Concept explainers
Whether the given culvert will operate under inlet or outlet control for the given conditions.

Answer to Problem 20P
The given culvert is acceptable and inlet control governs.
Explanation of Solution
Given:
The diameter of concrete circular box is
The angle of inclination of flared walls is
The
The design headwater elevation is
Elevation of stream bed at face of invert is
Tail water depth is
Approximate length of culvert is
Slope of stream is
The value of
The value of
Formula used:
The flow rate per width is given by,
Here,
The required headwater is given by,
Here,
The design headwater depth is given by,
Here,
The formula for fall is given by,
The culvert invert elevation is given by,
The depth from outlet invert to hydraulic line is given by,
Here,
The outlet water elevation is given by,
Here,
The required outlet headwater elevation is given by,
Here,
Calculation:
The flow rate per width is calculated as,
Substitute
Consider Figure 16.17, "Headwater Depth for Concrete Pipe Culverts with Inlet Control" from the book "Traffic and Highway Engineering", for a depth of
The required headwater is calculated as,
Substitute
The design headwater depth is calculated as,
Substitute
The fall is calculated as,
Substitute
The culvert invert elevation is calculated as,
Substitute
The depth from outlet invert to hydraulic line is calculated as,
Substitute
The tail water is not greater so take
The outlet water elevation is calculated as,
Substitute
For circular culvert with
The required outlet headwater elevation is calculated as,
Substitute
The required outlet headwater elevation is less than the design headwater design so the given culvert is acceptable and inlet control governs.
Conclusion:
Therefore, the given culvert is acceptable and the inlet control governs.
Want to see more full solutions like this?
Chapter 16 Solutions
MindTap Engineering for Garber/Hoel's Traffic and Highway Engineering, 5th Edition, [Instant Access], 1 term (6 months)
- 6. A lake with no outlet is fed by a river with a constant flow of 1200 ft3/s. Water evaporates from the surface at a constant rate of 13 ft3/s per square mile of surface area. The surface area varies with the depth h (in feet) as A (square miles) = 4.5 + 5.5h. What is the equilibrium depth of the lake? Below what river discharge (volume flow rate) will the lake dry up?arrow_forwardProblem 5 (A, B, C and D are fixed). Find the reactions at A and D 8 k B 15 ft A -20 ft C 10 ft Darrow_forwardProblem 4 (A, B, E, D and F are all pin connected and C is fixed) Find the reactions at A, D and F 8 m B 6m E 12 kN D F 4 marrow_forward
- Problem 1 (A, C and D are pins) Find the reactions and A, C and D. D 6 m B 12 kN/m 8 m A C 6 marrow_forwardUniform Grade of Pipe Station of Point A is 9+50.00. Elevation Point A = 250.75.Station of Point B is 13+75.00. Elevation Point B = 244.10 1) Calculate flowline of pipe elevations at every 50 ft. interval (Half Station). 2) Tabulate station and elevation for each station like shown on example 3) Draw Sketcharrow_forward40m 150N B 40marrow_forward
- Note: Please accurately answer it!. I'll give it a thumbs up or down based on the answer quality and precision. Question: What is the group name of Sample B in problem 3 from the image?. By also using the ASTM flow chart!. This unit is soil mechanics btwarrow_forwardPick the rural location of a project site in Victoria, and its catchment area-not bigger than 25 sqkm, and given the below information, determine the rainfall intensity for ARI = 5, 50, 100 year storm event. Show all the details of the procedure. Each student must propose different length of streams and elevations. Use fig below as a sample only. Pt. E-ht. 95.0 200m 600m PLD-M. 91.0 300m Pt. C-93.0 300m PL.B-ht. 92.0 PL.F-ht. 96.0 500m Pt. A-M. 91.00 To be deemed satisfactory the solution must include: Q.F1.1.Choice of catchment location Q.F1.2. A sketch displaying length of stream and elevation Q.F1.3. Catchment's IFD obtained from the Buro of Metheorology for specified ARI Q.F1.4.Calculation of the time of concentration-this must include a detailed determination of the equivalent slope. Q.F1.5.Use must be made of the Bransby-Williams method for the determination of the equivalent slope. Q.F1.6.The graphical display of the estimation of intensities for ARI 5,50, 100 must be shown.arrow_forwardQUANTITY SURVEYINGarrow_forward
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage LearningFundamentals of Geotechnical Engineering (MindTap...Civil EngineeringISBN:9781305635180Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Geotechnical Engineering (MindTap C...Civil EngineeringISBN:9781305970939Author:Braja M. Das, Khaled SobhanPublisher:Cengage Learning
- Principles of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781305081550Author:Braja M. DasPublisher:Cengage LearningSolid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,