a)
To explain: The sensitivity analysis.
Introduction:
Sensitivity Analysis:
The process to evaluate the effect of change in one variable on the end result of a project is called sensitivity analysis. It reflects the change in
Scenario Analysis:
The process to evaluate different probable events and their outcomes that is end result of a project is called scenario analysis. It reflects the level of end result with multiple estimates called scenario categorized as base, best, and worst case scenario.
Simulation Analysis:
Simulation analysis is an extended version of sensitivity analysis that has improved the evaluation process as it considers detailed inputs. It can record the effect of changes in multiple input variables at once.
b.
To explain: The scenario analysis
Introduction:
Scenario analysis is the process to reflect the outcome in different probable scenarios. It changes the estimates based on the depended factors.
c.
To explain: The simulation analysis and the project on which the simulation will be applied.
Want to see the full answer?
Check out a sample textbook solutionChapter 12 Solutions
Mindtapv2.0 Finance, 1 Term (6 Months) Printed Access Card For Brigham/houston's Fundamentals Of Financial Management, 15th (mindtap Course List)
- Your boss wants you to conduct a sensitivity and scenario analysis to determine whether the following project is a winner. You are entering an established market, and you know the market size will be 1,100,000 units. You are unsure of your exact market share, the price you will be able to charge, and your variable cost per unit, but have determined a range of possible values for each (in the table below). Your initial investment cost is $150 million, and that investment will depreciate in straight-line form over the 20-year life of the project. There are no new NWC requirements, and there will be no salvage value at the end of the 20 years. The tax rate is 35%. The discount rate is 18%. a) Use the following table to conduct a full sensitivity analysis for the project. Make sure to include the NPV for the expected outcome as part of the full sensitivity analysis. Also add the best- and worst-case scenarios to the full sensitivity analysis. Show all of your work (written out, not an…arrow_forwardAssume a firm has several hundred possible investments and that it wants to analyze the risk-return trade-off for portfolios of 20 projects. How should it proceed with the evaluation? How would various choices impact the company?arrow_forwardI need solutions for questions d, e, f, g, h and i. Thanks d. Are this project’s cash flows likely to be positively or negatively correlated withreturns on Cory’s other projects and with the economy, and should this matter in youranalysis? Explain.e. Unrelated to the new product, Cory is analyzing two mutually exclusive machines thatwill upgrade its manufacturing plant. These machines are considered average-riskprojects, so management will evaluate them at the firm’s 10% WACC. Machine Xhas a life of 4 years, while Machine Y has a life of 2 years. The cost of each machineis $60,000; however, Machine X provides after-tax cash flows of $25,000 per year for4 years and Machine Y provides after-tax cash flows of $42,000 per year for 2 years. Themanufacturing plant is very successful, so the machines will be repurchased at the endof each machine’s useful life. In other words, the machines are “repeatable” projects.1. Using the replacement chain method, what is the NPV of the better machine?2.…arrow_forward
- Consider the following statement about real options: Sometimes real options can give managers the flexibility to decide to invest in a project or wait to make a more calculated decision. True or False: The preceding statement is correct. True False Which type of real option allows a project to be expanded if demand turns out to be greater than expected? Expansion option Flexibility option Abandonment option Timing option Consider the following example: King Snowplows began operations in New York City two years ago. As an independent contractor, the company does the majority of its business working for the city. The company also had offers from surrounding cities in New Jersey and Long Island, but these offers would have required the company to invest in additional snowplows—which have high up-front costs. King Snowplows decided to purchase only the snowplows necessary to handle its contract with New York City. The company…arrow_forward. Suppose that your organization wants to decide which one of the given two projects can be selected for the development, as summarized in the following table. Calculate the Expected Monetary Value (EMV) for each project and suggest which project can be selected? Probability of occurrence of risk/opportunity (Impact) Estimated Profits/Losses Project 1 40% $140000 60% -$60000 Project 2 80% $40000 20% -$8000arrow_forwardSuppose that, for an engineering project, the optimistic, most likely, and pessimistic estimates are as shown in the accompanying table. Develop a spreadsheet to determine the AW for each of the three estimate conditions. It is thought that the most critical elements are useful life and net annual cash flow. Include in your spreadsheet a table showing the AW for all combinations of the estimates for these two factors, assuming that all other factors remain at their most likely values.arrow_forward
- Man.1arrow_forwardConsider the case of another company. Kim Printing is evaluating two mutually exclusive projects. They both require a $1 million investment today and have expected NPVS of $200,000. Management conducted a full risk analysis of these two projects, and the results are shown below. Risk Measure Standard deviation of project's expected NPVS Project beta Correlation coefficient of project cash flows (relative to the firm's existing projects) Which of the following statements about these projects' risk is correct? Check all that apply. Project B has more stand-alone risk than Project A. Project A has more corporate risk than Project B. Project A $80,000 1.2 0.7 Project B has more corporate risk than Project A. Project A has more market risk than Project B. Project B $40,000 1.0 0.9arrow_forwardSpencer Enterprises is attempting to choose among a series of new investment alternatives. The potential investment alternatives, the net present value of the future stream of returns, the capital requirements, and the available capital funds over the next three years are summarized as follows: Develop and solve an integer programming model for maximizing the net present value. Assume that only one of the warehouse expansion projects can be implemented. Modify your model from part (a). Suppose that if test marketing of the new product is carried out, the advertising campaign also must be conducted. Modify your formulation from part (b) to reflect this new situation.arrow_forward
- Determine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present value table appearing above. Processing Mill Electric Shovel EE Present value of net cash flow total Less amount to be invested Net present value Which project should be favored?arrow_forwardYokam Company is considering two alternative projects. Project 1 requires an initial investment of $400,000 and has a present value of cash flows of $1,100,000. Project 2 requires an initial investment of $4 million and has a present value of cash flows of $6 million. Compute the profitability index for each project. Based on the profitability index, which project should the company prefer? Explain.arrow_forwardhow would i solve this problemarrow_forward
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub