A company makes two types of products, A and B. These products are produced during a 40-hr work week and then shipped out at the end of the week. They require 20 and 5 kg of raw material per kg of product, respectively, and the company has access to 9500 kg of raw material per week. Only one product can be created at a time with production times for each of 0.04 and 0.12 hr, respectively. The plant can only store 550 kg of total product per week. Finally, the company makes profits of $45 and $20 on each unit of A and B, respectively. Each unit of product is equivalent to a kg.
(a) Set up the linear programming problem to maximize profit.
(b) Solve the linear programming problem graphically.
(c) Solve the linear programming problem with the simplex method.
(d) Solve the problem with a software package.
(e) Evaluate which of the following options will raise profits the most: increasing raw material, storage, or production time.
(a)
The linear programming problem to maximize the profit if the company makes profits of $45 on each unit of A and $20 on each unit of B.
Answer to Problem 1P
Solution:
The linear programming problem to maximize the profit is,
Subject to the constraints:
Explanation of Solution
Given Information:
Product A and B are produced during a 40-hr of work week.
Company has access to 9500 kg of raw material per week.
Company required 20 kg of raw material per kg of product A and 5 kg of raw material per kg of product B.
One product of A can be created in 0.04 hour and one product of B can be created in 0.12 hour.
Plant can store 550 kg of total product per week.
And, the company makes profits of $45 on each unit of A and $20 on each unit of B.
Assume
Therefore, total number of products is
But plant can store 550 kg of total product per week. Therefore, the storage constrain is,
Company required 20 kg of raw material per kg of product A and 5 kg of raw material per kg of product B. Therefore, total raw material per week is,
But the company has access to 9500 kg of raw material per week. Therefore, raw material constraint is,
One product of A can be created in 0.04 hour and one product of B can be created in 0.12 hour. Therefore, the total production time is,
Since, product A and B are produced during a 40-hr of work week. Therefore, the production time constraint is,
Since, the amount of product cannot be negative. Therefore, the positivity constraint is,
Now, the company makes profits of $45 on each unit of A and $20 on each unit of B. Therefore, maximum profit is,
Subject to the constraints:
(b)
To calculate: The solution of the linear programming problem,
Subject to the constraints:
By the graphical method.
Answer to Problem 1P
Solution:
The maximum value of P is approximately
Explanation of Solution
Given Information:
The linear programming problem,
Subject to the constraints:
Formula used:
The equation of a straight line is,
Where, m is the slope and C is the intercept of y.
Calculation:
Consider the linear programming problem,
Subject to the constraints:
Reformulate the constraints to straight lines by replacing inequality by equal sign and solving for
The above equations are the equation of straight lines and represent the constraints.
The value of P in the objective function
Plot all the straight lines.
The graph obtained is,
Hence, the maximum value of P is approximately
(c)
The solution of the linear programming problem,
Subject to the constraints:
By the Simplex method.
Answer to Problem 1P
Solution:
The values of variables are
Explanation of Solution
Given Information:
The linear programming problem,
Subject to the constraints:
Consider the provided linear programming problem,
Subject to the constraints:
First convert the above problem to standard form by adding slack variables.
As the constraints are subjected to less than condition, non- negative slack variables are added to reach equality.
Let the slack variables be
Thus, the linear programming model would be:
Subject to the constraints:
The above linear programming models consist of three non-basic variables
Now the apply the Simplex method and solve the above problem as:
Basic | Solution | Intercept | ||||||
1 | -45 | -20 | 0 | 0 | 0 | 0 | ||
0 | 20 | 5 | 1 | 0 | 0 | 9500 | 475 | |
0 | 0.04 | 0.12 | 0 | 1 | 0 | 40 | 1000 | |
0 | 1 | 1 | 0 | 0 | 1 | 550 | 550 |
The negative minimum, P is
The minimum ratio is 475 and it corresponds to basis variable S 1. So, the leaving variable is S 1.
Therefore, the pivot element is 20.
Basic | Solution | Intercept | ||||||
1 | 0 | -8.75 | 2.25 | 0 | 0 | 21375 | ||
0 | 1 | 0.25 | 0.05 | 0 | 0 | 475 | 1900 | |
0 | 0 | 0.11 | -0.002 | 1 | 0 | 21 | 190.9090 | |
0 | 0 | 0.75 | -0.05 | 0 | 1 | 75 | 100 |
The negative minimum, P is
The minimum ratio is 100 and it corresponds to basis variable S 3. So, the leaving variable is S 3.
Therefore, the pivot element is 0.75.
Basic | Solution | Intercept | ||||||
1 | 0 | 0 | 1.6667 | 0 | 11.6667 | 22250 | ||
0 | 1 | 0 | 0.0667 | 0 | -0.3333 | 450 | 1900 | |
0 | 0 | 0 | 0.0053 | 1 | -0.1467 | 10 | 190.9090 | |
0 | 0 | 1 | -0.0667 | 0 | 1.3333 | 100 | 100 |
Since
Hence, the values of variables are
(d)
The solution of the linear programming problem,
Subject to the constraints:
By the use of software.
Answer to Problem 1P
Solution:
The maximum profitis
Explanation of Solution
Given Information:
The linear programming problem,
Subject to the constraints:
Use excel solver as below, to solve the linear programming,
Step 1: Enter the coefficients of
Step 2: Use formulas in column D to find total are as below,
Step 3: click on Solver button under the Data Ribbon. Set the values in pertinent cells of Solver dialogue box as below:
Step 4: Press the solve button.
The result obtained as,
Hence, the maximum value profitis
(e)
The constraint among increasing raw material, storage or production time that gives the maximum profit.
Answer to Problem 1P
Solution:
The storage will give the maximum profit.
Explanation of Solution
Given Information:
The linear programming problem,
Subject to the constraints:
To obtain the maximum profit, the shadow price should be high.
Use excel as below to find the shadow price by generating the sensitivity report,
Follow same steps up to the step 4 of part (d) then select the report as sensitivity as below,
The sensitivity report for the linear programming problem is as follows:
From the above sensitivity report, it is observed that the storage has a high shadow price.
Hence, the storage will give the maximum profit.
Want to see more full solutions like this?
Chapter 15 Solutions
Numerical Methods for Engineers
- What is a carrying capacity? What kind of model has a carrying capacity built into its formula? Why does this make sense?arrow_forwardIf during the following year it is predicted that each comedy skit will generate 30 thousand and each musical number 20 thousand, find the maximum income for the year. A television program director must schedule comedy skits and musical numbers for prime-time variety shows. Each comedy skit requires 2 hours of rehearsal time, costs 3000, and brings in 20,000 from the shows sponsors. Each musical number requires 1 hour of rehearsal time, costs 6000, and generates 12,000. If 250 hours are available for rehearsal and 600,000 is budgeted for comedy and music, how many segments of each type should be produced to maximize income? Find the maximum income.arrow_forwardThe half-life of radioactive iodine is 60 days. How much of a 50-mg sample will be left in 40 days?arrow_forward
- The half-life of radioactive iodine is 60 days. How much of a 50 mg sample will be left in 40 days?arrow_forwardThe half-life of magnesium-27 is 9.45 minutes. How much of a 10-mg sample will be left in 6 minutes?arrow_forwardSuppose the coal and steel industries form a closed economy. Every $1 produced by the coal industry requires $0.30 of coal and $0.70 of steel. Every $1 produced by steel requires $0.80 of coal and $0.20 of steel. Find the annual production (output) of coal and steel if the total annual production is $20 million.arrow_forward
- The half-life of a radioactive material is about 34.2 years. How much of the material is left after 20 years?arrow_forwardThe maintenance cost on a new machine is at the rate of 100t dollars per year at time t years. Compute total maintenance cost for the first four years. How many years will it take for the total maintenance cost to amount to $5,000?arrow_forwardTotal Parenteral Nutrition (TPN) is ordered for a 43 year old male patient is 6 ft 0 in tall and weighs 262 lbs.The Total Daily Energy Requirement (TDER) for this patient is 2778 kcal/day.The order calls for 25% of their calories from fat. The order calls for the use of a 30% lipid emulsion. A 30% lipid emulsion provides 3 kcal/g. What volume of the 30% lipid emulsion should be added to the TPN? Round the answer to one decimal palce.arrow_forward
- A system of two 3000 L holding tanks is set up with a pipe bringing water to the first tank, anotherpipe taking water from the first tank to the second, and a final pipe draining away from the secondtank, with each pipe moving 100 L/hr. Usually, the system holds nothing but pure water, withthe tanks kept half-full. One day (or so the story is told), an apprentice spilled a 60 kg bag of saltat the mouth of the pipe feeding into the first tank. To add further injury to the original injury,the bag itself flew from his grasp and partially clogged the pipe draining from the second tank(don’t ask how – it just did). If the pile of salt is being dissolved by the water at the rate of half of the remaining amount everyln 2/3 hours (if you don’t end up glad that this number is ugly, then you made an error) and if thedrainage pipe now only carries 50 L/hr, what is the amount of salt in the second tank at themoment it fills up (and right before the pipes burst)? As usual, assume everything mixes…arrow_forwardBrawdy Plastics, Inc., produces plastic seat belt retainers for General Motors at the Brawdy Plastics plant in Buffalo, New York. After final assembly and painting, the parts are placed on a comveyor belt that moves the parts past a final inspection station. How fast the parts move past the final inspection station depends upon the line speed of the conveyor belt (feet per minute). Although faster line speeds are desirable, management is concerned that increasing the line speed too much may not provide enough time for inspectors to identify which parts are actually defective. To test this theory, Brawdy Plastics conducted an experiment in which the same batch of parts, with a known number of defective parts, was inspected using a variety of line speeds. The following data were collected. Number of Line Speed Defective Parts Found 20 22 20 21 30 19 30 17 40 16 40 17 50 14 50 10 (a) Develop a scatter diagram with the line speed as the independent variable. * 25 25 25 25 20- 20 20 20 2…arrow_forwardAs a construction engineer for a city, you are responsible for ensuring that the company that is providing gravel for a new road puts as much gravel in each truckload as they claim to. It has been estimated that it will take 500 truckloads of gravel to complete this road, so you plan to measure the volume of gravel in an SRS of 25 trucks to make sure that the company isn’t delivering less gravel per truckload than they claim. Each truckload is supposed to have 20 m3of gravel, so you will test the hypothesis H0: μ = 20 versus Ha: μ < 20. Describe what a Type I error is in this context.arrow_forward
- College Algebra (MindTap Course List)AlgebraISBN:9781305652231Author:R. David Gustafson, Jeff HughesPublisher:Cengage LearningAlgebra for College StudentsAlgebraISBN:9781285195780Author:Jerome E. Kaufmann, Karen L. SchwittersPublisher:Cengage LearningLinear Algebra: A Modern IntroductionAlgebraISBN:9781285463247Author:David PoolePublisher:Cengage Learning
- Algebra & Trigonometry with Analytic GeometryAlgebraISBN:9781133382119Author:SwokowskiPublisher:Cengage