A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production nm, at a cost of $300. Inventory holding costs will be $10 a year.
a. What runs quantity should be used to minimize total annual costs?
b. How many days does it take to produce the optimal run quantity?
c. What is the average amount of inventory?
d. If the manager wants to run another job between runs of this item, and needs a minimum of 10 days per cycle for the other work, will there be enough time?
e. Given your answer to part d, the manager wants to explore options that will allow this other job to be performed using this equipment. Name three options the manager can consider.
f. Suppose the manager decides to increase the new size the new product. How many additional units would be needed to just accommodate the other job? How much will that increase the total annual cost?
a)

To determine: The run quantity to minimize the total cost.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of run quantity to minimize the total cost:
The optimal run size is calculated by dividing the product of 2 and 200,000 and 300 with 10 and taking square root which gives the resultant value as 1095 units and 200 is divided with the difference of 200 and 80 and square root is taken which gives 1.290, both values are multiplies which gives the optimal run size as 1414 units.
Hence, the run quantity to minimize the total cost is 1,414 units.
b)

To determine: The number of days to produce optimal run quantities.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of days to produce optimal run quantities:
The number of days to produce optimal run quantity is calculated by dividing 1,414 with 200 which gives 7.07 days.
Hence, the number of days to produce optimal run quantities is 7.70 days.
c)

To determine: The average inventory.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of average inventory:
The average inventory is calculated by dividing 848.4 by 2 which yields 424.2 units.
Hence, the average inventory is 424.2 units.
d)

To explain: Whether there is adequate time for another job between the run of items.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation to check whether there is adequate time to do the job between the production batches:
The cycle time is calculated by dividing 1,414 with 80 which yields the resultant as 17.68 days.
The run time is calculated by dividing 1,414 by 200 and adding the resultant with setup time which yields 8.07 days.
Consumption time is calculated by subtracting cycle time of 17.68 with the consumption time of 8.07 which yields the resultant as 9.61 days which is not sufficient since other job requires 10 days.
Hence, there will not be adequate time for the other job.
e)

To explore: Three options for managers that will allow him to do other job.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Explanation of Solution
Given information:
Three options for managers that will allow him to do other job:
The three options for manager to explore the ways to do other jobs are,
- The setup time for other job can be shortened.
- Increase the run time of the new product which allows longer run time between runs which is there less need to run the component.
- Reducing the run time for other jobs.
f)

To determine: The addition units produced from the new product and the total annual cost.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 11P
Explanation of Solution
Given information:
Formula:
Calculation of addition units produced from the new product and the total annual cost:
The additional units produced is computed by finding the value of Qp
Solving for Qp, we get the values as,
The additional units per run = 1,467 – 1,414 = 53 units per run.
The additional unit per run is calculated by subtracting 1,467 and 1,414 which gives 53 units per run.
Increase in total cost:
Difference in total cost:
The increase in total cost is calculated by calculating the difference between $8,490.98 and $8,485.28 which is $5.70 per year.
Hence, additional units produced and increase in cost is 53 units per run and $ 5.7 per year.
Want to see more full solutions like this?
Chapter 13 Solutions
Loose Leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardThe deaths are included in the discharges; this includes deaths occurring in less than 48 hours and postoperative deaths. Rehabilitation had 362 discharges, 22 deaths, 1<48 hours, 0 Postoperative. what is the gross death rate for the rehabilitation service?arrow_forwardA copy machine is available 24 hours a day. On a typical day, the machine produces 100 jobs. Each job takes about 3 minutes on the machine, 2 minutes of which is processing time and 1 minute is setup time (logging in, defining the job). About 20 percent of the jobs need to be reworked, in which case the setup time and the processing time have to be repeated. The remainder of the time, the equipment is idle. What is the OEE of the equipment?arrow_forward
- How do you think we can keep updating Toyota's ideas as new technologies come out and what customers want keeps changing?arrow_forwardGiven how TPS has helped change things in so many fields, do you think there are parts of it that might be hard to use in areas that aren’t about making things, like in healthcare or services? If so, why do you think that might be?arrow_forwardDo you feel there is anything positive about rework?arrow_forward
- Do you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forwardHave you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forward
- Research a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forwardDo you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub