Numerical Methods for Engineers
Numerical Methods for Engineers
7th Edition
ISBN: 9780073397924
Author: Steven C. Chapra Dr., Raymond P. Canale
Publisher: McGraw-Hill Education
bartleby

Videos

Question
Book Icon
Chapter 15, Problem 2P

(a)

To determine

The linear programming problem to maximize the profit if the factors are given as below,

Resource Regular Premium Supreme Resource Availability
Raw gas 7 m3/tonne 11 m3/tonne 15 m3/tonne 154 m3/week
Production time 10 hr/tonne 8 hr/tonne 12 hr/tonne 80 m3/week
Storage 9 tonnes 6 tonnes 5 tonnes
Profit 150/tonne 175/tonne 250/tonne

(a)

Expert Solution
Check Mark

Answer to Problem 2P

Solution:

The linear programming problem to maximize the profit is,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

Explanation of Solution

Given Information:

The factors are given as below,

Resource Regular Premium Supreme Resource Availability
Raw gas 7 m3/tonne 11 m3/tonne 15 m3/tonne 154 m3/week
Production time 10 hr/tonne 8 hr/tonne 12 hr/tonne 80 m3/week
Storage 9 tonnes 6 tonnes 5 tonnes
Profit 150/tonne 175/tonne 250/tonne

Assume x be the amount of regular resource, y be the amount of premium resource and z be the amount of supreme resource

Therefore, total amount of raw gas is 7x+11y+15z.

But the resource availability is 154 m3/week. Therefore, the material constrain is,

7x+11y+15z154

Now, the total production time from the provided table is 10x+8y+12z.

But the resource production time is 80 m3/week. Therefore, the time constrain is,

10x+8y+12z80

Now, regular resource can store up to 9 tones. Therefore,

x9

And, premium resource can store up to 6 tones. Therefore,

y6

Also, supreme resource can store up to 5 tones. Therefore,

z5

Since, the amount of resource cannot be negative. Therefore, the positivity constraints are,

x,y,z0 

Now, the company makes profits of 150/tonne on regular resources, 175/tonne on premium resources and 250/tonne on supreme resources. Therefore, maximum profit is,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

(b)

To determine

The solution of the linear programming problem,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

By the Simplex method.

(b)

Expert Solution
Check Mark

Answer to Problem 2P

Solution:

The values of variables are x=0, y=6,z=2.6667. The maximum P=1716.7.

Explanation of Solution

Given Information:

The linear programming problem,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

Consider the provided linear programming problem,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

First convert the above problem to standard form by adding slack variables.

As the constraints are subjected to less than condition, non- negative slack variables are added to reach equality.

Let the slack variables be S10, S20,S30,S40 and S50.

Thus, the linear programming model would be:

Maximize P=150x+175y+250z+0S1+0S2+0S3+0S4+0S5

Subject to the constraints:

7x+11y+15z+S1=15410x+8y+12z+S2=80x+S3=9y+S4=6z+S5=5

The above linear programming models consist of three non-basic variables (x, y,z) and five basic variables (S1, S2, S3,S4,S5).

Now the apply the Simplex method and solve the above problem as:

Basic P x y z S1 S2 S3 S4 S5 Solution Intercept (solutionz)
P 1 -150 -175 -250 0 0 0 0 0 0
S1 0 7 11 15 1 0 0 0 0 154 10.2667
S2 0 10 8 12 0 1 0 0 0 80 6.66667
S3 0 1 0 0 0 0 1 0 0 9
S4 0 0 1 0 0 0 0 1 0 6
S5 0 0 0 1 0 0 0 0 1 5 5

The negative minimum, P is 250 and it corresponds to variable z. So, the entering variable is z.

The minimum ratio is 5 and it corresponds to basis variable S5. So, the leaving variable is S5.

Therefore, the pivot element is 1.

Basic P x y z S1 S2 S3 S4 S5 Solution Intercept (solutiony)
P 1 -150 -175 0 0 0 0 0 250 1250
S1 0 7 11 0 1 0 0 0 -15 79 7.18182
S2 0 10 8 0 0 1 0 0 -12 20 2.5
S3 0 1 0 0 0 0 1 0 0 9
S4 0 0 1 0 0 0 0 1 0 6 6
z 0 0 0 1 0 0 0 0 1 5

The negative minimum, P is 175 and it corresponds to variable y. So, the entering variable is y.

The minimum ratio is 2.5 and it corresponds to basis variable S2. So, the leaving variable is S2.

Therefore, the pivot element is 8.

Basic P x y z S1 S2 S3 S4 S5 Solution Intercept (solutionS5)
P 1 68.75 0 0 0 21.88 0 0 -12.5 1687.5
S1 0 -6.75 0 0 1 -1.375 0 0 1.5 51.5 34.3333
y 0 1.25 1 0 0 0.125 0 0 -1.5 2.5 -1.66667
S3 0 1 0 0 0 0 1 0 0 9
S4 0 -1.25 0 0 0 -0.125 0 1 1.5 3.5 2.33333
z 0 0 0 1 0 0 0 0 1 5 5

The negative minimum, P is 12.5 and it corresponds to variable S5. So, the entering variable is S5.

The minimum positive ratio is 2.33333 and it corresponds to basis variable S4. So, the leaving variable is S4.

Therefore, the pivot element is 1.5.

Basic P x y z S1 S2 S3 S4 S5 Solution
P 1 58.3333 0 0 0 20.83 0 8.33 0 1716.7
S1 0 -5.5 0 0 1 -1.25 0 -1 0 48
y 0 0 1 0 0 0 0 1 0 6
S3 0 1 0 0 0 0 1 0 0 9
S5 0 -0.8333 0 0 0 -0.083 0 0.67 1 2.3333
z 0 0.83333 0 1 0 0.083 0 -0.67 0 2.6667

Since P0, optimal solution is obtained.

Hence, the values of variables are x=0, y=6,z=2.6667. The maximum P=1716.7.

(c)

To determine

The solution of the linear programming problem,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

By the use of software.

(c)

Expert Solution
Check Mark

Answer to Problem 2P

Solution:

The maximum profit is 1716.7 with x=0, y=6,z=2.67.

Explanation of Solution

Given Information:

The linear programming problem,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

Use excel solver as below, to solve the linear programming,

Step 1: Enter the coefficients of x, y and z for each constraint as below,

Numerical Methods for Engineers, Chapter 15, Problem 2P , additional homework tip  1

Step 2: Use formulas in column E to find total are as below,

Numerical Methods for Engineers, Chapter 15, Problem 2P , additional homework tip  2

Step 3: click on Solver button under the Data Ribbon. Set the values in the Solver dialogue box as below:

Numerical Methods for Engineers, Chapter 15, Problem 2P , additional homework tip  3

Step 4: Press the solve button.

The result obtained as,

Numerical Methods for Engineers, Chapter 15, Problem 2P , additional homework tip  4

Hence, the maximum value profit is 1716.7 with x=0, y=6,z=2.67.

(d)

To determine

The constraint among increasing raw material, storage or production time that gives the maximum profit.

(d)

Expert Solution
Check Mark

Answer to Problem 2P

Solution:

The increasing production time will give the maximum profit.

Explanation of Solution

Given Information:

The linear programming problem,

Maximize P=150x+175y+250z

Subject to the constraints:

7x+11y+15z15410x+8y+12z80x9y6z5x,y,z0

To obtain the maximum profit, the shadow price should be high.

Use excel as below to find the shadow price by generating the sensitivity report,

Follow same steps up to the step 4 of part (d) then select the report as sensitivity as below,

Numerical Methods for Engineers, Chapter 15, Problem 2P , additional homework tip  5

The sensitivity report for the linear programming problem is as follows,

Numerical Methods for Engineers, Chapter 15, Problem 2P , additional homework tip  6

From the above sensitivity report, it is observed that the production time has a high shadow price.

Hence, the production time will give the maximum profit.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Advanced Math
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, advanced-math and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Advanced Engineering Mathematics
Advanced Math
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Wiley, John & Sons, Incorporated
Text book image
Numerical Methods for Engineers
Advanced Math
ISBN:9780073397924
Author:Steven C. Chapra Dr., Raymond P. Canale
Publisher:McGraw-Hill Education
Text book image
Introductory Mathematics for Engineering Applicat...
Advanced Math
ISBN:9781118141809
Author:Nathan Klingbeil
Publisher:WILEY
Text book image
Mathematics For Machine Technology
Advanced Math
ISBN:9781337798310
Author:Peterson, John.
Publisher:Cengage Learning,
Text book image
Basic Technical Mathematics
Advanced Math
ISBN:9780134437705
Author:Washington
Publisher:PEARSON
Text book image
Topology
Advanced Math
ISBN:9780134689517
Author:Munkres, James R.
Publisher:Pearson,
Solve ANY Optimization Problem in 5 Steps w/ Examples. What are they and How do you solve them?; Author: Ace Tutors;https://www.youtube.com/watch?v=BfOSKc_sncg;License: Standard YouTube License, CC-BY
Types of solution in LPP|Basic|Multiple solution|Unbounded|Infeasible|GTU|Special case of LP problem; Author: Mechanical Engineering Management;https://www.youtube.com/watch?v=F-D2WICq8Sk;License: Standard YouTube License, CC-BY
Optimization Problems in Calculus; Author: Professor Dave Explains;https://www.youtube.com/watch?v=q1U6AmIa_uQ;License: Standard YouTube License, CC-BY
Introduction to Optimization; Author: Math with Dr. Claire;https://www.youtube.com/watch?v=YLzgYm2tN8E;License: Standard YouTube License, CC-BY