OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 15, Problem 7P

a)

Summary Introduction

To decide: What actions to be taken immediately, in case 1,000 finished lamps are required in week 5 and 1,500 finished lamps are required in week 6, given the “parts explosion”, the inventory on hand of finished lamps and parts and lead times as shown below.

b)

Summary Introduction

To calculate the total assembly time required, given that it takes 15 minutes to assemble the parts into the frame and 5 minutes to assemble the shade and frame into a finished lamp.

c)

Summary Introduction

To find out the changes in the material plan, if the lead time of assembly of lamps is extended from one week to two weeks.

Blurred answer
Students have asked these similar questions
Table B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B).   Table A   Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7   Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B   Item: Ball bearings   Quantity on hand: 400 Order policy: 500 units Lead time: 1 week   Week   1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory                     MPS quantity 500                   MPS start                     Available to promise (ATP)
Product Z is made from three units of A, two of B, and four of C. A, in turn, is made of one unit of C and five of D. A customer order was received for 200 units of Z in Week 8. (Hint: You will need to use "low-level coding", i.e., pull each item to the lowest level it appears on the BOM.) Item Lot Size On Hand Lead Time Z LFL 30 3 A LFL 40 1 B LFL 100 4 C 1000 50 3 D 500 2000 3 a. Show the Bill of Materials b. Develop MRP schedules showing gross/net requirements and planned order releases/receipts for each item.
Heather​ Adams, production manager for a Colorado exercise equipment​ manufacturer, needs to schedule an order for 50​ UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume​ lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F ​(enter your responses as whole​ numbers).
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY