Principles of Foundation Engineering
9th Edition
ISBN: 9780357684832
Author: Das
Publisher: Cengage Learning US
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 14, Problem 14.4P
To determine
Find the settlement.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
12.20 A 600 mm diameter and 25 m long driven concrete pile car-
ries a column load of 1200 kN. It is estimated that the shaft
carries 900 kN and the point carries 300 kN. Determine
the settlement of the pile head using the Poulos and Davis
method with the following data:
E = 25 MN/m², Ep = 30,000 MN/m², and μ = 0.2
Please do 12,21
2.
Consider a group of 450 mm x 450 mm reinforced concrete piles were driven into
thick loose sand layer with the average unit weight and internal friction angle of 16 kN/m3
and 30°, respectively. Estimate the group pile capacity with the arrangement as shown in
Figure Q2 if the length of pile embedment is 30 m assuming ground water table is far
below the ground surface. Use 8 = 0.80 and K = 1.5Ko.
3B
3B
3B
1
3
3.5B
b
'P
9.
10
11
a
3.5B
2
4
1.5B
1.5B
1.5B
1.5B
1.5B
1.5B
Figure Q2
Chapter 14 Solutions
Principles of Foundation Engineering
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Question 3 A nine-pile group arranged in a square pattern is used as a foundation for a column in sand. Piles are 300 mm in diameter and placed at a spacing of 900 mm in each direction. What will be the settlement of pile group, if the settlement of single pile is 5 mm ?arrow_forwardExample (3): A site consist of two layers of clay. The upper layer is 8m- thick and has an undrained shear strength of 80 kN/m². The lower layer is a thick layer which has an undrained shear strength of 120 kN/m². Assume • Top 1m of pile doesn't support load. • FS 1.5 and FS₁=3 = (A) Estimate the working load of the pie with the following: D=1.5m, Ds=4.5 m, L=27m Bell length is 3m. (B)Determine the length of 600mm- diameter of driven pile to support a working load of 1200 kN.arrow_forwardSKIP IF YOU CAN;T SOLVE THE EXACT ANSWER IN THE CHOICESarrow_forward
- A group of piles as shown on the figure has a cross section of 0.30 m x 0.30 m. It has a total length of 15 m. The piles are embedded in a homogeneous saturated clay with Cu = 70 kPa. Unit weight of clay is 18.8 kN/m³ and the ground water table is located at a depth of 18 m. below the ground surface. Factor of safety = 4. Compute the allowable load- bearing capacity of the group of pile acting as individual piles. Qall Clay Cu70 kPa 70 15m 56 m- LI-2.74 m -Lz=3,96- Ans. 2816.10 kNarrow_forwardA 30 cm diameter pile is driven 10 m deep into a homogeneous consolidated clay deposit. The safe load carrying capacity (in kN) against the factor of safety of 2.5. Take unit cohesion of clay as 40 kN/m² and adhesion factor as 0.7. A 150.8 B 105.6 C 215.4 D 115.7arrow_forwardThe section of a 4 x 4 group pile in a layered saturated clay is shown in Figure P 9.29. The piles are square in cross section (356 mm x 356 mm). The center-to-center spacing (d) of the piles is 1 m. Determine the allowable load bearing capacity of the pile group. Use FS = 3 and Table 9.10.arrow_forward
- 9.27 The plan of a group pile is shown in Figure P9.27. Assume that the piles are embedded in a saturated homogeneous clay having a c = 90 kN/m². Given: diameter of piles (D) = 316 mm, center-to-center spacing of piles = 600 mm, and length of piles = 20 m. Find the allowable load-carrying capacity of the pile group. Use Table 9.10 and FS = 3. d Figure P9.27arrow_forward3. Consider a soil profile as shown in Figure Q3. Note that the ground water table is situated at 10 m below the ground surface. Assume piles settle sufficiently so that soil strengths are fully mobilized. Use L' = 15D where necessary. a) Determine the allowable load that can be supported by a 25 m long concrete bored pile with a diameter of 1200 mm.arrow_forwardPlease answer 11.24arrow_forward
- Figure 1 shows a cross-section through an excavation in a deep sand deposit. The site engineer determined that the exaction is too deep for a cantilever sheet pile to perform as an economical option and recommended to prop a smaller thickness sheet pile wall by using wooden struts that are spaced 3 m along the length of the wall. You are the office design engineer and are given the sketch below and asked to determine the following: i. 11. 111. The distribution of the lateral pressure over the wall height. The total force that the retaining wall must resist. The loads (in kN) carried by the individual upper and lower props. 1.5 m Props 1.5 m q=12 kPa ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ Sand y=17.5 kN/m² # = 34° Figure 1 ▼ Sand sat = 19.5 kN/m² # = 34° 3.0 m 7.0 marrow_forward3. A concrete pile 15.24 m long having a cross section of 406 mm × 406 mm is fully embedded in a saturated clay layer for which Ysat 19.02 kN/m³, Ø = 0, and cu=76.7 kN/m². Determine the allowable load that the pile can carry (Assuming FS-3). Use the a method to estimate the skin friction and Vesic's method for point load estimation.arrow_forwardSquare concrete piles are arranged in 5 row by 5 column formation beneath the pile cap. These piles are embedded into several layers of cohesive soil. The first layer is 3.75m deep and the second layer is 4.49m deep. The total depth of the third layer was not fully captured in the geotechnical report and is assumed to extend indefinitely. The piles are 0.60m wide. Each pile span 12.59m in length. The first layer has c = 61 kPa and α = 0.99. The second layer has c = 82 kPa and α = 0.78. The third layer has c = 81 kPa and α = 0.63. The bearing capacity factor Nc is equal to 8.What should be the spacing (m) to get a group efficiency of 111%? Consider ultimate capacities. Please answer this asap. For upvote. Thanksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
CE 414 Lecture 02: LRFD Load Combinations (2021.01.22); Author: Gregory Michaelson;https://www.youtube.com/watch?v=6npEyQ-2T5w;License: Standard Youtube License