Chapter 12, Problem 6QQ
Program Description Answer
The Point of Total Assumption is when the contractor is held responsible for every extra dollar of the contract cost.
Hence, the correct answer is option “D”.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Table that fulfills the function of relating each project requirement to the deliverable that satisfies it.
a.BCG Matrix
b.Project Requirements Traceability Matrix
c.Traceability Matrix
Question One (1)
You participated in an evaluation of proposals for consulting services. At the end of the Technical Evaluation which required a minimum of 70 points, you got the following results:
CONSULTANTS
KANYIHAMPA
MUSANGILA
Technical Score
75.17
76.17
Amount
USD475,000.00
USD625,000.00
The lowest evaluated financial proposal (Fm) is given the maximum financial score of 100. The formula for determining the financial score is as follows:
SF = 100 x Fm /F in which SF is the financial score, Fm is the lowest price and F is the price of the proposal under consideration. The weights given to the Technical and Financial proposals are 80 and 20 respectively.
Calculate for each consultant below (a – c):
Weighted Technical score.
Financial score
Combined weighted Technical and weighted Financial score
Indicate the best evaluated bidder and their points
Use Critical Path Method to estimate in how many weeks the project below will be submitted and find the critical path.
(Choose 2 answers weeks and critical path)
Activity
A: Prepare initial design
B: Identify new potential clients
C: Develop prospectus for tenants A
D: Prepare final design
E: Obtain planning permission
F: Obtain finance from bank
G: Select contractor
H: Construction
I: Finalize tenant contracts
dependent
time
8
D
3
D
4
6, F
В, С, Е
I, H
17
13
J: Tenants move in
Critical path : A-D-E-F-H-J
O Critical path: A-C-E-F H-J
35 weeks
29 Weeks
Critical path : A-G-E-F-H-J
34 Weeks
Chapter 12 Solutions
INFORMATION TECHNOLOGY PROJECT MANAGEME
Knowledge Booster
Similar questions
- A company specializing in custom-engineered equipment is planning to submit a proposal to the National 5. Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? ij Activity Immediate predecessor Optimistic time (weeks) a b d. h b e, d d e,f f,g h, i a a a 15 8 10 20 17 4 10 Most likely time (weeks) 24 16 10 14 26 23…arrow_forwardSYSTEM ANALYSIS AND DESIGN ( COMPUTER SCIENCE) Instruction: As a system analyst, you are required to analyze and propose a system design for your client company to help in their daily business process. Choose ONE (1) of the following system and discuss the development process in detail. Online Tuition Center - Online Babysitter - Online Cleaning Service Online Event Management - Online Emergency Management - Online Personal Shopper Question 1 a) Identify the appropriate system development method and explain why it is suitable for the system. b) List all the possible functions applicable to the system. c) Create a Gantt chart for the system analysis and design proposal. You may use the outline provided as a guideline for your Gantt Chart Outline for Gantt chart System Investigation - Introduction - System Request Form - Project Proposal - Feasibility Studies - Fact Finding Techniques Used - List of End-user Requirement System Analysis - Proposed Actors & Use cases - Proposed Use case…arrow_forwardA purpose of Commitment Scale is to to list actions that can improve Stakeholder interest. True/Falsearrow_forward
- You are charged with choosing a vendor to produce a new software that is going to benefit your company. The project has a life cycle of 15 years and MARR of 9% Part a.) Draw the cycle cash flow diagram for each vendor. Part b.) Set up the calculation to determine an overall rate of return for each Vendor. Use i* as the ROR in your calculation. Part c.) Determine the ROR for each vendor. HINT: you can use the formulas/tables and guess and check for the interest rate. Vendor N Cost, $ 258,500 23,000 61,000 Task Vendor M Cost, $ 190,000 30,000 55,000 Time Frame Time Frame Now Development Operation Now Annually Annually Annually REVENUE Annually Part d.) Decide which Vendor to choose using an incremental ROR approach.arrow_forwardQ6) Which of the following does not fall under the project risk categories? a. Schedule b. Resource c. Scope d. Qualityarrow_forwardThe projected number of defects submitted, resolved, and remaining open inthe first four weeks of a test project are given in the upper half of Table 13.18.The actual numbers of submitted and resolved defects are shown in the lowerhalf of the table. Calculate the actual number of open defects?arrow_forward
- Given the following information for a one-year IT project of Gulf Hospital System, answer the following questions. Recall that PV is the planned value, EV is the earned value, and AC is the actual cost. PV = $ 32,000 EV = $ 25,000 AC = $ 36,000 Calculate the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the given project. Justify the results.arrow_forwardProject managementarrow_forwardThe examination of alternatives is one of the major tasks of a proposal team, especially for tender proposals. However, in many cases, important alternatives are omitted or neglected by the proposal team. 1. List real cases and common situations where negligence in defining and examining important alternatives can be expected. 2. In what situations are these types of discrepancies least likely to occur?arrow_forward
- The purpose of a scope statement is to outline the deliverables of the project for the benefit of stakeholders particularly the end user. Select one: True Falsearrow_forwardUse one requirement gathering technique to help clarify your proposed PM project (described in your answer for question 1). Then explain how you have used the technique and the results you have found. Answer: Chosen Requirement Gathering Technique: Chosen Requirement Gathering Technique Scope: Procedure followed: Results: Project scope statement:arrow_forwardplease helparrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning