Question
Book Icon
Chapter 15, Problem 29P
To determine

(a)

The projects that should be approved.

Expert Solution
Check Mark

Answer to Problem 29P

The projects B, C, D, E, H, and J should be approved.

Explanation of Solution

Given:

Salvage Value is 0.

Duration is 5 years.

Calculation:

Write the expression to calculate the present worth.

PW=P+A(1+i)n1(1+i)n×i ...... (I)

Substitute 14% for i and 5 for n in Equation (I)

PW=P+A(1+0.14)51(1+0.14)5×0.14=P+A(3.433) ...... (II)

Find the table to calculate the present worth.

Project PV(thousand)(COST) Uniform annual benefits Rate of return PW PW/COST
A $10 $2.98 15% $0.01 0.001
B $15 $5.58 25% $0.006 0.0004
C $5 $1.53 16% $0.0096 0.00192
D $20 $5.55 12% $.0065 0.000325
E $15 $4.37 14% $0.0026 0.000173
F $30 $9.81 19% $0.0046 0.000153
G $25 $7.81 17% $0.013 $0.00052
H $10 $3.49 22% $5.86 $0.586
I $5 $1.67 20% $0.0056 0.00112
J $10 $3.20 18% $0.00694 $0.000694

Here, the present worth has been calculated using Equation (I).

Conclusion:

Therefore, the projects B, C, D, E, H, and J should be approved.

To determine

(b)

The ranking order of all the acceptable projects.

Expert Solution
Check Mark

Answer to Problem 29P

The ranking has been shown below.

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10

Explanation of Solution

Calculation:

Rank the project according to the PW/COST

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10

Conclusion:

Rank the project according to the PW/COST

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10
To determine

(c)

The projects to be approve if only $70000 is available.

Expert Solution
Check Mark

Answer to Problem 29P

The project to be approve if only $70000 available are H, C, J, B, D, and A.

Explanation of Solution

Calculation:

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10

If the project budget is $70000 then the project with best return should be selected.

The project to be approve if only $70000 available are H, C, J, B, D, and A.

Sum=$10000+$5000+$10000+$15000+$20000+$10000=$70000

Hence, the chosen project is correct.

Conclusion:

Therefore, the project to be approve if only $70000 available are H, C, J, B, D, and A.

To determine

(d)

If the result will be the same if the projects are ranked on IRR and calculate the opportunity cost of capital.

Expert Solution
Check Mark

Answer to Problem 29P

No, there will be change in the rank of the project if they are ranked on IRR.

The opportunity cost of capital is 20%.

Explanation of Solution

Make the table to calculate the present worth.

Project PV(thousand)(COST) Uniform annual benefits Rate of return PW PW/COST
A $10 $2.98 15% $0.01 0.001
B $15 $5.58 25% $0.006 0.0004
C $5 $1.53 16% $0.0096 0.00192
D $20 $5.55 12% $.0065 0.000325
E $15 $4.37 14% $0.0026 0.000173
F $30 $9.81 19% $0.0046 0.000153
G $25 $7.81 17% $0.013 $0.00052
H $10 $3.49 22% $5.86 $0.586
I $5 $1.67 20% $0.0056 0.00112
J $10 $3.20 18% $0.00694 $0.000694

Here, the present worth has been calculated using Equation (I).

The project with highest PW is project H and the opportunity cost will be equal to its rate of return that is 22%.

Conclusion: No, there will be change in the rank of the project if they are ranked on IRR.

The opportunity cost of capital is 20%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
It is possible to use transformational leadership strategies to reach unethical objectives.  Traditional leadership theories and morals standards are not adequate to help employees solve complex organizational issues. For the statement above, argue in position for both in favor or opposed to the statements.
Discuss the preferred deterrent method employed by the Zambian government to combat tax evasion, monetary fines. As noted in the reading the potential penalty for corporate tax evasion is a fine of 52.5% of the amount evaded plus interest assessed at 5% annually along with a possibility of jail time. In general, monetary fines as a deterrent are preferred to blacklisting of company directors, revoking business operation licenses, or calling for prison sentences. Do you agree with this preference? Should companies that are guilty of tax evasion face something more severe than a monetary fine? Something less severe? Should the fine and interest amount be set at a different rate? If so at why? Provide support and rationale for your responses.
answer
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education