![Operations Management (Comp. Instructor's Edition)](https://www.bartleby.com/isbn_cover_images/9781259948237/9781259948237_largeCoverImage.gif)
Concept explainers
Determine material requirements plans for pans N and V and subassembly I as described in Solved Problem 3 for each of the following:
a. Assume that there are currently 100 Ns on hand and scheduled receipts of 40 Is and 10 Vs at the beginning of week 3. No Es are on hand: 120 Es are needed at the start of week 5.
b. Assume on-hand and scheduled receipts as in part a. Now suppose that 100 Es are needed at the stmt of week 5 and 55 at the start of week 7. Also, use multiples of these order sizes: N, 800; V, 200. Use lot-for-lot ordering for I.
C. Using your answer to part b, update the MRP for V, using the following additional information for each of these cases: (1) one week has elapsed (making it the start of week 2), and (2) three weeks have elapsed (making it the start of week 4).
The updated master
a)
![Check Mark](/static/check-mark.png)
To prepare A Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which is used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 40 units of Component I and 10 units of Component C would arrive at the beginning of Week 3. 120 units of Component E are needed at the beginning of Week 5.
Product structure tree:
Prepare master schedule:
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Quantity | 120 |
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 120 units of End item E, which must be shipped at the start of week 5.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 120 units (120-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 120 units in the beginning of week 5. Hence, they need to order for 120 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 200 units on week 4 (240-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 200 units in the beginning of week 4. Hence, they need to order for 200 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 700 units on week 3 (800-100).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 10 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 190 units on week 3 (200-10).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 0 units. Calculation is as follows:
b)
![Check Mark](/static/check-mark.png)
To prepare A Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 40 units of Component I and 10 units of Component C would arrive at the beginning of week 3. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in the start of week 5 and 55 units of End item E in the start of week 7.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units in week 5 (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of Week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 540 units on week 3 (640-100).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 540 units in the beginning of week 3. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 10 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 150 units on week 3 (160-10).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 150 units in the beginning of week 3. Hence, they need to order for 200 units (as the lot size is multiples of 200) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
c)
1)
![Check Mark](/static/check-mark.png)
To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 800 units of Component N and 200 units of Component V would arrive at the beginning of week 3. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Week 1 has elapsed. Hence, plan has to be prepared from week 2 through week 9. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 5 (440-260).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 5. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 210 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 5 (110-50).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
1)
![Check Mark](/static/check-mark.png)
To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 800 units of Component N and 200 units of Component V would arrive at the beginning of week 3. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Week 1 has elapsed. Hence, plan has to be prepared from week 2 through week 9. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 5 (440-260).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 5. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 210 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 5 (110-50).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
2)
![Check Mark](/static/check-mark.png)
To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Two weeks (week 2 and week 3) has elapsed. Hence, plan has to be prepared from week 4 through week 11. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Planned order releases from 2nd and 3rd week should be used as scheduled receipt units. Scheduled receipt are 160 units of Component I at the start of 4th week, 800 units of Component N at the start of 5th week, and 200 units of Component V at the start of 5th week.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units at week 5 (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 40 units.
- Scheduled receipt is 160 units at the beginning of week 4.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units on week 6 (110-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 110 units in the beginning of week 6. Hence, they need to order for 110 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 260 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 7 (800-620).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 7. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 5 is 1,060 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 50 units.
- Scheduled receipt is 200 units at the beginning of week 5.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 7 (200-140).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 60 units in the beginning of week 7. Hence, they need to order for 200 units (as the lot size is multiples of 200) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
Want to see more full solutions like this?
Chapter 12 Solutions
Operations Management (Comp. Instructor's Edition)
Additional Business Textbook Solutions
Intermediate Accounting (2nd Edition)
Managerial Accounting (5th Edition)
Marketing: An Introduction (13th Edition)
Horngren's Accounting (12th Edition)
Essentials of MIS (13th Edition)
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
- Read Himachal Fertilizer Corporation (B) and critique the decision he actually made after reading Part B. Was your recommendation similar to what Neil did...how was it the same or how did it differ? Explain why with details from course materials and the case.arrow_forwardName the key stakeholders in the Himachal Fertilizer Corporation Part A case. Consider the stakeholder map in the image below. Which stakeholders would be the most important under your default lens?arrow_forwardThis crosstab shows product sub-category sales within categories, broken out by sales quarter. The quarterly values for each sub-category increase within each category, with the largest value at the bottom. Using Running Total as the calculation type, which scope and direction option gives this result?arrow_forward
- 6:35 nvas.liberty.edu < 72% i You must post before seeing replies. Edit history will be available to instructors. ☑ Due Feb 13 33 Replies (33) 50 points Discussion Thread: How to Look at the Bible After reading the assigned chapters in Everyday Bible Study (Chapters 1-5), create a learning log that lists 10 quotes from the assigned reading that highlight either a concept that resonated with you or a concept that represents new learning for you. Following each of these quotes, you must provide a 3-5 sentence explanation of how the selected quote represents either what resonated with you or this new learning. For an example of this type of thread, please see the provided example. Pleas ◄ Previous cussion Assignment instructions ✓ and the ||| Next ▸arrow_forwardDo a report to promote an innovative product/service within an organization of your choice. In your assignment, you need to focus on the below: 1. Give a brief introduction of the innovative product/service you are thinking about within an organization of your choice. 2. Analyze how you are going to promote your idea internally to your colleagues (e.g. meetings, presenting and disseminating the information). 3. Explain how you are going to convince them that this product/service is applicable and that it will create a competitive advantage in the market. 4. Refer to a similar product/service that your competitors have and analyze how the competitors’ product can be considered as a threat to your new product/service. 5. Estimate how much will the whole procedure cost to the business. 6. In your conclusions, describe how the new product/service will influence the whole organization’s environment. 3000 words and include and introducion, conclusion and references.arrow_forwardFor my learning and not a assignment question: Tesla, the U.S. electric vehicle manufacturer, has recently proposed to join Indonesia’s initiative to develop an EV battery supply chain within the country. This information was shared by a senior Indonesian government official, who noted that the government received Tesla's proposal on Thursday. Indonesia, known for its rich nickel reserves, is already in discussions with companies like China's Contemporary Amperex Technology (CATL) and South Korea's LG Chem to establish a comprehensive EV battery supply chain that covers everything from raw materials to the final product. Sepian Hari Seto, the deputy for investment and mining at the Coordinating Ministry of Maritime Affairs and Investment, expressed enthusiasm for Tesla's advanced lithium battery technology. He conveyed that the collaboration with Tesla, along with CATL and LG, presents a valuable opportunity for technology transfer and learning. Furthermore, Seto mentioned the…arrow_forward
- Your company is considering investing in a Human Resource Information System (HRIS).Briefly explain the strategies for justifying HRIS investments.arrow_forwardPresent the criteria you would utilize to determine if a right should be extended to an employee or if it would unnecessarily impact a manager’s ability to manage. Additionally, assess how you would balance the need for management rights against the need for employee rights, and how greater employee rights positively and negatively affect the future of the organization.arrow_forwardprovide schoarly research and references as to how internal and exteral audit is a risk management strategy to mitigate risk in a financial institutionarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)