Chapter 16, Problem 8P
The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.
a. Determine the processing sequence at the first work center using each of these rules: (1) FCFS, (2) S/O.
b. Compute the effectiveness of each rule using each of these measures: (1) average flow time, (2) average number of jobs at the work center.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
i need help creating a flow chart for my model in the attachment
The table below shows the time stamps of 10 customers who visited a local bank branch from 9:00 a.m. to 9:45 a.m. What is the flow
time of customers?
Customer
1
2
3
4
5
6
7
8
9
10
Time in
9:2
9:5
9:6
9:8
9:8
9:10
9:12
9:15
9:18
9:19
Time out
9:7
9:10
9:17
9:23
9:36
9:21
9:41
9:41
9:28
9:42
Instruction: Round your answer to 1 decimal place.
Flow time of customers
3.5 minutes
Kindly help
Chapter 16 Solutions
OPERATIONS MANAGEMENT >C<
Ch. 16 - Why is scheduling fairly simple for repetitive...Ch. 16 - Prob. 2DRQCh. 16 - What are Gantt charts? How are they used in...Ch. 16 - Prob. 4DRQCh. 16 - Briefly describe each of these priority rules: a....Ch. 16 - Why are priority rules needed?Ch. 16 - What problems not generally found in manufacturing...Ch. 16 - Explain forward and backward schedulings and each...Ch. 16 - Prob. 9DRQCh. 16 - Prob. 10DRQ
Ch. 16 - Prob. 11DRQCh. 16 - What general trade-offs are involved in sequencing...Ch. 16 - Prob. 2TSCh. 16 - Prob. 3TSCh. 16 - One approach that can be effective in reducing the...Ch. 16 - Doctors and dentists offices frequently schedule...Ch. 16 - Prob. 3CTECh. 16 - Use the assignment method to determine the best...Ch. 16 - Rework Problem 1, treating the numbers in the...Ch. 16 - Assign trucks to delivery routes so that total...Ch. 16 - Develop an assignment plan that will minimize...Ch. 16 - Use the assignment method to obtain a plan that...Ch. 16 - The following table contains information...Ch. 16 - Using the information presented in the following...Ch. 16 - The following table shows orders to be processed...Ch. 16 - A wholesale grocery distribution center uses a...Ch. 16 - The times required to complete each of eight jobs...Ch. 16 - Prob. 11PCh. 16 - A shoe repair operation uses a two-step sequence...Ch. 16 - The following schedule was prepared by the...Ch. 16 - The production manager must determine the...Ch. 16 - A foreman has determined processing times at a...Ch. 16 - Given the information in the following table,...Ch. 16 - Given the following information on job times and...Ch. 16 - Prob. 18PCh. 16 - The following table contains order-dependent setup...Ch. 16 - The following table contains order-dependent setup...Ch. 16 - Prob. 21PCh. 16 - Given this information on planned and actual...Ch. 16 - Given the following data on inputs and outputs at...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Prob. 1CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A bank receives loan applications from 6 customers a day. The bank has promised customers that applications will be processed in the order they are received. The table below shows the applications in the order they were received, the processing time for each loan application, and the due date that customers need to hear about their application status: Customer Processing time (days) Due date (days) A 9 13 B 11 18 C 8 11 D 7 13 E 10 22 F 12 28 Average flow time days Average tardiness days Average number of jobs applicationsarrow_forwardA company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operation when shipments are received:i) Operation A-draw a random sample, package, and deliver to testing, andii) Operation B-test the materials and issue a disposition reportThere are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are:Shipment Operation A (hours) Operation B (hours)1 1.5 1.02 1.1 2.73 1.2 1.44 0.7…arrow_forwardb) A company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operations when shipments are received: Operation A – draw a random sample, package, and deliver to testing; and Operation B – test the materials and issue a disposition report. There are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are given in the table below. Shipment Operation A (hours) Operation B (hours) A 1.5 1.0 В 1.1 2.7 1.2 1.4 D 0.7 1.6 E 1.6 1.5 F 1.9 2.9 Use Johnson's Rule to set the sequence of processing the shipments through Quality Control. i. ii. How much total time is required to process all the six shipments through Quality Control? Show all times on a Gantt Chart. w luarrow_forward
- Number of Processing Time for A Processing Time for B Processing Time for C (minutes) Resource Workers (minutes) (minutes) 1 2 2 2 4 4 5 1 15 3 2 6. 4arrow_forwardThe following six jobs are to be scheduled on a single machine: Job 1 2 3 4 5 6 Processing time 130 160 210 70 140 90 (min.) a. Suppose the jobs are processed in FCFS numerical order. Compute the makespan, flow time for each job, and overall average flow time. Round your answers to the nearest whole number. Job Flow Time (min) 1 2 3 4 5 6 Makespan: Average flow time: b. In what order would the jobs be processed using the SPT rule? The SPT sequence is -Select---Select---Select---Select---Select- V -Select- V. Compute the average flow time after each job is completed. Round your answer to the nearest whole number. Average flow time: minutes Compare this answer with your answer to part a. The -Select- minutes minutes ✓ minimizes flow time and gets the most work done in the least amount of time.arrow_forwardWorkPro is a small manufacturer. It uses a job process for production. The following sample of jobs are listed in the order that they were received. Job Due Date Operation Time P 5 1 Q 20 8 R 8 5 S 11 6 T 3 12 When the shortest operating time (SOT) rule is applied to the sample of jobs, the resulting sequence is: A. Choos the following answer choice. T, P, R, S, Q R, S, T, P, Q P, Q, R, S, T P, R, S, Q, T B. In the WorkPro example above, average flow time for the sample of jobs when sequenced by the shortest operating time (SOT) rule is approximately: 19.8 14.2 4.8 6.4 C. In the WorkPro example above, average lateness for the sample of jobs when sequenced by the earliest due date (EDD) rule is approximately: Group of answer choices 10.4 4.8 7.8 5.8 D. Using the sample of jobs in the WorkPro example above, the shortest operating time (SOT) rule appears more attractive than the earliest due date (EDD) rule…arrow_forward
- Using the information presented in the following table, identify the processing sequence that wouldresult using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, determine (1) average jobflow time, (2) average job tardiness, and (3) average number of jobs in the system. Jobs are listedin order of arrival. (Hint: First determine the total job time for each job by computing the total processing time for the job and then adding in the setup time. All times and due dates are in hours.)JobProcessingTime per UnitUnitsper JobSetupTimeDueDatea .14 45 0.7 4b .25 14 0.5 10c .10 18 0.2 12d .25 40 1.0 20e .10 75 0.5 15arrow_forwardStation 1 Machine A 20 min/unit Note: Station 1 Machine B 20 min/unit Station 2 12 min/unit Station 1 Machine A Station 1 Machine B Station 2 Station 3 Station 3 A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The process time of each machine/station is indicated in the flowchart. The unit is then processed at Stations 2 and 3 before leaving the work cell. Specify the bottleneck(s). 8 min/unit 1- These are checkboxes, you can select more than one option if needed.arrow_forwardPlease do not give solution in image format thankuarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY