 | 8 |
C | 5 | 8 | 12 | |
M | C | 1 | 1 | 1 |
N | M | 6 | 7 | 11 |
O | N | 8 | 9 | 13 |
End | H, G, K, O |
Formula to calculate expected time and variance:
Calculation of mean and variance:
Activity | Optimistic time | Most likely time | Pessimistic time | Expected time | Standard deviation | Variance |
A | B | C | (A+(4*B)+C)/6 | (C-A)/6 | (C-A)^2/6^2 | |
A | 2 | 4 | 6 | 4 | 0.667 | 0.444 |
D | 6 | 8 | 10 | 8 | 0.667 | 0.444 |
E | 7 | 9 | 12 | 9.17 | 0.833 | 0.694 |
H | 2 | 3 | 5 | 3.17 | 0.500 | 0.250 |
F | 3 | 4 | 8 | 4.5 | 0.833 | 0.694 |
G | 5 | 7 | 9 | 7 | 0.667 | 0.444 |
B | 2 | 2 | 3 | 2.17 | 0.167 | 0.028 |
I | 2 | 3 | 6 | 3.33 | 0.667 | 0.444 |
J | 3 | 4 | 5 | 4 | 0.333 | 0.111 |
K | 4 | 5 | 8 | 5.33 | 0.667 | 0.444 |
C | 5 | 8 | 12 | 8.17 | 1.167 | 1.361 |
M | 1 | 1 | 1 | 1 | 0.000 | 0.000 |
N | 6 | 7 | 11 | 7.5 | 0.833 | 0.694 |
O | 8 | 9 | 13 | 9.5 | 0.833 | 0.694 |
End |
Network diagram:
The activity on arrow diagram is constructed. The activities are mentioned on the arrows. The arrows in the diagram are mentioned in the precedence order. The arrows indicates the successor for each node.
b)
To determine: The probability of each bonus.
Answer to Problem 12P
Explanation of Solution
Given information:
- If the project is finished in 26 weeks the bonus is $1,000.
- If the project is finished in 27 weeks the bonus is $500.
Calculation of expected duration, variance and standard deviation for each path:
Path A-D-E-H:
Path A-F-G:
Path B-I-J-K:
Path C-M-N-O:
Bonus of $1,000 (less than or equal to 26 weeks):
Calculation of probability of completion in less than or equal to 26 weeks:
Calculation of z value for all paths:
Formula:
Path A-D-E-H:
From the standard normal distribution table,
The probability value for (z = 1.23) is 0.8907.
Path A-F-G:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path B-I-J-K:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path C-M-N-O:
From the standard normal distribution table,
The probability value for (z = -0.10) is 0.4602.
Probability of completion in less than or equal to 26 weeks:
The probability of achieving a bonus of $1,000 is 0.4099.
Bonus of $500 (less than or equal to 27 weeks):
Calculation of probability of completion in less than or equal to 27 weeks:
Calculation of z value for all paths:
Formula:
Path A-D-E-H:
From the standard normal distribution table,
The probability value for (z = 1.96) is 0.9750.
Path A-F-G:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path B-I-J-K:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path C-M-N-O:
From the standard normal distribution table,
The probability value for (z = 0.50) is 0.6915.
Probability of completion in less than or equal to 27 weeks:
The probability of achieving a bonus of $500 is 0.6742.
Want to see more full solutions like this?
Chapter 17 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
- 1) View the video What is Operations Management (14.01 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 1 and/or 2) after watching this video. (https://www.viddler.com/embed/d01189e1) Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) View the video What McDonald’s is serving up at its new CosMc’s Chain (3.42 mins, Ctrl+Click in the link), and answer the following questions: (https://www.youtube.com/watch?v=k7ojpUzE8q4) i) From a strategic perspective, why do you think McDonald’s is opting for this new chain rather than trying to launch the new menu in its existing restaurants? ii) What factors do you think in McDonald’s external and internal environments are driving its decision to open the CosMc’s locations? iii) How do you think this format will improve McDonald’s profit margin as compared to its regular fast-food restaurants? Note: As a…arrow_forwardSince the end of World War II, globalization has steadily increased with rapid expansion around the turn of the 21st century. What are some of the forces driving globalization and international business? What are some of the challenges of engaging in international business compared to doing business in your home country?arrow_forwardPS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forward
- Choose one major approach to job design, and then discuss how best that approach can be utilized in either your current or previous employer, including a discussion of its strengths and weaknesses.arrow_forwardThe results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value. Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be includedarrow_forwardi). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.arrow_forward
- In the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why. ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.arrow_forwardi). Complete the table for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible. You should support your answer with numerical data derived from Table 3. In comparing the costs, state any other assumptions made.arrow_forwardi). Complete for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible.arrow_forward
- Complete the table for a Chase production plan.arrow_forwardHow much can the garden centre expect to sell during each quarter of next year (Year 3) accounting for seasonality? Your forecast must make use of seasonal indices. All workings must be shown in full. (NOTE: Please round your calculations to three decimal places).arrow_forwardPS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,