Construct A and L matrices.
A=
L=
Given that
Baseline
Explanation:
Writing observation equation for X coordinate for bonnieto ray:
WHERE
XB= X coordinate of the station bonnie =
ΔXB-R= X component in baseline vector =
ʋ1= residual
Writing observation equation for Y coordinate for Bonnie to Ray:
Writing observation equation for Z coordinate for Bonnie to Ray:
Writing observation equation for X coordinate for tom to herb:
Writing observation equation for y coordinate for tom to herb:
Writing observation equation for Z coordinate for tom to herb
Writing observation equations for X coordinate for bonnie to herb:
Writing observation equation for Y coordinates for bonnie to herb:
YB-H= YB+ ΔYB-H+ʋ8WHERE
YB= Y coordinate of the station Tom = -4,655,872.977m
ΔYB-H= Y component in baseline vector = 5,106.722m
ʋ8= residual
XA-T=4,655,872.977+5,106.722+ʋ8 = -4,650,766.255+ ʋ8
Writing observation equation for Z coordinates for bonnie to herb:
Writing observation equation for X coordinate for tom to ray:
Writing observation equation for Y coordinate for tom to ray:
Writing observation equation for Z coordinate for tom to ray:
A =
A=
Construct L matrix:
L =
Conclusion:
A=
L=
Want to see the full answer?
Check out a sample textbook solutionChapter 16 Solutions
Elementary Surveying, Global Edition
- H.W. A soil profile is shown in figure below. Calculate the values of ot, o', u at points A, B, C and D. draw the variation of ot, o', u with the depth. 3m Water table 2.5m + 2m D Rock Dry sand, e=0.52, Gs=2.65 Sand, e=0.52, Gs=2.65 Clay, w=45%, e = 1.22arrow_forwardNo chatgpt pls will upvotearrow_forwardCalculate steel quantity in kg for CF3, CF4,CF5, CF6 from foundation layout and other footing? The depth of CF3, CF4,CF5 and CF6 are 50, 55,55 , 60 cm in order. Both long and short bar for CF3, CF4,CF5 and CF6 are Y14@15c/c T&B, Y14@15c/c T&B, Y14@15c/c T&B, Y14@12c/c T&B in order. 2. Calculate quantity of flexible sheet from foundation layout?arrow_forward
- (A): As shown in the rig. A hydraulic jump was occurred in a rectangular channel,the velocity of flow before and after the jump equal to 8 m/s and 2 m/s respectively. Find: The energy dissipation for the jump (AE) and what is the name of this jump. V1-8 m/s -V2-2 m/sarrow_forwardA cylinder of fluid has dimensions of 0.2 ft in diameter by 0.45 ft high. If the weight of thefluid is 0.55 lb , determine the specific gravity and density of fluid.arrow_forwardA cylinder of fluid has dimensions of 0.2 ft in diameter by 0.45 ft high. If the weight of thefluid is 0.55 lb , determine the specific gravity and density of fluid.arrow_forward
- A cylinder of fluid has dimensions of 0.2 ft in diameter by 0.45 ft high. If the weight of thefluid is 0.55 lb , determine the specific gravity and density of fluid.arrow_forwardDraw the shear and bending moment diagrams and find the immediate deflection for a simply supported beam of length 20 ft. with the same live load at ½ span and cross-section as the previous problem. Assume a reasonable Modulus of Elasticity and concrete self-weight. Hint: You may look online for typical concrete self-weights and compressive strengths. You may also use the ACI 318 Code equation for the Modulus of Elasticity shown below, and the supplied Design Aids.arrow_forwardProblem 4. A major transmission pathway of the novel coronavirus disease 2019 (COVID- 19) is through droplets and aerosols produced by violent respiratory events such as sneezes and coughs (Fig. 1). For the purpose of providing public health guidelines, we would like to estimate the amount of time it takes for these droplets to settle from air to the ground. The relevant parameters are the settling time (ts), the initial height of the droplets (H), gravitational acceleration (g), density of the droplets (pa), radius of the droplets (R), as well as dynamic viscosity of the ambient air (Pair). Use dimensional analysis and the Buckingham theorem to answer the following questions: 1. Find the independent dimensionless parameters using the table method. Then, express the settling time as a function of the other relevant parameters. Your solution should match the physical intuition that the settling time scales linearly with the initial height. 2. How would the settling change if the…arrow_forward
- Question 4 An engineer is assigned to design a 25-stories office building which has a building height of 75 m. Reinforced concrete shear wall system as shown in Figure Q1(a) is adopted to resist the lateral loads. The shear wall is of thickness t = 350 mm and length L = 8.5 m. Use the following data: Young's modulus of concrete E = 28 kN/mm² and the lateral load intensity w = 1.20 kN/m². Assuming the frontal width of the building façade is 15 m is facing the wind force which in turn transmitting the wind force to the shear wall system, estimate the total value of sway A at the roof level. Question 5 For the Shear Wall in Question 4, if the total ultimate gravity load of the building acted on shear wall is 6000 KN, using a partial factor of 1.2 for the wind load, calculate the stress on the extreme right corner of the shear wall at first storey level. (A) 9.46 mm (B) 189.26 mm (C) 14.20 mm (D) 141.95 mm STOREY FLOOR LEV Shear wall Figure Q1(a) (A) 3.228 N/sq mm (B) 14.029 N/sq mm 75 m…arrow_forwardQuestion 4 An engineer is assigned to design a 25-stories office building which has a building height of 75 m. Reinforced concrete shear wall system as shown in Figure Q1(a) is adopted to resist the lateral loads. The shear wall is of thickness t = 350 mm and length L = 8.5 m. Use the following data: Young's modulus of concrete E = 28 kN/mm² and the lateral load intensity w = 1.20 kN/m². Assuming the frontal width of the building façade is 15 m is facing the wind force which in turn transmitting the wind force to the shear wall system, estimate the total value of sway A at the roof level. Question 6 If the similar building in Question 4 is designed using rigid frame method is to be designed to ensure the sway is within the allowable limit. If the building width is B, and with the same building height H=75m. Using a rough estimation method, calculate the maximum allowable deflection A at the roof level. (A) 9.46 mm (B) 189.26 mm (C) 14.20 mm 町 141.95 mm 1ST STOREY FLOOR LEV. Shear wall…arrow_forwardWhat are the biggest challenges estimators' face during the quantity takeoff and pricing phases?arrow_forward
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning