
Concept explainers
The following table contains information concerning four jobs that are awaiting processing at a work center.
Sequence the jobs using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. Assume the list is by order of arrival.
b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.
c. Is one method superior to the others? Explain.
a)
1)

To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is A-B-C-D.
1)

To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is A-B-C-D.
2)

To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using SPT:
According to SPT, the job that has the shortest processing would be served first and it goes on as the processing time increase. Duration should be assembled in the ascending order
Hence, the sequence of jobs using SPT is D-C-B-A.
3)

To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would be going on from earliest due date to latest due date.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using EDD:
According to EDD, the job that has the earliest due date would be served first and it goes on as the due date increases. The job should be arranged based on due date. Due date should be assembled in the ascending order
Hence, the sequence of jobs using EDD is C-B-D-A.
4)

To determine: Sequence of jobs based on decision rule critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using critical ratio:
Initial critical ratio should be determined at day 0:
Job | Processing time (days) | Due date (days) | Critical ratio |
A | 14 | 20 | 1.43 |
B | 10 | 16 | 1.6 |
C | 7 | 15 | 2.14 |
D | 6 | 17 | 2.83 |
Critical ratio for Job A:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Critical ratio for Job B:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Critical ratio for Job C:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Critical ratio for Job D:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Job A has the lowest critical ratio. Thus, it will be completed first. Hence, Job A would be completed first in the sequence of jobs.
Determine the critical ratio after the completion of Job A:
As the processing time of job A is 14 days, completion day of completed day would be 14.
Job | Processing time (days) | Due date (days) | Critical ratio |
A | - | - | - |
B | 10 | 16 | 0.20 |
C | 7 | 15 | 0.14 |
D | 6 | 17 | 0.50 |
Critical ratio for Job B:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Critical ratio for Job C:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Critical ratio for Job D:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job C has the lowest critical ratio. Hence, Job C would be completed next in the sequence of jobs after Job A.
Determine the critical ratio after the completion of Job A and Job C:
As the processing time of job A is 14 days and Job C is 7, completion day of completed day would be 21 (14+7).
Job | Processing time (days) | Due date (days) | Critical ratio |
A | - | - | - |
B | 10 | 16 | -0.50 |
C | |||
D | 6 | 17 | -0.67 |
Critical ratio for Job B:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Critical ratio for Job D:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job D has the lowest critical ratio. Hence, Job D would be completed next in the sequence of jobs after Job A and Job C.
As Job B is the remaining job, it will be completed next.
Hence, the sequence of jobs using critical ratio is A-C-D-B.
b)

To determine: Average flow time, average tardiness, and average number of jobs for each method.
Introduction: Rules that are framed for providing the order in which the jobs need to be performed are termed as priority rules. These rules are more suitable for process-oriented facilities. The main purpose of priority rules are on-time completion of jobs, efficient utilization of services, and the maximizing the customer services.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
First Come First Served:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
A | 14 | 20 | 14 | 0 |
B | 10 | 16 | 24 | 8 |
C | 7 | 15 | 31 | 16 |
D | 6 | 17 | 37 | 20 |
Total | 37 | 68 | 106 | 44 |
Average | 9.3 | 17.0 | 26.5 | 11.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job A:
Flow time of Job A is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 8.
Tardiness of Job C:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job C is 16.
Tardiness of Job D:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job D is 20.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 26.5 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 11.0 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.86 jobs.
Shortest processing time:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
D | 6 | 17 | 6 | |
C | 7 | 15 | 13 | |
B | 10 | 16 | 23 | 7 |
A | 14 | 20 | 37 | 17 |
Total | 37 | 68 | 79 | 24 |
Average | 9.3 | 17.0 | 19.8 | 12.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job D and Job C:
Flow time of Job D and Job C is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 7.
Tardiness of Job A:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job A is 17.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 19.75 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 6.0 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.14 jobs.
Earliest Due Date:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
C | 7 | 15 | 7 | |
B | 10 | 16 | 17 | 1 |
D | 6 | 17 | 23 | 6 |
A | 14 | 20 | 37 | 17 |
Total | 37 | 68 | 84 | 24 |
Average | 9.3 | 17.0 | 21.0 | 8.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job C:
Flow time of Job C is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 1.
Tardiness of Job D:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job D is 6.
Tardiness of Job A:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job A is 17.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 21.00 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 6.0 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.27 jobs.
Critical ratio:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
A | 14 | 20 | 14 | 0 |
C | 7 | 15 | 21 | 6 |
D | 6 | 17 | 27 | 10 |
B | 10 | 16 | 37 | 21 |
Total | 37 | 68 | 99 | 37 |
Average | 9.3 | 17.0 | 24.8 | 9.3 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job A:
Flow time of Job A is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job C:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job C is 6.
Tardiness of Job D:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job D is 10.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 21.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 24.75 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 9.25 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.68 jobs.
c)

To determine: The method which is superior to others.
Introduction: Rules that are framed for providing the order in which the jobs need to be performed are termed as priority rules. These rules are more suitable for process-oriented facilities. The main purpose of priority rules are on-time completion of jobs, efficient utilization of services, and the maximizing the customer services.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the method which is superior to other:
Shortest Processing Time (SPT) is the method which is superior to other, as it is the method which would provide lowest value when compare to others.
Want to see more full solutions like this?
Chapter 16 Solutions
EBK OPERATIONS MANAGEMENT
- 1) View the videos Taco Bell test-drives Live Mas restaurant concept in South Bay (0.32 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=04wRc5Wg8GU , and First-ever Taco Bell Live Mas Café serving exclusive drinks in Chula Vista (1.56 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=fq6jDxJk1LM , and answer the following questions: a) What is driving Taco Bell to try a beverage-focused format? b) What type of a process strategy does their beverage-focused format represent? c) What operational issues do you think Taco Bell would face from their beverage-focused format? d) What do you think are the main advantages and disadvantages of kiosk ordering? Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions. 2) Taipei Pharmaceuticals is planning to open a new manufacturing facility as part of its expansion plans. The firm has narrowed down the search to locate its new manufacturing facility…arrow_forwardThe Clothing Shack is an online retailer of men's, women's, and children's clothing. The company has been in business for four years and makes a modest profit from its online sales. However, in an effort to compete successfully against online retailing heavyweights, the Clothing Shack's marketing director, Makaya O'Neil, has determined that the Clothing Shack's marketing information systems need improvement. Ms. O'Neil feels that the Clothing Shack should begin sending out catalogs to its customers, keep better track of its customer's buying habits, perform target marketing, and provide a more personalized shopping experience for its customers. Several months ago, Ms. O'Neil submitted a systems service request (SSR) to the Clothing Shack's steering committee. The committee unanimously approved this project. You were assigned to the project at that time and have since helped your project team successfully complete the project initiation and planning phase. Your team is now ready to move…arrow_forwardb-1. Activity ES EF LS LF Slack 1 2 3 4 5 6 7 8 9 b-2. Identify the critical activities, and determine the duration of the project. The critical activities are .arrow_forward
- The forecast for each week of a four-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are follows: Week Customer Order 1 52 35 20 12 Use a production lot size of 75 units and no beginning Inventory. Determine the available-to-promise (ATP) quantities for each period. Note: Leave no cells blank - be certain to enter "0" wherever required. Period ATP 1 2 3arrow_forwardPrepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 2 36 28 4 1 Use a production lot size of 85 units and no beginning inventory. Note: In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required. June July 1 2 3 4 5 8 7 8 Forecast 60 60 60 60 60 60 60 60 Customer Orders 38 28 4 1 0 0 0 0 Projected On-Hand Inventory MPS ATParrow_forwardSales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 Forecast 21.0 21 21 24 31 28 29 32 28 26.50 b) For the forecast developed using exponential smoothing (a = 0.50 and initial forecast 21.0), the MAD = |||||sales (round your response to two decimal places).arrow_forward
- Sales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week Demand 1 2 3 4 5 6 7 8 9 10 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 Demand 21 21 27 38 Forecast 21.0 ☐ G ☐ ☐ 6 7 25 30 35 ∞ ☐ 8 9 10 24 25 30arrow_forwardEach machine costs $3 Million. Building the room with all its attendant safety protection and other ancillary costs increases the spending by an additional $2.0 million dollars per MRI suite. Each machine can perform 2000 scans per year. Each reading of an MRI scan by a radiologist, along with other per-scan-related costs, is $500 per scan. The machine will last five years. Don’t worry about discount rates for this problem Graph the total costs over 5 years as a function of sales for 0-3000 patients annually. Hint: you may need to add a second MRI at some point. Suppose that you want to make a profit of $500 per scan at a target volume of 1000 patients per year, and you purchase only one machine. Superimpose the total revenue curve on top of the total cost curve in (1).arrow_forwardI need the answer to requirement C.arrow_forward
- Imagine you are Susan Kim and are faced with a difficult choice to either follow the orders she was given, or refusing to do so. Using each lens determine what the ethical response would be. Suppot your answer with materials from readings and lectures. For example, using Universalism what would the ethical response be? Do the same for all four lenses.arrow_forwardAnswer all these questions, selecting any company of your choice. Choose a specific type of food company. Select a specific product. Develop all the inputs that are part of the process. Develop the transformation process in a graphic (diagram, etc.). Develop all the outputs or finished products that are part of the process. Describe all the processes involved in one line of production in any manufacturing facility. Also describing how good management is the center of any part of a production company.arrow_forwardUsing exponential smoothing with α =0.2, forecast the demand for The initial forecast for January is 2000 tons. Calculate the capacity utilization for June, July and Discuss the implications of underutilized or over utilized capacity for Green Harvestarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
