Question
Chapter 13, Problem 13.6.5P
To determine
Concept Introduction:
Direct labor variances:
Direct labor variances refer to the difference between the standard direct labor cost and actual direct labor cost incurred. Direct labor cost variances are categorized into following categories:
- Direct labor Rate variance: this variance shows the difference of standard rate and actual rate of labor. The formula to calculate this variance is as follows:
- Direct labor efficiency variance: this variance shows the difference of standard usage and actual usage of labor. The formula to calculate this variance is as follows:
- Direct labor cost variance: this variance shows the difference of
standard cost and actual cost of labor. The formula to calculate this variance is as follows:
Or
Direct Labor cost variance = Actual Labor cost − Standard Labor Cost
To Indicate:
The Decision for the selection of type of labor payment
Expert Solution & Answer

Want to see the full answer?
Check out a sample textbook solution
Students have asked these similar questions
Given below are the account balances for Redstone
Corp:
.
Gross sales: $150,000
•
Sales returns and allowances: $6,000
•
Selling expenses: $15,000
•
Cost of goods sold: $65,000
•
Interest expense: $4,000
How much is the gross profit margin?
Techtronic Inc., a manufacturing company, has just completed an order that
Micro Solutions placed for 150 gadgets. The direct material, purchased parts, and
direct labor costs for the Micro order are as follows:
•
Cost of direct materials: $54,000
•
Cost of purchased parts: $30,000
•
Direct labor hours: 300 hours
•
•
Average direct labor pay rate: $18 per hour
Overhead costs were applied at a plant wide overhead rate of 250 percent
of direct labor dollars.
Compute the total cost of the Micro order.
BlueSky Corp has total debt of $250 million and 40 million shares
outstanding with a market price of $5.50 per share. Calculate
BlueSky's market debt-equity ratio.
A) 1.52
B) 0.88
C) 1.14
D) 2.15
Chapter 13 Solutions
CengageNOWv2, 1 term Printed Access Card for Warren's Survey of Accounting, 8th
Ch. 13 - Static budgets are often used: A.By production...Ch. 13 - The total estimated sales for the coming year is...Ch. 13 - Dixon Company expects $650,000 of credit sales in...Ch. 13 - The actual and standard direct materials costs for...Ch. 13 - Bower Company produced 4,000 units of product. The...Ch. 13 - Prob. 1CDQCh. 13 - What is the manager’s role in a responsibility...Ch. 13 - Briefly describe the type of human behavior...Ch. 13 - Give an example of budgetary slack.Ch. 13 - What behavioral problems are associated with...
Ch. 13 - Prob. 6CDQCh. 13 - Prob. 7CDQCh. 13 - Under what circumstances would a static budget be...Ch. 13 - How do computerized budgeting systems aid firms in...Ch. 13 - What is the first step in preparing a master...Ch. 13 - Why should the production requirements set forth...Ch. 13 - Why should the timing of direct materials...Ch. 13 - Prob. 13CDQCh. 13 - Prob. 14CDQCh. 13 - Prob. 15CDQCh. 13 - Prob. 16CDQCh. 13 - Prob. 17CDQCh. 13 - Prob. 18CDQCh. 13 - What is meant by reporting by the "principle of...Ch. 13 - Prob. 20CDQCh. 13 - How are standards used in budgetary performance...Ch. 13 - a. What are the two variances between the actual...Ch. 13 - Prob. 23CDQCh. 13 - Prob. 24CDQCh. 13 - Prob. 25CDQCh. 13 - Prob. 26CDQCh. 13 - Flexible budget for selling and administrative...Ch. 13 - Static budget vs. flexible budget The production...Ch. 13 - Flexible budget for Fabrication Department...Ch. 13 - Sales and production budgets Ultimate Audio...Ch. 13 - Professional fees earned budget Day & Spieth,...Ch. 13 - Professional labor cost budget Based on the data...Ch. 13 - Direct materials purchases budget Zippy's Frozen...Ch. 13 - Prob. 13.8ECh. 13 - Prob. 13.9ECh. 13 - Production and direct labor cost budgets Levi...Ch. 13 - Factory overhead cost budget Nutty Candy Company...Ch. 13 - Cost of goods sold budget The controller of Pueblo...Ch. 13 - Prob. 13.13ECh. 13 - Schedule of cash collections of accounts...Ch. 13 - Schedule of cash payments Tadpole Learning Systems...Ch. 13 - Schedule of cash payments Organic Physical Therapy...Ch. 13 - Capital expenditures budget On August 1, 20Y4. the...Ch. 13 - Standard product cost Sorrento Furniture Company...Ch. 13 - Prob. 13.19ECh. 13 - Direct materials variances The following data...Ch. 13 - Standard direct materials cost per unit from...Ch. 13 - Standard product cost, direct materials variance...Ch. 13 - Direct labor variances The following data relate...Ch. 13 - Prob. 13.24ECh. 13 - Direct materials and direct labor variances At the...Ch. 13 - Prob. 13.26ECh. 13 - Factory overhead cost variances The following data...Ch. 13 - Prob. 13.28ECh. 13 - Factory overhead variance corrections The data...Ch. 13 - Prob. 13.30ECh. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Prob. 13.2.7PCh. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Cash budget The controller of Shoe Mart Inc. asks...Ch. 13 - Cash budget The controller of Shoe Mart Inc. asks...Ch. 13 - Direct materials and direct labor variance...Ch. 13 - Direct materials and direct labor, variance...Ch. 13 - Prob. 13.6.1PCh. 13 - Prob. 13.6.2PCh. 13 - Prob. 13.6.3PCh. 13 - Prob. 13.6.4PCh. 13 - Prob. 13.6.5PCh. 13 - Standards for nonmanufacturing expenses The...Ch. 13 - Prob. 13.7PCh. 13 - Prob. 13.1.1MBACh. 13 - Prob. 13.1.2MBACh. 13 - Prob. 13.1.3MBACh. 13 - Prob. 13.1.4MBACh. 13 - Prob. 13.1.5MBACh. 13 - Prob. 13.1.6MBACh. 13 - Prob. 13.2.1MBACh. 13 - Prob. 13.2.2MBACh. 13 - Prob. 13.2.3MBACh. 13 - Prob. 13.2.4MBACh. 13 - Process yield Hendrick Motorsports sponsors cars...Ch. 13 - Prob. 13.3.1MBACh. 13 - Prob. 13.3.2MBACh. 13 - Prob. 13.3.3MBACh. 13 - Prob. 13.3.4MBACh. 13 - Prob. 13.4.1MBACh. 13 - Prob. 13.4.2MBACh. 13 - Prob. 13.4.3MBACh. 13 - Prob. 13.4.4MBACh. 13 - Prob. 13.5.1MBACh. 13 - Prob. 13.5.2MBACh. 13 - Prob. 13.5.3MBACh. 13 - Prob. 13.5.4MBACh. 13 - Utilization rate Delta Air Lines (DAL) reported...Ch. 13 - Prob. 13.6.2MBACh. 13 - Prob. 13.6.3MBACh. 13 - Prob. 13.7.1MBACh. 13 - Prob. 13.7.2MBACh. 13 - Prob. 13.7.3MBACh. 13 - Ethics and professional conduct in business The...Ch. 13 - Prob. 13.2.1CCh. 13 - Prob. 13.2.2CCh. 13 - Prob. 13.3.1CCh. 13 - Prob. 13.3.2CCh. 13 - Objectives of the master budget Domino's Pizza LLC...Ch. 13 - Prob. 13.5.1CCh. 13 - Prob. 13.5.2CCh. 13 - Prob. 13.6CCh. 13 - Prob. 13.7C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Please need answer the general accounting question not use aiarrow_forwardGroot Co. (GC) sells $1,200,000 of 6-year, 10% bonds at par plus accrued interest. The bonds are dated January 1, 2026 but due to market conditions are not issued until May 1, 2026. Interest is payable on June 30 and December 31 each year. The market rate of interest at time of issue is the same as the stated rate. Required The issuance of the bonds on May 1, 2026. Assume that GC has adopted a policy of crediting accrued interest payable for the accrued interest on the date of sale. Payment of interest on June 30, 2026. Payment of interest on December 31, 2026.arrow_forward1. Define working capital and explain its importance in financial health and liquidity management. 2. Assess how the matching concept and accrual basis affect the reporting of current assets and liabilities. 3. Using a hypothetical balance sheet (you may create one), identify at least 5 current assets and 5 current liabilities and analyze how changes in these elements affect liquidity ratios. 4. Recommend at least two strategies VinGrenDom Ltd. can implement to optimize working capital.arrow_forward
- Theron Interiors manufactures handcrafted cabinetry and uses a process costing system. During the month of October, the company started Production on 720 units and completed 590 units. The remaining 120 units were 60% complete in terms of materials and 40% complete in terms of labor and overhead. The total cost incurred during the month was $45,000 for materials and $31,200 for labor and overhead. Using the weighted-average method, what is the equivalent unit cost for materials and conversion costs (labor and overhead)?arrow_forwardGeneral Accountingarrow_forwardKamala Khan has to decide between the following two options: Take out a student loan of $70,000 and study accounting full time for the next three years. The interest on the loan is 4% per year payable annually. The principle is to be paid in full after ten years. Study part time and work part time to earn $15,000 per year for the following six years. Once Kamala graduates, she estimates that she will earn $30,000 for the first three years and $40,000 the next four years. Kamala's banker says the market interest for a ten-year horizon is 6%. Required Calculate NPV of the ten-year cash flows of the two options. For simplification assume that all cash flows happen at year-end. Based on the NPV which of the two options is better for Kamala?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning

Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub

Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,

Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning

Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License