a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z, 70 units of A, 100 units of B, and 30 units of C. Also, there is a
b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as 50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and are expected to arrive in week 4. Lead times are two weeks for E and C. and one week for the other components. Assume lot-for-lot ordering except for D. where multiples of 40 must be used.
a)

To prepare: A material requirements plan for Component C.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item)
Explanation of Solution
Given information:
120 units of end item (Z) are required at the beginning of Week 7. It is given that 40 units of Component Z, 100 units of Component B, 70 units of Component A, and 30 units of Component C are available on hand. Scheduled receipt is 20 units of Component C in Week 4. Lead-time is given as 2 weeks for Component Z and Component B and 1 week for other components. Lot size is lot-for-lot.
In addition to the above information, the following diagram is given:
Prepare a Material Requirement Plan (MRP) for Component Z:
- Gross requirement is given as 120 units at the beginning of Week 7.
- On-hand inventory is 40 units. It remains same until Week 6, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 80 units are required at the beginning of Week 7. Hence, they need to order for 80 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks), which means on Week 5.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Prepare a Material Requirement Plan (MRP) for Component A (2):
- Component Z is the parent item of Component A (2). As the number of Component A is 2, the planned order release should be multiplied with 2 to determine the gross requirement of Component A.
- On-hand inventory is 70 units. It remains same until Week 4, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 90 units are required at the beginning of Week 5. Hence, they need to order for 90 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 weeks), which means on Week 4.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Prepare a Material Requirement Plan (MRP) for Component B (4):
- Component Z is the parent item of Component B (4). As the number of Component B is 4, the planned order release should be multiplied with 4 to determine the gross requirement of Component B.
- On-hand inventory is 100 units. It remains same until Week 4, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 220 units are required at the beginning of Week 5. Hence, they need to order for 220 units (as the lot size is lot-for-lot) on two weeks before (as the lead-time is 2 weeks), which means on Week 3.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Prepare a Material Requirement Plan (MRP) for Component C (3) and C (2):
- Component A (2) is the parent item of Component C (3) and Component B (4) is the parent item of Component C (2). As the number of Component C is 3, the planned order release of Component A should be multiplied with 3 to determine the gross requirement of Component C. The same should be followed for Component C (2) with its parent item B (4).
- On-hand inventory is 30 units. It remains same until Week 3, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 410 units are required at the beginning of Week 3. Hence, they need to order for 410 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week), which means on Week 2.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
b)

To prepare: A material requirements plan for Component D.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item)
Explanation of Solution
Given information:
95 units of end item (E) are required at the beginning of Week 7. It is given that 5 units of Component E, 50 units of Component B, 80 units of Component D, and 100 units of Component C are available on hand. Scheduled receipt is 30 units of Component C in Week 4. Lead-time is given as 2 weeks for Component E and Component C and 1 week for other components. Lot size is lot-for-lot for all the components except Component D. Lot size for Component C is multiples of 40.
In addition to the above information, the following diagram is given:
Prepare a Material Requirement Plan (MRP) for Component E:
- Gross requirement is given as 95 units at the beginning of Week 7.
- On-hand inventory is 5 units. It remains same until Week 6, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 90 units are required at the beginning of Week 7. Hence, they need to order for 90 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks), which means on Week 5.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Prepare a Material Requirement Plan (MRP) for Component B (3):
- Component E is the parent item of Component B (3). As the number of Component B is 3, the planned order release should be multiplied with 3 to determine the gross requirement of Component 3.
- On-hand inventory is 50 units. It remains same until Week 4, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 220 units are required at the beginning of Week 5. Hence, they need to order for 220 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 weeks), which means on Week 4.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Prepare a Material Requirement Plan (MRP) for Component C (2):
- Component E is the parent item of Component C (2). As the number of Component C is 2, the planned order release should be multiplied with 2 to determine the gross requirement of Component C.
- On-hand inventory is 100 units. It remains same until Week 3, as there is no demand. Scheduled receipts of 30 units arrived on Week 4. Hence, the on-hand inventory is 130 units on Week 4.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 50 units are required at the beginning of Week 5. Hence, they need to order for 50 units (as the lot size is lot-for-lot) on two weeks before (as the lead-time is 2 weeks), which means on Week 3.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Prepare a Material Requirement Plan (MRP) for Component D (2) and D (2):
- Component B (3) is the parent item of Component D (2) and Component C (2) is the parent item of Component D (2). As the number of Component D is 2, the planned order release of Component B should be multiplied with 2 to determine the gross requirement of Component D. The same should be followed for Component D (2) with its parent item C (2).
- On-hand inventory is 80 units. It remains same until Week 3, as there is no demand.
- Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.
- 20 units are required at the beginning of Week 3. Hence, they need to order for 40 units (as the lot size is multiples of 40) on previous week (as the lead-time is 1 week), which means on Week 2.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
- Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.
Want to see more full solutions like this?
Chapter 12 Solutions
Operations Management (Comp. Instructor's Edition)
Additional Business Textbook Solutions
Horngren's Accounting (12th Edition)
Principles of Microeconomics (MindTap Course List)
Principles Of Taxation For Business And Investment Planning 2020 Edition
Essentials of MIS (13th Edition)
Marketing: An Introduction (13th Edition)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
- Prepare a graph of the monthly forecasts and average forecast demand for Chicago Paint Corp., a manufacturer of specialized paint for artists. Compute the demand per day for each month (round your responses to one decimal place). Month B Production Days Demand Forecast Demand per Day January 21 950 February 19 1,150 March 21 1,150 April 20 1,250 May 23 1,200 June 22 1,000' July 20 1,350 August 21 1,250 September 21 1,050 October 21 1,050 November 21 December 225 950 19 850arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 2,300 January 1,500 May February 1,700 June 2,100 March April 1,700 1,700 July August 1,900 1,500 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August. The average monthly demand requirement = units. (Enter your response as a whole number.) In order to arrive at the costs, first compute the ending inventory and stockout units for each month by filling in the table below (enter your responses as whole numbers). Ending E Period…arrow_forwardMention four early warning indicators that a business may be at risk.arrow_forward
- 1. Define risk management and explain its importance in a small business. 2. Describe three types of risks commonly faced by entrepreneurs. 3. Explain the purpose of a risk register. 4. List and briefly describe four risk response strategies. (5 marks) (6 marks) (4 marks) (8 marks) 5. Explain how social media can pose a risk to small businesses. (5 marks) 6. Identify and describe any four hazard-based risks. (8 marks) 7. Mention four early warning indicators that a business may be at risk. (4 marks)arrow_forwardState whether each of the following statements is TRUE or FALSE. 1. Risk management involves identifying, analysing, and mitigating risks. 2. Hazard risks include interest rate fluctuations. 3. Entrepreneurs should avoid all forms of risks. 4. SWOT analysis is a tool for risk identification. 5. Scenario building helps visualise risk responses. 6. Risk appetite defines how much risk an organisation is willing to accept. 7. Diversification is a risk reduction strategy. 8. A risk management framework must align with business goals. 9. Political risk is only relevant in unstable countries. 10. All risks can be eliminated through insurance.arrow_forward9. A hazard-based risk includes A. Political instability B. Ergonomic issues C. Market demand D. Taxation changesarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning