
Concept explainers
Ozark Industries manufactures and sells three products, which are manufactured in a factory with four departments. Both labor and machine time are applied to the products as they pass through each department. The machines and labor skills required in each department are so specialized that neither machines nor labor can be switched from one department to another.
Ozark Industries’ management is planning its production schedule for the next few months. The planning is complicated, because there are labor shortages in the community and some machines will be down several months for repairs.
Management has assembled the following information regarding available machine and labor time by department and the machine hours and direct-labor hours required per unit of product. These data should be valid for the next six months.
Inventory levels are satisfactory and need not be increased or decreased during the next six months. Unit price and cost data that will be valid for the next six months are as follows:
Required:
- 1. Calculate the monthly requirement for machine hours and direct-labor hours for the production of products M07, T28, and B19 to determine whether the monthly sales demand for the three products can be met by the factory.
- 2. What monthly production schedule should Ozark Industries select in order to maximize its dollar profits? Explain how you selected this production schedule, and present a schedule of the contribution to profit that would be generated by your production schedule.
- 3. Identify the alternatives Ozark Industries might consider so it can supply its customers with all the product they demand.
1.

Calculate the monthly requirement for machine hours and direct labor hours for the production of products M07 and B19 to ascertain whether the monthly sales demand for the three products are met by the factory.
Explanation of Solution
Manufacturing overheads: Manufacturing overheads refers to the indirect factory- related cost that has occurred while manufacturing a product. Some of the examples of manufacturing overheads are indirect labor, indirect materials, factory building and indirect factory supplies.
The monthly requirement for machine hours is calculated as follows:
Department | ||||
Product | 1 | 2 | 3 | 4 |
M07 |
500 |
500 |
1,000 |
1,000 |
T28 |
400 |
400 | 0 |
800 |
B19 |
2,000 |
2,000 |
1,000 |
1,000 |
Total required | 2,900 | 2,900 | 2,000 | 2,800 |
Total available | 3,000 | 3,100 | 2,700 | 3,300 |
Excess (deficiency) | 100 | 200 | 700 | 500 |
Table (1)
Note: Monthly requirement for “machine hours” is computed by multiplying the monthly unit sale of each product with the “machine time” required for each department.
The monthly requirement for direct-labor requirements is calculated as follows:
Department | ||||
Product | 1 | 2 | 3 | 4 |
M07 |
1,000 |
1,500 |
1,500 |
500 |
T28 |
400 |
800 | 0 |
800 |
B19 |
2,000 |
2,000 |
2,000 |
1,000 |
Total required | 3,400 | 4,300 | 3,500 | 2,300 |
Total available | 3,700 | 4,500 | 2,750 | 2,600 |
Excess (deficiency) | 300 | 200 | (750) | 300 |
Table (2)
Due to the labor shortage in Department 3, the monthly sales demand cannot be met for all three products
Note: Monthly requirement for direct labor is computed by multiplying the monthly unit sale of each product with the direct labor required for each department.
2.

Identify the monthly production schedule that Industry O must select in order to maximize its dollar profits, explain the manner in which the production schedule is selected, and present a schedule of the contribution to profit that is generated by the production schedule.
Explanation of Solution
Contribution Margin: The process or theory which is used to judge the benefit given by each unit of the goods produced is called as contribution margin.
“The aim is to increase contribution margin. Fixed costs are irrelevant. Direct-labor hours (DLH) are the scarce resource in Department 3. Industry must initially produce the product that maximizes contribution margin per unit of the scarce resource (DLH). In this situation, two products, M07 and B19, need direct-labor hours in Department 3”.
Calculate the contribution margin:
M07 | T28 | B19 | |
Sales price (a) | $196 | $123 | $167 |
Variable costs | |||
Direct material | $7 | $13 | $17 |
Direct labor | $66 | $38 | $51 |
Variable overhead | $27 | $20 | $25 |
Variable selling | $3 | $2 | $4 |
Total variable costs (b) | $103 | $ 73 | $ 97 |
Contribution margin | $ 93 | $ 50 | $ 70 |
Note: Direct labor is computed by adding the direct labor of Department 1, Department 2, Department 3, and Department 4.
Table (3)
Product |
Contribution Margin (a) |
Department 3 DLH (b) |
Contribution Margin per DLH |
M07 | $93 | $3 | $31 |
B19 | $70 | $2 | $35 |
Table (4)
Prepare the resulting production schedule:
Product | Units | Resulting production schedule Comments |
M07 | 250 | Produce as much as the constraint permits |
T28 | 400 | Produce up to monthly sales demand; unaffected by Department 3. |
B19 | 1,000 | Produce as much as possible to increase contribution margin per DHL. |
Table (5)
Prepare the schedule of contribution margin by product:
Schedule of contribution margin by product | |||
Product |
Contribution Margin per Unit (a) |
Units Produced (b) |
Contribution to Profit |
M07 | $93 | 250 | $23,250 |
T28 | $50 | 400 | $20,000 |
B19 | $70 | 1,000 | $70,000 |
Total contribution margin | $113,250 |
Table (6)
3.

Identify the alternatives considered by Industry O for supplying all the products demanded by the customers.
Explanation of Solution
Industry O must consider the following aspects for supplying the additional quantities of MO7.
- Functioning on an overtime basis”.
- “Subcontracting the additional units”.
- “Obtaining labor from outside the community”.
Want to see more full solutions like this?
Chapter 14 Solutions
Managerial Accounting: Creating Value in a Dynamic Business Environment
- Zanzibar Limited entered into a lease agreement on July 1 2016 to lease somehighly customized hydraulic equipment to Kaizen Limited. The fair value of theequipment as at that date was $ 700,000. The terms of the lease agreement were: Note: the lease is cancellable but only with Zanzibar’s permission At the end of the lease term, the equipment is to be returned to Zanzibar Limited.On July 1, 2016, Zanzibar incurred $12,000 in legal fees for setting up the lease. Theannual rental payment includes $10, 000 to reimburse the lessor for maintenancefees incurred on behalf of the lessee. Requirements:a) Discuss the nature of the lease using the appropriate criteria. Justify youranswer using calculations where applicable b) Prepare the lease schedule for the Kaizen Limited c) Prepare Kaizen’s journal entries for 2016 & 2017 d) If the lease agreement could be cancelled at any time without penalty.Wouldyour answer in parts a & b change? If yes, explain how and why.arrow_forwardSuppose Chrysler Motors has 720 million shares outstanding with a share price of $68.25, and $30 billion in debt. If in three years, Chrysler has 750 million shares outstanding trading for $76 per share, how much debt will Chrysler have if it maintains a constant debt-equity ratio? Correct Answerarrow_forwardHow much is Henry Enterprises break even point?arrow_forward
- Suppose Chrysler Motors has 720 million shares outstanding with a share price of $68.25, and $30 billion in debt. If in three years, Chrysler has 750 million shares outstanding trading for $76 per share, how much debt will Chrysler have if it maintains a constant debt-equity ratio? Accounting Answerarrow_forwardGive me Answerarrow_forwardCompute the company's plantwide predetermined overhead rate for the yeararrow_forward
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,




