OM (with OM Online, 1 term (6 months) Printed Access Card)
OM (with OM Online, 1 term (6 months) Printed Access Card)
6th Edition
ISBN: 9781305664791
Author: David Alan Collier, James R. Evans
Publisher: Cengage Learning
Question
Book Icon
Chapter 12, Problem 9PA

a

Summary Introduction

Interpretation:

Total annual parts and logistics cost for each supplier.

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

a

Expert Solution
Check Mark

Explanation of Solution

    Data Supplier A Supplier L
    Procurement cost/ unit, P$11.80$10.85
    Tariff cost/ unit,
    Tc
    $0.00$0.46
    Unit transportation cost,
    Tm
    $0.90$1.25
    Order cost/ order,
    Cο
    $155$195
    Holding cost per unit,
    Ch
    $1.45$1.10
    Lead time, L45100

The different cost components that are involved in this case are:

   Total procurement cost

   Total tariff cost

   Total transportation cost

   Annual ordering cost

   Annual inventory carrying cost

   Average annual pipeline Inventory cost

Compute these costs for all the three suppliers and select based on the least total cost of the supply chain.

The following formulae will be used:

Total procurement cost = D.P

Total tariff cost = D.Te

Total transportation cost = D.Tm

Annual ordering cost = (DQ).Cο

Annual carrying cost = (Q2).Ch

Annual pipeline inventory cost = (Dd).L.Ch

Where, D= annual demand, P= procurement cost per unit, Tc = tariff cost per unit, Tm = unit transportation cost, Cο = ordering cost per order, Ch = unit carrying cost per annum, Q = order size, d = number of days in a year, and L = lead time.

Note the computations done in the following Excel format.

    Total supply chain cost analysis
    Data Supplier A Supplier L
    Procurement cost/ unit, P$11.80$10.85
    Tariff cost/ unit,
    Tc
    $0.00$0.46
    Unit transportation cost,
    Tm
    $0.90$1.25
    Order cost/ order,
    Cο
    $155$195
    Holding cost per unit,
    Ch
    $1.45$1.10
    Lead time, L45100
    Order quantity50000100000
    Average number of orders/ year (D/Q)2010
    Annual demand, D1000000
    No. of days in a year, d340
    Average daily demand (D/d)2941
    Cost calculations
    Total procurement cost$11,800,000.00$10,850,000.00
    Total management oversight cost$0.00$460,000.00
    Total annual transportation cost$900,000.00$1,250,000.00
    Annual order cost$3,100$1,950
    Annual holding cost$36,250.00$55,000.00
    Average annual pipeline Inventory cost$191,911.76$323,529.41
    Total supply chain cost$12,931,261.76$12,940,479.41

The following is the formulated excel sheet calculations as shown below:

  OM (with OM Online, 1 term (6 months) Printed Access Card), Chapter 12, Problem 9PA

b

Summary Introduction

Interpretation:

Recommendation on order quantity

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

b

Expert Solution
Check Mark

Explanation of Solution

Based on the minimum total cost, the correct choice should be the Supplier A with Q = 50,000.

c

Summary Introduction

Interpretation:

Criteria for choosing supplier and quantity

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

c

Expert Solution
Check Mark

Explanation of Solution

Following are some of the criteria other than then total cost. The relevant metrics for measurement are also mentioned in the following table.

    CriteriaMetric
    QualitySigma level
    ReliabilityAverage service level
    CapacityPercentage utilization
    Delivery adherenceVariability in lead time

d

Summary Introduction

Interpretation:

Recommendation for supplier who is not awarded the brake pad order..

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

d

Expert Solution
Check Mark

Explanation of Solution

Supplier L should be given a target of reducing the procurement cost per unit by, say, 3%. Even with a 3% reduction of procurement cost per unit, it can compete with supplier A based on the total cost. This is shown below.

    Total supply chain cost analysis
    Data Supplier A Supplier L
    Procurement cost/ unit, P$11.80$10.85
    Tariff cost/ unit,
    Tc
    $0.00$0.46
    Unit transportation cost,
    Tm
    $0.90$1.25
    Order cost/ order,
    Cο
    $155$195
    Holding cost per unit,
    Ch
    $1.45$1.10
    Lead time, L45100
    Order quantity50000100000
    Average number of orders/ year (D/Q)2010
    Annual demand, D1000000
    No. of days in a year, d340
    Average daily demand (D/d)2941
    Cost calculations
    Total procurement cost$11,800,000.00$10,524,500.00
    Total management oversight cost$0.00$460,000.00
    Total annual transportation cost$900,000.00$1,250,000.00
    Annual order cost$3,100$1,950
    Annual holding cost$36,250.00$55,000.00
    Average annual pipeline Inventory cost$191,911.76$323,529.41
    Total supply chain cost$12,931,261.76$12,614,979.41

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Delivery of goods from a supplier is in transit for 10 days. If annual demand is 5200 units, what is the average amount of inventory in transit?
Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground control valve. See the table below. Annual usage is 800 valves; order cost is $7 per order; and annual inventory holding costs are $2.15 per unit. D Vendor A units at a time from Vendor C Vendor B Quantity 1-14 15-24 25-99 100-199 200-399 400+ Which vendor should be selected and what order quantity is best if Sandvig Irrigation wants to minimize total cost? Chris Sandvig Irrigation should order (enter your response as a whole number). Vendor A Price $35.00 34.75 33.55 32.35 31.15 30.75 Vendor D Vendor B Quantity 1-24 25-99 100-199 200-399 400+ Price $34.75 34.00 32.80 31.60 30.50 Vendor C Quantity 1-49 50-149 150-299 300+ Price $34.50 33.75 32.50 31.10 Vendor D Quantity 1-149 150-299 300+ Price $34.25 33.00 31.00
Please do not give solution in image format thanku
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning